Justia Construction Law Opinion Summaries
Travelers Cas. Ins. Co. of America v. Williams Co. Construction
In Spring 2008, Williams Company Construction, Inc. entered into a construction contract to remodel the Friendly Smiles Cosmetic Dentistry Office owned by Dr. Brenda Barfield. Dr. Barfield previously leased the building from Williams Company owner Glen Williams for approximately five years before she purchased the property from him in 2008. Dr. Barfield hired Williams to remodel the building because of its construction experience and familiarity and knowledge of the building. When Dr. Barfield hired Williams, she did not know whether the remodeling work would be done by Williams or subcontractors. Dr. Barfield did not deal directly with any subcontractors during the remodeling project nor did she direct Williams to hire any specific subcontractors. During the remodel, Williams served as the general contractor and hired subcontractors to do various construction tasks. In December 2008, a section of a copper water pipe froze and burst. The frozen water pipe caused minor water damage and was repaired by plumbing subcontractor Home Heating. During the repair process, a Home Heating employee cut a hole in the wall to locate the leak and discovered that the air in the plumbing wall was cold. The employee was concerned the pipe could freeze again and notified the Friendly Smiles Cosmetic Dentistry Office about the cold air. Dr. Barfield contacted Williams to express her concern about the pipes re-freezing from the cold air. According to testimony, Williams told Dr. Barfield not to worry about the pipes freezing again because of circulating warm air around the hole. Dr. Barfield also wanted the hole in the wall patched, but had difficulty in securing Williams or Home Heating to fix it. Dr. Barfield made repeated requests for Williams or Home Heating to resolve the cold air issue, but they did not fix the problem. Approximately one week after the pipe was fixed, the water pipe froze and broke again, this time causing extensive water damage to the dental office. Dr. Barfield and her insurance company, Travelers Insurance, brought suit against Williams, Home Heating (and other subcontractors) for negligence, and breach of contract. Before trial, the parties stipulated that the total amount of damages was $220,046.09. Williams requested the trial court to include a jury instruction concerning the independent contractor distinction (C-55.25), and a jury instruction pertaining to the failure of a party to produce witnesses (C-80.30). The court denied the two requests. At the pretrial hearing, the parties stipulated that the case would be tried before the jury based on comparative fault. The jury was given a special verdict form and found Williams seventy percent at fault, Home Heating twenty-five percent at fault, and Dr. Barfield five percent at fault. Judgment was entered against Williams. Williams subsequently filed a motion for a new trial arguing the court erred in denying its requested jury instructions and there was insufficient evidence for the jury to find Williams seventy percent at fault for the damages. Following a hearing, the district court denied the motion. Williams appealed the district court's judgment, but finding no reversible error, the Supreme Court affirmed.
View "Travelers Cas. Ins. Co. of America v. Williams Co. Construction" on Justia Law
Kellogg Brown & Root Servs. v. United States
In 2001 KBR agreed to provide the Army with logistics support services during Operation Iraqi Freedom. Individual task orders required KBR to install, operate and maintain dining services near Mosul, Iraq on a cost-plus-award-fee basis. KBR selected ABC, a subcontractor, to build a prefabricated metal dining facility and to provide dining services for a camp population of 2,573. In June 2004, the Army ordered KBR to stop construction of the metal facility and begin construction of a reinforced concrete facility for an estimated 2,573 to 6,200+ persons. Instead of requesting bids for the new work, KBR kept ABC as the subcontractor due to the urgency of the request. ABC submitted a new proposal with a total monthly cost about triple the monthly cost initially quoted. ABC attributed the increased costs to additional labor and equipment to serve a larger population and to a drastic increase in the cost of labor and a severe shortage of staff willing to work in Iraq. Due to a calculation error, it was determined that ABC’s proposal was reasonable. KBR’s management reviewed and approved a change order, embodying ABC’s proposal. In 2005 the subcontract ended and title to the dining facility passed to the Army. In 2007, the Defense Contract Auditing Agency suspended payment of certain costs paid by KBR to ABC pursuant to the change order. KBR prepared a new price justification for the concrete dining facility and ultimately filed suit, seeking recovery of the $12,529,504 in costs disapproved for reimbursement. The Claims Court awarded $6,779,762. The Federal Circuit affirmed.View "Kellogg Brown & Root Servs. v. United States" on Justia Law
Hughes Gen. Contractors, Inc. v. Utah Labor Comm’n
The Utah Occupational Safety and Health Division (UOSH) cited and fined Hughes General Contractors, which oversaw a construction project involving over 100 subcontractors, for a subcontractor’s violation on the project. In determining that Hughes was responsible for safety conditions for the subcontractor’s employees, the UOSH invoked the multi-employer worksite doctrine, which makes a general contractor responsible for the occupational safety of all workers on a worksite, including those who are not the contractor’s employees. Both an administrative law judge and the Labor Commission’s Appeals Board upheld the citation and the multi-employer worksite doctrine, which federal OSHA regulations have adopted and federal courts have upheld. The Supreme Court reversed the citation and penalty, holding (1) the multi-employer worksite doctrine is incompatible with the governing Utah statute, Utah Code 34A-6-201(1; (2) the responsibility for ensuring occupational safety under the governing statute is limited to an employer’s responsibility to its employees; and (3) because Hughes was not an employer of the workers in question in this case, Hughes was improperly cited and sanctioned.View "Hughes Gen. Contractors, Inc. v. Utah Labor Comm’n" on Justia Law
Star Equip., Ltd. v. State
The Iowa Department of Transportation (IDOT) hired a general contractor, which was a “targeted small business” (TSB), for two public construction contracts. The general contractor subcontracted with three subcontractors, which the general contractor failed to pay in full. The subcontractors sued IDOT and the general contractor. The district court granted IDOT’s motion to dismiss and entered default judgments against the general contractor, ruling that, in absence of a bond, the subcontractors’ remedy against the state was limited to the funds IDOT retained on its contract with the general contractor. The subcontractors appealed, arguing that Iowa Code 573.2, the statute that governs subcontractors’ remedies for unpaid work on public improvements when the state waives the performance bond for a general contractor that is a TSB, allowed broader recovery rights and required IDOT to step into the TSB’s shoes to pay the balances owed them. The Supreme Court reversed, holding that section 573.2 operates as a waiver of sovereign immunity that allows subcontractors to recover from IDOT the unpaid balances TSBs owe for work on public improvements. Remanded.View "Star Equip., Ltd. v. State" on Justia Law
Posted in:
Constitutional Law, Construction Law
NJ Carpenters v. Tishman Constr. Corp. of NJ
The New Jersey Prevailing Wage Act, N.J. Stat. 34:11-56.25 (PWA) provides that laborers on certain public works projects are to be paid the prevailing wage. Carpenters hired to work on the Revel Casino Project in Atlantic City claimed that the Revel Casino Project is a “public work” within the meaning of the PWA because it received financial assistance in the form of incentives, tax exemptions, and tax reimbursements from the New Jersey Economic Development Authority (EDA), which, they argued is a “public body” within the meaning of the Act. They assigned their claims for unpaid prevailing wages to the plaintiffs, employee benefit plans within the meaning of the Employee Retirement Income Security Act (ERISA), 29 U.S.C. 1001, and trust funds within the meaning of the Labor Management Relations Act (LMRA), 29 U.S.C. 141. The district court held that the claims were completely preempted under ERISA section 502(a). Although it did not directly address LMRA complete preemption, the court also noted that the complaint “seeks interpretation of the collective bargaining agreement.” The Third Circuit vacated and remanded with instructions to remand to state court, holding that neither statute completely preempts the PWA. View "NJ Carpenters v. Tishman Constr. Corp. of NJ" on Justia Law
JEM Contracting, Inc. v. Morrison-Maierle, Inc.
Morrison-Maierle, Inc. (MMI) was hired by two counties to provide engineering services and supervision on a road improvement contract. The counties retained JEM Contracting, Inc. (JEM) to provide the construction services on the project. JEM filed suit against MMI alleging detrimental reliance and fraudulent inducement for promises MMI allegedly made during the job that JEM would be paid for unanticipated costs incurred during pulverization of the old road. The district court granted summary judgment for MMI, concluding that JEM could not prove it had been harmed by MMI’s alleged representations. The Supreme Court affirmed, holding that the district court did not err by (1) concluding that JEM was required to continue performance pending approval of a change order under a certain contract provision, as the provision was not void as against public policy; and (2) granting summary judgment to MMI on the ground that JEM failed to show it was harmed by the representations made by MMI.
View "JEM Contracting, Inc. v. Morrison-Maierle, Inc." on Justia Law
Posted in:
Construction Law, Contracts
Golden State v. Eastern Municipal Water Dist.
The Eastern Municipal Water District (EMWD) hired general contractor S.J. and Burkhardt, Inc. (SJB) for a public works construction project in 2006. Safeco Insurance Company (Safeco) executed performance and payment bonds for the project. Plaintiff Golden State Boring & Pipe Jacking, Inc. (GSB) was a subcontractor for the project, completing its work by September 2006, but it did not receive payment. In March 2008, SJB sent a voluntary default letter to Safeco. In July 2008, GSB sued SJB, EMWD, and Safeco for the unpaid amounts under the contract, separately seeking payment from Safeco under its payment bond. EMWD filed a cross-complaint to interplead retained sums. Safeco made a motion for summary judgment on the cause of action for payment under the bond on the ground that GSB’s claim was untimely. The trial court granted the motion, finding that there had been three cessations of labor that triggered GSB’s duty to file a stop notice in order to secure payment under Safeco's payment bond. At a subsequent court trial on the contract claims, GSB was awarded judgment against SJB, and Safeco was awarded judgment on the interpleader action. GSB appealed the summary judgment ruling, arguing: (1) the trial court erroneously overruled its objections to evidentiary matters presented in support of Safeco’s summary judgment; and (2) the court erred in finding the action was untimely. Finding no reversible error, the Court of Appeal affirmed.
View "Golden State v. Eastern Municipal Water Dist." on Justia Law
Shafer Electric & Construction v. Mantia
In August, 2010, Appellants, Washington County residents Raymond and Donna Mantia, hired Appellee, West Virginia contractor Shafer Electric & Construction, to build a 34 foot by 24 foot, two-car garage addition onto their house. The proposals for the garage did not comply with several requirements of Section 517.7 of the Home Improvement Consumer Protection Act. Specifically, any home improvement contract, in order to be valid and enforceable against the owner of real property, had to be legible, in writing, and contain thirteen other specific requirements. Despite the detail in the specifications for the work to be completed, the contract here only complied with subsections (5), (7), and (8) of Section 517.7(a). Notwithstanding these deficiencies, work on the project began in October, 2010, when Appellants, who owned their own excavation business, began the foundation excavation. When Appellee commenced construction of the addition, it contended that problems surfaced because of Appellants' failure to complete the excavation work properly. During the subsequent months, Appellants eventually reexcavated the foundation area for the addition and, in the process (according to Appellee), changed the design of the addition several times. Negotiations into these design changes and other necessary alterations as a result of the excavation problems occurred, but ultimately failed when Appellants apparently refused to enter into a new contract with Appellee. Upon the breakdown of the negotiations, the parties mutually agreed that Appellee would invoice Appellants for the work completed, and that Appellee would discontinue efforts on the project. Appellants refused to pay the bill. Appellee responded by filing a mechanic's lien in the Washington County Court of Common Pleas. When Appellants still had failed to satisfy the outstanding balance, Appellee filed a civil action in the common pleas court, alleging both breach of contract and quantum meruit causes of action. The Supreme Court granted allowance of appeal in this matter to determine whether the Act barred a contractor from recovery under a theory of quantum meruit in the absence of a valid and enforceable home improvement contract as defined by the Act. The Superior Court held that the Act did not bar a cause of action sounding in quantum meruit and, for slightly different reasons, the Supreme Court affirmed.
View "Shafer Electric & Construction v. Mantia" on Justia Law
Gillespie Cmty. Unit Sch. Dist. No. 7 v. Wight & Co.
In 1998 the Gillespie School District hired Wight under for services preliminary to the actual designing and construction of a new elementary school building. Wight agreed to perform a “site mine investigation.” Wight hired Hanson Engineers to assess the potential for coal mine subsidence. A physical engineer at Hanson sent a letter to Wight, noting recorded subsidence events, including five to six events since 1979, affecting more than 40 structures in the area. The letter stated: “No one can predict when or if the land above the roof-and-pillar mine will subside… The owner should consider the fact that there is no economically feasible corrective action… to guarantee against future subsidence… it can be intuitively concluded that there is a relatively high risk of subsidence in the Benld/Gillespie area. The letter was not attached to the report, which noted some of its highlights. The school was built and occupied, but in 2009 was severely damaged as the result of subsidence and was condemned. The District sued Wight, alleging professional negligence, breach of implied warranty, and fraudulent misrepresentation by concealment of material fact. The court entered summary judgment in favor of Wight, based on statutes of limitations applicable to the claims. The appellate court affirmed. The Illinois Supreme Court affirmed, noting that it was expressing no opinion concerning the merits of various claims.View "Gillespie Cmty. Unit Sch. Dist. No. 7 v. Wight & Co." on Justia Law
The Cote Corp. v. Kelley Earthworks, Inc.
The Cote Corporation filed a mechanic’s lien against real property owned by Kelley Earthworks, Inc. Cote subsequently brought a complaint to enforce the lien against Kelley. Kelley did not respond to the complaint or to Cote’s motion for summary judgment. The superior court entered Kelley’s default and then entered judgment for Cote, plus interest and attorney fees, and ordered that the property be sold to satisfy the judgment. Kelley appeared ten days after the judgment was entered on the docket and filed motions to set aside its default and for relief from the judgment. The court declined to set aside the default but did strike its order to sell the real property, instead awarding Cote a money judgment. The Supreme Court vacated the judgment, holding that the court erred in striking the provision of its order requiring a sale of the property. Remanded for entry of an order for the sale of at least a portion of Kelley’s land. View "The Cote Corp. v. Kelley Earthworks, Inc." on Justia Law
Posted in:
Construction Law, Real Estate & Property Law