Justia Construction Law Opinion Summaries
C.G. Schmidt Inc. v. Permasteelisa N. Am.
Using a form provided by CGS, the general contractor for construction of an 18-story Milwaukee office building, PNA submitted a $12,675,421 bid to provide a glass curtainwall--a nonstructural outer covering for weatherproofing and aesthetics. The contract manual provided by CGS stated that “[t]he bidder must accept all terms of the [standard CGS] subcontract as a condition for submitting a bid.” After CGS chose PNA’s bid, PNA repeatedly expressed a need to review the finalized prime contract before it would execute a formal subcontract. CGS and PNA engaged in a “value engineering process” during which they refined the price and other terms of the subcontract. PNA regularly updated the proposed price and communicated the updates to CGS. Several times, PNA raised concerns about subcontract terms. CGS never indicated to PNA that, in CGS’s view, there was already an agreement in place. The parties never entered into a formal subcontract. CGS had to use a different subcontractor at a higher price. CGS filed suit. The district court granted PNA summary judgment, finding that the parties did not intend to be bound until the execution of a formal subcontract. The Seventh Circuit affirmed, agreeing that the parties never entered into a binding contract and that CGS’s promissory estoppel claim fails as a matter of law. View "C.G. Schmidt Inc. v. Permasteelisa N. Am." on Justia Law
Goodwin v. Kingsmen Plastering, Inc.
This case required the Oregon Supreme Court's interpretation of ORS 12.135(1)(a). ORS 12.135(1)(a) provided that an action arising from the “construction, alteration or repair of any improvement to real property” must be commenced within “[t]he applicable period of limitation otherwise established by law.” The question in this construction defect case was precisely what is the period of limitation “otherwise established by law.” Plaintiffs argued their action was subject to a six-year statute of limitations set out in ORS 12.080(3). Defendant argued that the action was not for injury to an “interest” in real property, but for damage to the property itself, which is governed by a shorter, two-year statute of limitations described in ORS 12.110(1) that applied to tort actions generally. The trial court agreed with plaintiffs that the six year-limitation period applied, but granted summary judgment for defendant on the ground that plaintiffs brought their action more than six years after the construction was completed. The Court of Appeals reversed and remanded, holding that, although the six-year statute applied, a “discovery rule” applied, there remained an issue of fact as to whether plaintiffs initiated their action within six years from the time that they knew or should have known of the injury that formed the basis for their claim. After its review, the Supreme Court concluded that the Court of Appeals erred in holding that plaintiffs’ action was subject to the six-year statute: that statute applied to actions for interference with or injury to an “interest” in real property, such as trespass or waste, not to actions for damage to property itself, which are subject to the two-year statute of limitations. There remained, however, a question of fact as to when plaintiffs discovered the damage to their property, which would have triggered the two-year statute of limitations. The Supreme Court therefore affirmed the Court of Appeals with regard to summary judgment, and remanded for for further proceedings. View "Goodwin v. Kingsmen Plastering, Inc." on Justia Law
Schumacher Homes of Circleville v. Spencer
Plaintiff signed a contract with Defendant for the construction of a house. The contract contained an arbitration clause. Plaintiff later brought suit against Defendant, claiming that there were defects in the house. Defendant filed a motion to dismiss and compel arbitration. The circuit court denied the motion, finding that the arbitration clause was unconscionable. Defendant appealed, arguing that the circuit court erred by ruling on questions of arbitrability despite the existence of a delegation provision in the arbitration agreement that vested the arbitrator with authority to determine issues of arbitrability relating to the dispute. The Supreme Court determined that the circuit court was within its rights not to enforce the delegation language because the language did not reflect the parties’ clear and unmistakable intention to delegate issues about the validity, revocability, or enforceability of the arbitration agreement to an arbitrator. The United States Supreme Court granted Defendant’s requested writ of certiorari, vacated the Supreme Court’s opinion, and remanded for further consideration in light of their decision in DIRECTV, Inc. v. Imburgia. The Supreme Court reversed the circuit court’s order, holding that because Plaintiffs never specifically challenged the delegation language before the circuit court or Supreme Court, Plaintiffs waived any right to challenge the delegation language. Remanded for arbitration. View "Schumacher Homes of Circleville v. Spencer" on Justia Law
Bates v. Chicago Lumber Co. of Omaha
Contractor Anderson Carpentry and Construction built a home for Shad and Trisha Bates. Anderson contracted with Century Lumber Center to purchase supplies and materials to build the Bates home. The Bates paid Anderson for materials used on the home, but those funds were applied to other accounts, and the account with Century on the Bates job became delinquent. Century filed a material lien against the Bates property and filed a complaint seeking to foreclose the lien against the property. The district court ultimately enforced the lien. The Supreme Court reversed, holding that the lien was not timely filed as a matter of law. View "Bates v. Chicago Lumber Co. of Omaha" on Justia Law
Cashman Equip. Corp., Inc. v. Cardi Corp., Inc.
Cashman sued, alleging Cardi provided defective cofferdams for construction of the Sakonnet River Bridge. Cofferdams are temporary watertight enclosures that are pumped dry to expose the bottom of a body of water so that construction can occur. During discovery, Cashman sought, and Cardi refused to produce, computer models and draft reports that had been “considered by” its testifying engineering expert to determine “certain stress and loads that are going to be placed on certain points on this cofferdam,” including models “that [the expert] created which [he] may not have relied on but certainly would’ve considered” and draft reports. Cardi argued that Rule 26(b)(4)(A) of the Superior Court Rules of Civil Procedure does not allow discovery of materials “considered by” an expert in forming an expert opinion. The hearing justice concluded that he did not have the authority to compel production of the material. The Rhode Island Supreme Court affirmed, after considering interpretations of the corresponding Federal Rule. The state rule is “clear and unambiguous” and is confined to discovery through interrogatories or deposition. It does not provide for the disclosure of documents. View "Cashman Equip. Corp., Inc. v. Cardi Corp., Inc." on Justia Law
Mountain States Contractors, LLC v. Perez
The Tennessee Department of Transportation engaged Mountain States to build two bridges over the Cumberland River at its intersection with Highway 109 in Gallatin. On May 21, 2013, the boom cable of a Terex HC 165 crane snapped while the crane operator was excavating material from under water, causing the boom—the extendable overhead arm of the crane controlled by the load-bearing wire boom cable—to collapse onto the adjacent highway. As the cable broke under tension, it whipped back to shatter the windows of the crane operator’s cab and the boom hit a passing vehicle. Though no person was injured, the subsequent OSHA investigation determined that at least four people were exposed to risk as a result of the accident. An Administrative Law Judge determined that Mountain States had committed a willful violation of the wire rope inspection standard of the Occupational Safety and Health Administration Act because, before the accident, Mountain States had knowledge that the boom cable had “visible broken wires” within the meaning of the provision requiring repair or replacement before further use. The Sixth Circuit affirmed the citation and penalty, finding substantial evidence to support findings of constructive and actual knowledge. View "Mountain States Contractors, LLC v. Perez" on Justia Law
H.A.S. Electrical Contractors, Inc. v. Hemphill Construction Company, Inc.
During jury selection, plaintiff H.A.S. Electrical Contractors (HAS) challenged defendant Hemphill Construction Company’s use of two peremptory strikes. HAS argued Hemphill’s strikes were racially discriminatory. The Supreme Court found that the trial court failed to follow the "Batson" criterial when it analyzed the challenged strike of one juror. The Supreme Court remanded this case back to the trial court for a limited "Batson" hearing for Juror 7. View "H.A.S. Electrical Contractors, Inc. v. Hemphill Construction Company, Inc." on Justia Law
Travelers Prop. Cas. Co. v. Stresscon Co.
Travelers Property Casualty Company of America (Travelers) petitioned for review of a court of appeals judgment affirming the district court’s denial of its motion for directed verdict in a lawsuit brought by its insured, Stresscon Corporation. Stresscon, a subcontracting concrete company, filed suit against Travelers, alleging, among other things, that Travelers acted in bad faith, unreasonably delaying or denying its claim for covered insurance benefits; and Stresscon sought awards of two times the covered benefits along with fees and costs, as prescribed by statute. Stresscon’s claims for relief arose from a serious construction accident in July 2007, which was caused by a crane operator employed by a company that was itself a subcontractor of Stresscon. Stresscon’s general contractor, Mortenson, sought damages from Stresscon, asserting Stresson’s contractual liability for the resulting construction delays, and Stresscon in turn sought indemnification from Travelers. Although there was much dispute over the factual and legal import of Travelers’ reservation of rights and other of its communications with both Stresscon and Mortenson concerning Mortenson’s claim, there was no dispute that by December 31, 2008, Travelers had not paid the damages asserted by Mortenson. The appellate court rejected Travelers’ contention that the no-voluntary-payments clause of their insurance contract relieved it of any obligation to indemnify Stresscon for payments Stresscon had made without its consent. Instead, the court of appeals found that the Colorato Supreme Court's opinion in "Friedland v. Travelers Indemnity Co.," (105 P.3d 639 (2005)) had effectively overruled prior “no voluntary payments” jurisprudence to the contrary and given Stresscon a similar opportunity. The Supreme Court found that its adoption of a notice-prejudice rule in "Friedland" did not overrule any existing “no voluntary payments” jurisprudence in Colorado, and because the Court declined to extend notice-prejudice reasoning in Friedland to Stresscon’s voluntary payments, made in the face of the no-voluntary-payments clause of its insurance contract with Travelers, the judgment of the court of appeals was reversed. View "Travelers Prop. Cas. Co. v. Stresscon Co." on Justia Law
Fattah v. Bim
In 2005, Masterklad built a house in Glenview, including a brick patio that extended off the rear of the house. Because the ground underneath the patio sloped down, dirt and gravel were placed underneath it to support the bricks and make them level with the house's rear entrance. A retaining wall was built to contain the fill. In 2007, the house was sold by Masterklad to a Lubeck for $1,710,000. In the contract Lubeck “knowingly, voluntarily, fully and forever,” waived the implied warranty of habitability in exchange for an express warranty provided by Masterklad, with a one-year term. In 2010, Lubeck sold the house to Fattah, for $1,050,000, with a document stating that the house was being sold “as is” and that the seller made no representations or warranty regarding its condition. In 2011, parts of the retaining wall around the rear patio gave way and part of the patio collapsed. The owner sued. The circuit court found that the patio wall had given way due to latent defects in its construction, but that plaintiff could not recover because Masterklad had executed a valid, enforceable waiver of the implied warranty of habitability with Lubeck. The appellate court reversed. The Illinois Supreme Court reversed. The implied warranty of habitability may not be extended to a second purchaser of a house when a valid, bargained-for waiver of the warranty has been executed between the builder-vendor and the first purchaser. View "Fattah v. Bim" on Justia Law
GSS Group Ltd. v. Republic of Liberia
GSS appealed the district court’s dismissal of its second attempt to confirm a $44 million arbitral award entered against the Port Authority for breach of a construction contract. GSS first tried to confirm the award, but the district court found that it had no personal jurisdiction over the Port Authority. Then GSS filed its second petition, also naming the Republic of Liberia, which owns the Port Authority, as respondents. The district court again dismissed GSS’s petition, finding that issue preclusion barred relitigating its personal jurisdiction over the Port Authority and that GSS failed to demonstrate that Liberia was liable for the Port Authority’s alleged breach. The court affirmed the district court's dismissal of the claims against Liberia for lack of subject matter jurisdiction under the Foreign Sovereign Immunities Act (FSIA), 28 U.S.C. 1330 et seq.; affirmed the district court's dismissal of GSS's petition against the Port Authority on sovereign immunities grounds; and concluded that the district court did not abuse its discretion by dismissing GSS's petition before allowing jurisdictional discovery. View "GSS Group Ltd. v. Republic of Liberia" on Justia Law