Justia Construction Law Opinion Summaries

by
Summit Construction filed a lawsuit against Jay Koontz and Jennie L. Kennette for breach of contract and unjust enrichment, alleging nonpayment for work performed on Mr. Koontz’s home based on an oral agreement. The work included an addition to the home and extensive renovations to the existing structure. The District Court rejected both claims, determining that there was no enforceable oral contract between the parties and that Summit did not sufficiently prove its damages for the unjust enrichment claim.The District Court found that the parties had not mutually agreed to sufficiently definite terms for an oral contract. The court noted that the project progressed without a clear understanding of the scope of work, how it would be paid for, and who would be responsible for payment. The court also found that Summit's invoices did not clearly define the terms of the contract. Furthermore, the court concluded that Summit had failed to prove the amount by which Mr. Koontz was unjustly enriched, i.e., its damages.Upon appeal, the Supreme Court of Wyoming affirmed the District Court's decision. The Supreme Court agreed that Summit had failed to show the existence of an enforceable oral contract with either Mr. Koontz or Ms. Kennette. The court also agreed with the lower court's finding that Summit had failed to establish its damages to a reasonable degree of certainty, which is necessary for an unjust enrichment claim. View "Summit Construction v. Koontz" on Justia Law

by
A general contractor, Graycor Construction Company Inc., was involved in a dispute with a subcontractor, Business Interiors Floor Covering Business Trust, over unpaid invoices for flooring work performed on a movie theater project. Business Interiors submitted three separate applications for periodic payments, which Graycor neither approved nor rejected within the time limit set by the Prompt Pay Act. As a result, the applications were deemed approved under the Act. Business Interiors sued Graycor for breach of contract and other claims in the Superior Court. The Superior Court granted Business Interiors's motion for summary judgment on its breach of contract claim and entered separate and final judgment. Graycor appealed.Graycor argued that the original contract was not a "contract for construction" within the meaning of the Act, and that it had a valid impossibility defense due to its failure to pay. The Supreme Judicial Court held that the Act defines its scope broadly, and the subcontract at issue was a "contract for construction" under the Act. The Court also held that common-law defenses are not precluded by the Act, but a contractor that does not approve or reject an application for payment in compliance with the Act must pay the amount due prior to, or contemporaneous with, the invocation of any common-law defenses in any subsequent proceeding regarding enforcement of the invoices. As Graycor sought to exercise its defenses without ever paying the invoices, it could not pursue the defenses. The Court also vacated and remanded the rule 54 (b) certification to the motion judge for reconsideration. View "Business Interiors Floor Covering Business Trust v. Graycor Construction Company Inc." on Justia Law

by
The Supreme Court of the State of Colorado was asked to review a case involving a dispute between the City of Aspen and the Burlingame Ranch II Condominium Owners Association, Inc. The dispute centered around alleged construction defects in an affordable housing project overseen by the City of Aspen. The Association claimed that Aspen had breached express and implied warranties, and Aspen argued that the claims were barred by the Colorado Governmental Immunity Act (CGIA), which provides immunity to public entities from claims for injury that lie in tort or could lie in tort.The lower court agreed with Aspen, ruling that the Association's claims sounded in tort, or could sound in tort, and were thus barred by the CGIA. The Association appealed, and the Colorado Court of Appeals reversed the lower court's decision. The appellate court reasoned that the Association's claims could only sound in contract, and thus were not barred by the CGIA. The court relied on the economic loss rule, which generally provides that a party suffering only economic loss from the breach of a contractual duty may not assert a tort claim for such a breach absent an independent duty of care under tort law.The Supreme Court of the State of Colorado reversed the appellate court's decision. The court held that the economic loss rule has no bearing on whether the CGIA bars a plaintiff’s claims. The court clarified that the CGIA bars claims that could arise in both tort and contract, and that the economic loss rule cannot rescue an otherwise CGIA-barred claim. The case was remanded back to the lower court for further proceedings. View "City of Aspen v. Burlingame Ranch II" on Justia Law

by
Jake Johnson, an electrician, was injured while working on a construction project in a building owned by Property Reserve, Inc. (PRI) and managed by CBRE. Johnson was employed by PCF Electric, a subcontractor hired by Crew Builders, the general contractor for the project. Johnson filed a complaint against PRI, CBRE, Crew, and PCF for damages. PRI and CBRE moved for summary judgment based on the Privette doctrine, which generally protects entities that hire independent contractors from liability for injuries sustained by the employees of the independent contractor. The trial court denied the motion, finding a triable issue of fact as to when PRI and CBRE hired Crew for the project.The trial court's decision was based on the execution date of the written contract between PRI, CBRE, and Crew. The court found that there was a triable issue of fact as to when PRI and CBRE hired Crew for the project. The court also granted Crew’s and PCF’s motions for summary judgment, concluding that the Privette doctrine barred Johnson’s claims against them.The Court of Appeal, Fourth Appellate District Division One, disagreed with the trial court's decision. The appellate court found that a written contract is not required to invoke the Privette doctrine, and the undisputed facts established that PRI and CBRE delegated control over the tenant improvements to Crew prior to Johnson’s injury. The court also found that no exception to the Privette doctrine applied. The court concluded that no triable issues of material fact precluded summary judgment and granted PRI and CBRE’s requested relief. View "CBRE v. Superior Court" on Justia Law

by
This case revolves around a dispute between California Specialty Insulation, Inc. (CSI) and Allied World Surplus Lines Insurance Company (Allied World) over a commercial general liability insurance policy. The policy was issued by Allied World to CSI. The dispute arose when Allied World refused to defend and indemnify CSI against a negligence claim following a construction site accident. The parties disagreed on whether one of the policy’s exclusions for bodily injury liability applied in this situation. The policy excluded coverage for bodily injury to the employees of any “contractor,” but the term “contractor” was not defined in the policy. Allied World argued that the term was unambiguous and the exclusion precluded coverage for the negligence claim, while CSI argued that the term was ambiguous and the exclusion did not apply to the negligence claim.The trial court ruled in favor of CSI, granting its motion for summary judgment and denying Allied World’s. The court found that the term “contractor” in the disputed exclusion was ambiguous and interpreted the term in favor of CSI.The Court of Appeal of the State of California Second Appellate District Division Seven affirmed the trial court's decision. The appellate court agreed with the trial court that the term “contractor” in the disputed exclusion was ambiguous. The court interpreted the term based on CSI’s objectively reasonable expectations and concluded that the exclusion did not apply to the negligence claim in question. Therefore, Allied World was obligated to defend and indemnify CSI against the negligence claim. View "California Specialty Insulation, Inc. v. Allied World Surplus Lines Insurance Co." on Justia Law

by
The case revolves around a construction dispute where several homeowners in the San Marcial neighborhood sued Oscar Renda Contracting, Inc., for negligence and gross negligence. The homeowners alleged that the company's misuse of heavy equipment and faulty construction techniques caused damage to their homes during the construction of a drainage pipeline. They sought actual damages to restore their properties and exemplary damages based on gross negligence.The trial court found Renda Contracting negligent and grossly negligent. However, the jury was not unanimous in deciding the amount of exemplary damages, with ten out of twelve jurors agreeing. Consequently, the trial court omitted exemplary damages from the judgment. The homeowners appealed, and the court of appeals reversed the decision, arguing that unanimity as to exemplary damages could be implied despite a divided verdict.The Supreme Court of Texas reversed the court of appeals' judgment and reinstated the trial court's judgment. The court held that under Section 41.003 of the Civil Practice and Remedies Code, a court may not imply a unanimous jury finding in imposing exemplary damages. The burden to secure a unanimous verdict is on the plaintiff and "may not be shifted." The court concluded that the plaintiff bears the burden to obtain the findings necessary to impose exemplary damages, including that the jury is unanimous as to any amount of exemplary damages awarded. It is the plaintiff who must challenge a divided verdict as infirm or in need of clarification. View "OSCAR RENDA CONTRACTING, INC. v. BRUCE" on Justia Law

by
In September 2019, Eleticia Garcia hired Ponagansett 2 LLC, doing business as Peter Bibby Heating & Air, to perform mechanical work on her property. The parties signed two contracts, one for the installation of gas lines, water heaters, and boilers, and another for the installation of baseboards. However, Garcia failed to make the agreed-upon payments, leading Ponagansett to file a mechanics' lien against her property. When Garcia did not respond to the complaint, the Superior Court entered a default judgment in favor of Ponagansett.The Superior Court denied Garcia's subsequent motions to vacate the entry of default, to file a counterclaim out of time, to quash the mechanics' lien, and to file an oral proof of claim. Ponagansett then filed a motion for entry of default judgment against Garcia and a petition for attorneys' fees. The Superior Court granted Ponagansett's request to enforce the mechanics' lien, awarded Ponagansett $20,000 plus interest, and granted attorneys' fees of $12,310.27.On appeal to the Supreme Court of Rhode Island, Garcia argued that the mechanics' lien was unenforceable because Ponagansett failed to provide notice of a possible mechanics' lien as required by law. She also contended that the decisions of the hearing justice to award Ponagansett the full payment of $20,000 and exclude the admission of a mechanical permit were reversible errors. The Supreme Court affirmed the judgment of the Superior Court, holding that Garcia had waived her enforceability argument by failing to timely respond to Ponagansett's complaint. The court also found no error in the hearing justice's award of damages and exclusion of the mechanical permit. View "Ponagansett 2 LLC v. Eleticia Garcia" on Justia Law

by
In 2003, the City of Chicago contracted with Walsh Construction Company to manage the construction of a canopy and curtain wall system at O’Hare International Airport. Walsh subcontracted with LB Steel, LLC to fabricate and install steel columns to support the wall and canopy. Several years into the project, the City discovered cracks in the welds of the steel columns and sued Walsh for breaching its contract. Walsh, in turn, sued LB Steel under its subcontract. Walsh also asked LB Steel’s insurers to defend it in the City’s lawsuit, but they never did. Walsh eventually secured a judgment against LB Steel, which led it to declare bankruptcy. Walsh then sued LB Steel’s insurers to recover the costs of defending against the City’s suit and indemnification for any resulting losses.The district court granted summary judgment in favor of the plaintiff insurers on both issues. The court reasoned that, because the physical damage at issue was limited to LB Steel’s own products, it did not constitute “property damage” as that term appears in the policies, thereby precluding coverage. As for the duty to defend, the court determined that the Insurers had none, because the City’s underlying claims did not implicate potential coverage under LB Steel’s policies.The United States Court of Appeals for the Seventh Circuit affirmed the district court's decision. The court concluded that the defects in the welds and columns do not constitute “property damage” under LB Steel’s commercial general liability (CGL) policies. The court also found that the insurers had no duty to defend Walsh in the City’s underlying suit. The court further affirmed the district court's denial of Walsh’s request for sanctions under § 155. View "St. Paul Guardian Insurance Company v. Walsh Construction Company" on Justia Law

by
The case involves two plaintiffs, Glen A. Canner and Louis D. Puteri, who separately sued a condominium association, Governors Ridge Association, Inc., alleging that the foundations supporting their respective units were defective. The units, part of a common interest community, were purchased by Canner and Puteri in 2001 and 2002 respectively. The defendant had affirmed its responsibility for any foundation settlement issues. However, despite the units suffering significant, uneven settling and the defendant hiring several companies to investigate potential repairs from 2012 to 2016, no repairs were ultimately made. The plaintiffs commenced their actions in 2016 and 2017, alleging that the defendant had negligently designed and constructed the foundations and had violated its duties under the Common Interest Ownership Act (CIOA) by failing to conduct necessary repairs.The trial court concluded that the CIOA claims were time-barred by the statutory three-year limitation period generally applicable to tort actions. The Appellate Court affirmed the trial court’s judgments, concluding that the limitation period set forth in § 52-577 applied because the claims sounded in tort rather than contract. The Appellate Court also agreed with the trial court’s conclusion that the declaration and bylaws created no duty to repair because the relevant declaration required the defendant to repair only insured common elements, and there was no requirement that the foundations themselves be insured.The Supreme Court of Connecticut held that the Appellate Court properly applied the statute of limitations set forth in § 52-577 to the portion of the CIOA claims seeking recovery for negligence during the course of construction of the foundations. However, the Supreme Court found that the Appellate Court improperly upheld the trial court’s disposition, in favor of the defendant, of the claims that the defendant had violated its contractual duties under the bylaws to maintain, repair or replace common elements when it failed to effectuate repairs to the foundations. The Supreme Court concluded that the claims that the defendant breached its contractual duties imposed under the bylaws by failing to repair the foundations were governed by the six-year limitation period applicable to contract claims in § 52-576. The case was affirmed in part, reversed in part, and remanded for further proceedings. View "Canner v. Governors Ridge Assn., Inc." on Justia Law

by
A homeowner, Mohammad Rafiei, sued his builder, Lennar Homes, alleging personal injuries due to a construction defect. The purchase contract between Rafiei and Lennar contained an agreement to submit disputes to arbitration under the Federal Arbitration Act, including issues of formation, validity, or enforceability of the arbitration agreement. Lennar moved to compel arbitration, but Rafiei argued that the arbitration agreement was unconscionable because the cost of arbitration was prohibitively high. The trial court denied Lennar's motion to compel arbitration.The Court of Appeals for the Fourteenth District of Texas affirmed the trial court's decision, holding that Rafiei had sufficiently demonstrated that the cost to arbitrate was excessive, making the arbitral forum inadequate to vindicate his rights. The court of appeals concluded that if Rafiei were required to pay more than $6,000, he would be precluded from pursuing his claims.The Supreme Court of Texas reversed the judgment of the court of appeals. The court held that the record failed to support a finding that the parties' delegation clause was itself unconscionable due to prohibitive costs to adjudicate the threshold issue in arbitration. The court noted that Rafiei had not provided sufficient evidence to show that he could not afford the cost of arbitrating the arbitrability question. The court also noted that Rafiei had not provided evidence of how the fee schedule would be applied to resolve the unconscionability issue. The court remanded the case to the trial court for further proceedings consistent with its opinion. View "Lennar Homes Of Texas Inc. v. Rafiei" on Justia Law