Justia Construction Law Opinion Summaries
Liu v. Christopher Homes, LLC
The developer (“Developer”) of a residential community hired a general contractor (“Contractor”) to construct homes in the community, and Contractor subcontracted with Subcontractor for construction services. Subcontractor performed services on several homes, including Appellant’s. Because Subcontractor was not fully paid, it recorded liens on properties within the community, including Appellant’s. Subcontractor filed a civil action against Developer, Contractor, Appellant, and other homeowners, seeking to foreclose on its liens. Appellant filed a cross-claim against Developer and Contractor for breach of contract and seeking to recover attorney fees as damages. The district court denied Appellant’s request to recover attorney fees, concluding that, under the standard set forth in Horgan v. Felton regarding the recovery of attorney fees in cloud-on-title cases, because the breach of contract in this case related to title of real property, and because Appellant failed to allege and prove slander of title, she could not recover the attorney fees that she sought as special damages. The Supreme Court reversed the district court’s judgment to the extent that it denied Appellant’s request for special damages, holding that Horgan did not apply to preclude such recovery in this case. View "Liu v. Christopher Homes, LLC" on Justia Law
Chabad Lubavitch of Litchfield v. Litchfield Historic District Commission
Chabad and Rabbi Joseph Eisenbach filed suit against defendants, alleging that defendants violated their rights by denying an application to expand an existing property to accommodate Chabad's religious mission. Chabad filed suit under 42 U.S.C. 1983, 1985, and 1986; the Religious Land Use and Institutionalized Persons Act (RLUIPA), 42 U.S.C. 2000cc et seq.; and Connecticut state law, seeking damages, injunctive and declaratory relief, attorneys' fees, and the appointment of a federal monitor. The court concluded that the district court erred in dismissing Rabbi Eisenbach's RLUIPA claims for lack of standing; vacated the district court's ruling insofar as it concerned the Rabbi and remanded for consideration, instead, whether the Rabbi failed to state a claim under RLUIPA; affirmed the remainder of the judgment due to the Rabbi's failure to brief his remaining claims; concluded that the HDC's review of the Chabad's application was an "individual assessment" subject to RLUIPA's substantial burden provision and that the Chabad need not cite an "identical" comparator to establish a claim under RLUIPA's nondiscrimination provision; vacated the district court's judgment insofar as it concerned these RLUIPA claims and remanded for consideration whether these claims survive summary judgment; and affirmed the remainder of the district court's February 2012 judgment largely due to the Chabad's failure to brief most of its remaining claims. View "Chabad Lubavitch of Litchfield v. Litchfield Historic District Commission" on Justia Law
State Ctr., LLC v. Lexington Charles Ltd. P’ship
At issue in this case was the State Center Project, a $1.5 billion redevelopment project intended to revitalize property owned by the State in Baltimore. In 2005, the State issued a public request for qualifications to solicit a master developer for the project. The State Center, LLC was chosen as the master developer. The Maryland Department of General Services (“DGS”), the Maryland Department of Transportation (“MDOT”) and the State Center, LLC negotiated for the Project, entering a series of agreements between 2007 and 2010 to complete the Project in a timely manner. In 2010, Plaintiffs, property owners in downtown Baltimore and taxpayers, filed suit against the DGS, MDOT, and the State Center and its subsidiaries, seeking a declaratory judgment that the formative contracts for the Project were void and seeking an injunction to halt the Project. The trial court voided the formative contracts, concluding that they violated the State Procurement Law. The Court of Appeals vacated the judgment of the circuit court and remanded with directions to dismiss Plaintiffs’ complaint with prejudice, holding that Plaintiffs’ claims were barred by the doctrine of laches due to an unreasonable delay in bringing their claims, causing prejudice to the defendants.View "State Ctr., LLC v. Lexington Charles Ltd. P’ship" on Justia Law
Gaytan v. Wal-Mart
Jose Dominguez was working for D & BR Building Systems, Inc. (D&BR) on the roof of a building being constructed for Wal-Mart Stores, Inc. when he was killed in an accident. D&BR had subcontracted with with Graham Construction, Inc. (Graham), the general contractor on the project, to install the steelwork necessary for the building. Guadalupe Gaytan, the special administrator of Dominguez’s estate, brought this negligence action against Wal-Mart and Graham. The district court granted summary judgment for Wal-Mart and Graham. The Supreme Court affirmed in part and reversed in part, holding (1) summary judgment was properly granted to Wal-Mart, as no genuine issues of material fact existed as to any of Gaytan’s claims against Wal-Mart; and (2) there were genuine issues of material fact with respect to Gaytan’s direct negligence claim against Graham arising from Graham’s alleged retention of control over the use of safety equipment on the roof. Remanded. View "Gaytan v. Wal-Mart" on Justia Law
Posted in:
Construction Law, Injury Law
White v. Valley County
A certified question of law from the U.S. District Court for the District of Idaho was presented to the Idaho Supreme Court. Karen White and her development company, Elkhorn, LLC, sought to recover $166,496 paid to Valley County for "capital investments for roads in the vicinity of [their] White Cloud development." Phase I of White Cloud was completed and it was undisputed by the parties that the tax monies paid for Phase I were used by the County to complete capital investments for roads in the vicinity of the White Cloud development. The County conceded that it did not adopt an impact fee ordinance or administrative procedures for the impact fee process as required by the Idaho Development Impact Fees Act (IDIFA). The County also conceded it did not enact an IDIFA-compliant ordinance, because, at the time, the County believed in good faith that none was required. Plaintiff filed suit against the County claiming that the road development fee imposed by the County as a condition for approval of the White Cloud project violated Idaho state law and deprived Plaintiff of due process under both the federal and Idaho constitutions. In her Second Amended Complaint, Plaintiff raised two claims for relief. The first claim for relief alleged that “Valley County’s practice of requiring developers to enter into a Road Development Agreement ("RDA," or any similar written agreement) solely for the purpose of forcing developers to pay money for its proportionate share of road improvement costs attributable to traffic generated by their development is a disguised impact fee, is illegal and therefore should be enjoined." The first claim for relief also alleged that, because the County failed to enact an impact fee ordinance under IDIFA, the imposition of the road development fees constituted an unauthorized tax. Plaintiff’s second claim for relief alleged that the County’s imposition of the road development fee constituted a taking under the federal and Idaho constitutions. The County argued Plaintiff voluntarily agreed to pay the RDA monies. Plaintiff denies that the payment was voluntary since it was required to obtain the final plat approval. The issue the federal district court presented to the Idaho Supreme Court centered on when the limitations period commences for statutory remedies made available under Idaho law to obtain a refund of an illegal county tax. The Court answered that the limitations period for statutory remedies made available under Idaho law to obtain a refund of an illegal county tax commences upon payment of the tax.
View "White v. Valley County" on Justia Law
Redondo Constr. Corp. v. Izquierdo
In 1999, Redondo Construction Corporation pled guilty to aiding and abetting the making of false statements during its work on a federal highway project. The Puerto Rico Highway and Transportation Authority (“PRHTA”) and the Puerto Rico Public Guildings Authority (“PBA”) subsequently revoked the bids it had awarded Redondo before the plea and suspended Redondo from bidding on new contracts. Redondo challenged both decisions, which resulted in settlement agreements with both agencies allowing Redondo to resume bidding for contracts. After Puerto Rico passed Law 458, which prohibited Puerto Rico agencies from awarding contracts corporations convicted of offenses involving public funds, the PBA cancelled several of Redondo’s bids and the contract it had executed with Redondo, and the PRHTA withdrew from its settlement with Redondo. Redondo sued PRHTA, PBA, and several officials at both agencies, alleging that Defendants were in breach of the settlement agreements, that this caused Redondo’s bankruptcy, and that Defendants were liable in damages. The district court granted the PRHTA’s and the individual defendants’ motions for summary judgment and sua sponte dismissed Redondo’s claims against the PBA. The First Circuit Court of Appeals (1) affirmed the entry of summary judgment as to the PRHTA and the individual defendants, as Redondo had no record of evidence of damages against these defendants; but (2) vacated the dismissal of the claim against the PBA, as the court did not meet the necessary conditions for entering judgment sua sponte.View "Redondo Constr. Corp. v. Izquierdo" on Justia Law
Edged In Stone v. NW Power Systems
Appellant Edged in Stone, Inc. (EIS) sought damages for breach of contract, breach of warranty, breach of implied covenant of good faith and fair dealing, negligence and unjust enrichment when a skid loader it purchased experienced mechanical problems. The district court dismissed all of EIS's claims except breach of contract and unjust enrichment. Later, the district court entered a judgment in favor of Northwest Power Systems, LLC (NWPS), dismissing EIS's remaining claims and awarded NWPS attorney's fees and costs. EIS appealed to the Supreme Court, arguing arguing that the district court erred in granting summary judgment to NWPS. After careful consideration of the trial court record, the Supreme Court found no reversible error and affirmed that court's grant of summary judgment.View "Edged In Stone v. NW Power Systems" on Justia Law
Sudan Drillings Inc. v. Anacker
Sudan Drilling, Inc. filed a complaint against Glen and Clarice Anacker seeking to foreclose on a construction lien. The district court granted summary judgment for the Anackers and directed the county clerk and recorder to remove Sudan’s lien from the public record. The Anackers recorded the judgment with the clerk and record’s office. The Supreme Court reversed and remanded, holding that genuine issues of material fact precluded summary judgment. On remand, the Anackers filed a motion for summary judgment, arguing that the lien was unenforceable because the recording of the district court’s prior judgment effectively discharged and released the lien, even though the Supreme Court reversed the judgment on appeal. The district court once again granted summary judgment for the Anackers. The Supreme Court reversed, holding that the recording of the previous judgment did not discharge Sudan’s construction lien or render Sudan’s claims moot.View "Sudan Drillings Inc. v. Anacker" on Justia Law
Posted in:
Construction Law
Krien v. Harsco Corp.
The general contractor of a Wisconsin construction project, hired Harsco to supply scaffolding. Krien, injured in a fall when a plank on a scaffold on which he was standing, broke, sued Harsco. The parties settled his claim for $900,000. Harsco filed a third‐party complaint against the contractor, seeking indemnification plus interest and attorneys’ fees. The district judge granted the contractor summary judgment. The Seventh Circuit reversed and remanded after examining the complex provisions of the contract between the two. The plank may or may have been supplied by Harsco and may or may not have been defective, as claimed by Krien, who could not sue Riley in tort, because against his employer his only remedy for a work‐related accident was a claim for workers’ compensation, but there has never been judicial resolution of these questions, because Krien’s suit was settled before there was any judgment. Indemnification, however, is a form of insurance, and could apply even if the party seeking indemnification was negligent. Riley’s duty to indemnify Harsco extends to legal expenses incurred by Harsco in defending against Krien’s suit and in litigating this suit.
View "Krien v. Harsco Corp." on Justia Law
Zachry Constr. Corp. v. Port of Houston Auth. of Harris County
Petitioner, a construction corporation, contracted to construct a wharf for Respondent, the Port of Houston Authority of Harris County, Texas. After the construction was to be completed, Petitioner sued, claiming damages from delays caused by the Port. The Port, in turn, claimed that a no-damages-for-delay provision in the construction contract between the parties precluded delay damages. Petitioner also sought recovery of $2.36 million in delay damages withheld by the Port for Petitioner’s failure to meet deadlines. After a trial, the jury found that the Port had breached the contract for deliberately and wrongfully interfering with Petitioner’s work, causing Petitioner to incur $18,602,697 in delay damages. The jury also found Petitioner had not released its claim to the $2.36 million liquidated damages the Port withheld. The court of appeals reversed. The Supreme Court reversed the court of appeals, holding (1) the Local Government Contract Claims Act waives governmental immunity from suit on a contract claim for delay damages the contract does not call for; (2) the no-damages-for-delay provision in the parties’ contract did not shield the Port from liability for deliberately and wrongfully interfering with the contractor’s work; and (3) Petitioner was entitled to recover the liquidated damages withheld by the Port. View "Zachry Constr. Corp. v. Port of Houston Auth. of Harris County" on Justia Law
Posted in:
Construction Law, Contracts