Justia Construction Law Opinion Summaries
DTJ Design, Inc. v. First Republic Bank
Downing, Thorpe & James Design, Inc. (DTJ) was an architectural firm incorporated in Colorado. Thomas Thrope, one of DTJ’s three founding principals, was allowed to practice individually as a foreign architect in Nevada, but DTJ was not allowed to practice as a foreign corporation in Nevada. In 2004, DTJ contracted with a Nevada developer to provide architectural services for a Las Vegas subdivision owned by Prima Condominiums, LLC (Prima). Prima obtained a loan from First Republic Bank in exchange for a promissory note secured by a deed of trust on one of the subdivision’s units. After Prima defaulted on its payments, DTJ recorded a notice of mechanic’s lien against the property for unpaid services. First Republic then foreclosed and purchased the property. DTJ subsequently brought an action against First Republic for lien priority and unjust enrichment. The district court granted summary judgment for First Republic. The Supreme Court affirmed, holding (1) because DTJ had failed to comply with Nevada’s statutory registration and filing provisions, it was barred from maintaining an action in Nevada for compensation for its architectural services; and (2) Thorpe’s individual status had no bearing on whether DTJ could bring or maintain an action for compensation for its services.View "DTJ Design, Inc. v. First Republic Bank" on Justia Law
Metcalf Const. Co., LLC v. United States
In 2002, the Navy awarded Metcalf a contract to design and build 212 housing units in Hawaii by October, 2006, for $50 million. Problems arose involving soil conditions. The request for proposals stated that the “soil reconnaissance report” was “for preliminary information only” and required that the contractor conduct independent soil investigation, incorporating 48 C.F.R. 52.236-2, concerning site conditions that differ materially from those disclosed. Discussions delayed construction for a year. Metcalf implemented its preferred changes by over-excavating and using non-expansive fill, without a contract modification. The Navy denied that there was any material difference between pre-bid and post-award soil assessments, but approved some modifications. Metcalf was about 200 days behind schedule and began using “post-tension” concrete, which was more expensive but avoided the additional time and cost of over-excavation. The Navy amended the contract to approve use of post-tension concrete slabs. Metcalf claims additional delays resulting from the presence of more of a chemical contaminant than was expected. With respect to contamination, the Navy granted a 286-day extension and reimbursed $1,493,103. The Navy accepted the buildings in March, 2007. Metcalf alleged that its final cost was $76 million. The government paid less than $50 million. The Claims Court ruled in favor of the government, under the Contract Disputes Act, 41 U.S.C. 7104. The Federal Circuit vacated, holding that the court misconstrued what Metcalf needed to show to prove that the government breached its duty of good faith and fair dealing and misinterpreted certain contractual provisions.View "Metcalf Const. Co., LLC v. United States" on Justia Law
Intervest Constr. of Jax, Inc. v Gen. Fidelity Ins. Co.
ICI Homes, Inc. (ICI) had a general liability insurance policy with General Fidelity Insurance Company. In 2007, Katherine Ferrin, the owner of a residence constructed by ICI, was injured while using stairs installed by Custom Cutting, Inc. Ferrin filed suit against ICI. ICI, in turn, sought indemnification from Custom Cutting. The parties agreed to a $1.6 million settlement of Ferrin’s claim. ICI accepted $1 million from Custom Cutting’s insurer to settle its indemnification claim, which it paid to Ferrin. ICI and General Fidelity then claimed the other was responsible for paying Ferrin the remaining $600,000. Both parties paid $300,000 to Ferrin to settle Ferrin’s claim. ICI then filed suit against General Fidelity seeking return of the $300,000 ICI paid above the $1 million indemnification payment. General Fidelity counterclaimed seeking return of the $300,000 it had paid to Ferrin. The district court entered judgment for General Fidelity. The court of appeals certified two questions to the Supreme Court for resolution. The Supreme Court answered (1) the General Fidelity policy allowed ICI to apply indemnification payments received from Custom Cutting’s insurer towards satisfaction of its $1 million self-insured retention; and (2) the transfer of rights provision in the policy did not abrogate the made whole doctrine.View "Intervest Constr. of Jax, Inc. v Gen. Fidelity Ins. Co." on Justia Law
Travelers Cas. Ins. Co. of America v. Williams Co. Construction
In Spring 2008, Williams Company Construction, Inc. entered into a construction contract to remodel the Friendly Smiles Cosmetic Dentistry Office owned by Dr. Brenda Barfield. Dr. Barfield previously leased the building from Williams Company owner Glen Williams for approximately five years before she purchased the property from him in 2008. Dr. Barfield hired Williams to remodel the building because of its construction experience and familiarity and knowledge of the building. When Dr. Barfield hired Williams, she did not know whether the remodeling work would be done by Williams or subcontractors. Dr. Barfield did not deal directly with any subcontractors during the remodeling project nor did she direct Williams to hire any specific subcontractors. During the remodel, Williams served as the general contractor and hired subcontractors to do various construction tasks. In December 2008, a section of a copper water pipe froze and burst. The frozen water pipe caused minor water damage and was repaired by plumbing subcontractor Home Heating. During the repair process, a Home Heating employee cut a hole in the wall to locate the leak and discovered that the air in the plumbing wall was cold. The employee was concerned the pipe could freeze again and notified the Friendly Smiles Cosmetic Dentistry Office about the cold air. Dr. Barfield contacted Williams to express her concern about the pipes re-freezing from the cold air. According to testimony, Williams told Dr. Barfield not to worry about the pipes freezing again because of circulating warm air around the hole. Dr. Barfield also wanted the hole in the wall patched, but had difficulty in securing Williams or Home Heating to fix it. Dr. Barfield made repeated requests for Williams or Home Heating to resolve the cold air issue, but they did not fix the problem. Approximately one week after the pipe was fixed, the water pipe froze and broke again, this time causing extensive water damage to the dental office. Dr. Barfield and her insurance company, Travelers Insurance, brought suit against Williams, Home Heating (and other subcontractors) for negligence, and breach of contract. Before trial, the parties stipulated that the total amount of damages was $220,046.09. Williams requested the trial court to include a jury instruction concerning the independent contractor distinction (C-55.25), and a jury instruction pertaining to the failure of a party to produce witnesses (C-80.30). The court denied the two requests. At the pretrial hearing, the parties stipulated that the case would be tried before the jury based on comparative fault. The jury was given a special verdict form and found Williams seventy percent at fault, Home Heating twenty-five percent at fault, and Dr. Barfield five percent at fault. Judgment was entered against Williams. Williams subsequently filed a motion for a new trial arguing the court erred in denying its requested jury instructions and there was insufficient evidence for the jury to find Williams seventy percent at fault for the damages. Following a hearing, the district court denied the motion. Williams appealed the district court's judgment, but finding no reversible error, the Supreme Court affirmed.
View "Travelers Cas. Ins. Co. of America v. Williams Co. Construction" on Justia Law
Kellogg Brown & Root Servs. v. United States
In 2001 KBR agreed to provide the Army with logistics support services during Operation Iraqi Freedom. Individual task orders required KBR to install, operate and maintain dining services near Mosul, Iraq on a cost-plus-award-fee basis. KBR selected ABC, a subcontractor, to build a prefabricated metal dining facility and to provide dining services for a camp population of 2,573. In June 2004, the Army ordered KBR to stop construction of the metal facility and begin construction of a reinforced concrete facility for an estimated 2,573 to 6,200+ persons. Instead of requesting bids for the new work, KBR kept ABC as the subcontractor due to the urgency of the request. ABC submitted a new proposal with a total monthly cost about triple the monthly cost initially quoted. ABC attributed the increased costs to additional labor and equipment to serve a larger population and to a drastic increase in the cost of labor and a severe shortage of staff willing to work in Iraq. Due to a calculation error, it was determined that ABC’s proposal was reasonable. KBR’s management reviewed and approved a change order, embodying ABC’s proposal. In 2005 the subcontract ended and title to the dining facility passed to the Army. In 2007, the Defense Contract Auditing Agency suspended payment of certain costs paid by KBR to ABC pursuant to the change order. KBR prepared a new price justification for the concrete dining facility and ultimately filed suit, seeking recovery of the $12,529,504 in costs disapproved for reimbursement. The Claims Court awarded $6,779,762. The Federal Circuit affirmed.View "Kellogg Brown & Root Servs. v. United States" on Justia Law
Hughes Gen. Contractors, Inc. v. Utah Labor Comm’n
The Utah Occupational Safety and Health Division (UOSH) cited and fined Hughes General Contractors, which oversaw a construction project involving over 100 subcontractors, for a subcontractor’s violation on the project. In determining that Hughes was responsible for safety conditions for the subcontractor’s employees, the UOSH invoked the multi-employer worksite doctrine, which makes a general contractor responsible for the occupational safety of all workers on a worksite, including those who are not the contractor’s employees. Both an administrative law judge and the Labor Commission’s Appeals Board upheld the citation and the multi-employer worksite doctrine, which federal OSHA regulations have adopted and federal courts have upheld. The Supreme Court reversed the citation and penalty, holding (1) the multi-employer worksite doctrine is incompatible with the governing Utah statute, Utah Code 34A-6-201(1; (2) the responsibility for ensuring occupational safety under the governing statute is limited to an employer’s responsibility to its employees; and (3) because Hughes was not an employer of the workers in question in this case, Hughes was improperly cited and sanctioned.View "Hughes Gen. Contractors, Inc. v. Utah Labor Comm’n" on Justia Law
Star Equip., Ltd. v. State
The Iowa Department of Transportation (IDOT) hired a general contractor, which was a “targeted small business” (TSB), for two public construction contracts. The general contractor subcontracted with three subcontractors, which the general contractor failed to pay in full. The subcontractors sued IDOT and the general contractor. The district court granted IDOT’s motion to dismiss and entered default judgments against the general contractor, ruling that, in absence of a bond, the subcontractors’ remedy against the state was limited to the funds IDOT retained on its contract with the general contractor. The subcontractors appealed, arguing that Iowa Code 573.2, the statute that governs subcontractors’ remedies for unpaid work on public improvements when the state waives the performance bond for a general contractor that is a TSB, allowed broader recovery rights and required IDOT to step into the TSB’s shoes to pay the balances owed them. The Supreme Court reversed, holding that section 573.2 operates as a waiver of sovereign immunity that allows subcontractors to recover from IDOT the unpaid balances TSBs owe for work on public improvements. Remanded.View "Star Equip., Ltd. v. State" on Justia Law
Posted in:
Constitutional Law, Construction Law
NJ Carpenters v. Tishman Constr. Corp. of NJ
The New Jersey Prevailing Wage Act, N.J. Stat. 34:11-56.25 (PWA) provides that laborers on certain public works projects are to be paid the prevailing wage. Carpenters hired to work on the Revel Casino Project in Atlantic City claimed that the Revel Casino Project is a “public work” within the meaning of the PWA because it received financial assistance in the form of incentives, tax exemptions, and tax reimbursements from the New Jersey Economic Development Authority (EDA), which, they argued is a “public body” within the meaning of the Act. They assigned their claims for unpaid prevailing wages to the plaintiffs, employee benefit plans within the meaning of the Employee Retirement Income Security Act (ERISA), 29 U.S.C. 1001, and trust funds within the meaning of the Labor Management Relations Act (LMRA), 29 U.S.C. 141. The district court held that the claims were completely preempted under ERISA section 502(a). Although it did not directly address LMRA complete preemption, the court also noted that the complaint “seeks interpretation of the collective bargaining agreement.” The Third Circuit vacated and remanded with instructions to remand to state court, holding that neither statute completely preempts the PWA. View "NJ Carpenters v. Tishman Constr. Corp. of NJ" on Justia Law
JEM Contracting, Inc. v. Morrison-Maierle, Inc.
Morrison-Maierle, Inc. (MMI) was hired by two counties to provide engineering services and supervision on a road improvement contract. The counties retained JEM Contracting, Inc. (JEM) to provide the construction services on the project. JEM filed suit against MMI alleging detrimental reliance and fraudulent inducement for promises MMI allegedly made during the job that JEM would be paid for unanticipated costs incurred during pulverization of the old road. The district court granted summary judgment for MMI, concluding that JEM could not prove it had been harmed by MMI’s alleged representations. The Supreme Court affirmed, holding that the district court did not err by (1) concluding that JEM was required to continue performance pending approval of a change order under a certain contract provision, as the provision was not void as against public policy; and (2) granting summary judgment to MMI on the ground that JEM failed to show it was harmed by the representations made by MMI.
View "JEM Contracting, Inc. v. Morrison-Maierle, Inc." on Justia Law
Posted in:
Construction Law, Contracts
Golden State v. Eastern Municipal Water Dist.
The Eastern Municipal Water District (EMWD) hired general contractor S.J. and Burkhardt, Inc. (SJB) for a public works construction project in 2006. Safeco Insurance Company (Safeco) executed performance and payment bonds for the project. Plaintiff Golden State Boring & Pipe Jacking, Inc. (GSB) was a subcontractor for the project, completing its work by September 2006, but it did not receive payment. In March 2008, SJB sent a voluntary default letter to Safeco. In July 2008, GSB sued SJB, EMWD, and Safeco for the unpaid amounts under the contract, separately seeking payment from Safeco under its payment bond. EMWD filed a cross-complaint to interplead retained sums. Safeco made a motion for summary judgment on the cause of action for payment under the bond on the ground that GSB’s claim was untimely. The trial court granted the motion, finding that there had been three cessations of labor that triggered GSB’s duty to file a stop notice in order to secure payment under Safeco's payment bond. At a subsequent court trial on the contract claims, GSB was awarded judgment against SJB, and Safeco was awarded judgment on the interpleader action. GSB appealed the summary judgment ruling, arguing: (1) the trial court erroneously overruled its objections to evidentiary matters presented in support of Safeco’s summary judgment; and (2) the court erred in finding the action was untimely. Finding no reversible error, the Court of Appeal affirmed.
View "Golden State v. Eastern Municipal Water Dist." on Justia Law