Justia Construction Law Opinion Summaries
James Construction Group, LLC v. Westlake Chemical Corp.
In this case arising out of a construction contract dispute involving competing claims of breach between the owner and the contractor, the Supreme Court reversed in part the court of appeals' judgment affirming the portion of the trial court's judgment awarding damages to the owner but reversing as to the contractor, holding that the judgment awarding certain expenses to the owner could not stand.The jury found that both the owner and the contractor breached the contract and awarded damages as to both parties. At issue was whether the owner's entitlement to recover contract damages associated with a termination of the contractor for default hinged on strict compliance with the written-notice conditions precedent to such recovery, whether sufficient evidence supported the jury's finding of compliance, and whether a contractual provision governing consequential damages was liability waiver or a covenant not to sue. The Supreme Court held (1) when a contract mandates written notice, a writing is a necessary part of complying with contractual notice conditions, substantially or otherwise; (2) because the owner failed to provide the requisite written notices to be entitled to recover expenses associated with a termination for default, the judgment awarding them to the owner could not stand; and (3) the contract did not contain a covenant not to sue for consequential damages. View "James Construction Group, LLC v. Westlake Chemical Corp." on Justia Law
Centerplan Construction Co. v. Hartford
The Supreme Court reversed the judgment of the trial court finding Plaintiffs responsible for failing to complete a project by the parties' agreed-upon deadline and awarding Defendant $335,000 in liquidated damages on its counterclaim, holding that the trial court's pretrial interpretation of various agreements between the parties was erroneous.At issue was which party was responsible for delays in constructing Dunkin Donuts Park in the City of Hartford. Plaintiffs, the project's developer and the design-builder, sued the City claiming breach of contract, and the City counterclaimed for breach of contract. The trial court concluded, as a matter of law, that Plaintiffs controlled the architect and were therefore liable for changes to and mistakes in the ballpark's design. Thereafter, the jury found Plaintiffs responsible for failing to complete the stadium by the agreed-upon deadline. The Supreme Court reversed, holding that the parties' contracts did not unambiguously grant Plaintiffs legal control of the architect and the stadium's design across all relevant time periods. View "Centerplan Construction Co. v. Hartford" on Justia Law
Kim v. TWA Construction, Inc.
The owners purchased the property in a wooded area of Los Gatos to build a home. They sought to remove some trees, including a large eucalyptus tree that straddled the property line, not realizing that the eucalyptus was partially on the neighbor’s property and that they needed her permission to remove it. They assumed they could remove the eucalyptus because they had received permits from the county. The owners’ general contractor, TWA, hired a subcontractor for tree trimming. The subcontractor damaged the eucalyptus tree.The neighbor sued. The owners filed a cross-complaint against TWA for comparative negligence, breach of contract, express contractual indemnity, equitable indemnity, and other claims. TWA filed a cross-complaint against the owners, alleging breach of contract and other claims. At trial, the owners and TWA settled the suit with the neighbor. The suits involving their cross-complaints continued. TWA presented no evidence that the subcontractor who worked on the eucalyptus was licensed for tree trimming work.The court of appeal affirmed that TWA was 100 percent at fault for the neighbor’s damages and had been paid $10,000 for the tree trimming services performed by the subcontractor. The court rejected arguments that the trial court erred in interpreting the licensing statute, Business and Professions Code section 7031.3, and misinterpreted the construction agreement. View "Kim v. TWA Construction, Inc." on Justia Law
APCO Construction, Inc. v. Helix Electric of Nev., LLC
The Supreme Court affirmed the decision of the district court determining that the covenant of good faith and fair dealing applied when it awarded delay damages to a subcontractor, holding that the district court properly determined that the covenant of good faith and fair dealing applied and that the contractor breached the covenant.At issue on appeal was (1) whether the district court properly applied the covenant of good faith and fair dealing when it awarded delay damages to a subcontractor, and (2) whether the subcontractor waived its right to receive delay damages by signing a waiver and release to receive its retention. The Supreme Court held (1) the covenant of good faith and fair dealing allowed for the subcontractor to receive delay damages; and (2) the conditional release and waiver the subcontractor signed did not preclude it from receiving delay damages. View "APCO Construction, Inc. v. Helix Electric of Nev., LLC" on Justia Law
United States v. Frazier
Defendant-appellant Antoine Frazier appealed the district court’s denial of his motion to suppress evidence obtained during a roadside search of his vehicle in 2019. A Utah state trooper pulled defendant over for speeding. The trooper did not begin the standard procedures necessary to issue a citation. Instead, he immediately began trying to contact a canine handler with the local sheriff’s office, so he could come to the scene and perform a dog sniff of the vehicle. At first, the trooper tried contacting the deputy via the instant-messaging system on his vehicle’s computer. When the deputy failed to respond to several messages, the trooper tried callling him on the radio. When the deputy again failed to respond, the trooper asked dispatch to locate him and send him to the scene. Approximately thirty minutes from the initial stop did the canine search defendant's vehicle, alerting to potential contraband. In this time, a records check from dispatch revealed defendant had pled guilty in 2006 to manslaughter; a pat-down search revealed defendant had a .22 caliber pistol in his pants pocket. Defendant was ultimately arrested for being a felon in possession of a firearm, and for possession of fentanyl and cocaine with the intent to distribute. Defendant argued the evidence obtained from that search was inadmissible because the trooper improperly prolonged the traffic stop to facilitate a dog sniff and thereby obtain probable cause to search his vehicle. The Tenth Circuit reversed, finding the trooper departed from the traffic-based mission of the stop by arranging the dog sniff, "an investigative detour that was unsupported by reasonable suspicion and that added time to the stop. ...The trooper’s consultation of the DEA database, a second investigative detour, only aggravated that ongoing violation. Accordingly, the evidence discovered because of that seizure is tainted by its unlawfulness and is inadmissible." View "United States v. Frazier" on Justia Law
Helix Electric of Nev., LLC v. APCO Construction, Inc.
In this construction contract action, the Supreme Court affirmed the judgment of the district court dismissing Helix Electric of Nevada, LLC's claims for retention against APCO Construction, Inc. and the award of attorney fees for APCO pursuant to Nev. R. Civ. P. 68 for less than APCO's requested amount.Gemstone Development West, Inc. sought to construct condominiums and hired APCO as its general contractor. APCO subcontracted with Helix at Gemstone's direction. Helix was paid less than it billed, and the difference, $505,021, was withheld in retention. Under the subcontract, the retention would be released only upon the occurrence of several conditions. Later, the relationship between the parties soured, and the project was terminated. APCO, Helix, and other subcontractors recorded mechanics' liens against the property. After a trial, the district court dismissed Helix's claims for retention against APCO and granted attorney fees. The Supreme Court affirmed, holding (1) the district court correctly concluded that a subcontract provision conditioning the payment of funds on APCO first being paid was unenforceable, but the unenforceablity of the pay-if-paid condition did not also invalidate the remaining conditions precedent for obtaining the retention payment; and (2) none of the remaining arguments on appeal warranted reversal. View "Helix Electric of Nev., LLC v. APCO Construction, Inc." on Justia Law
Service Steel Warehouse Co., L.P. v. United States Steel Corp.
In this dispute arising from a supplier's sale of steel for a project to a fabricator who did not perform any work on the project site, the Supreme Court reversed the order of the trial court granting summary judgment for the site's owner, holding that the trial court did not err.The supplier in this case sued to foreclose on its mechanic's lien against the project site. In granting summary judgment for the site's owner, the trial court concluded that the fabricator's lack of on-site work meant that it was also a supplier, and case law barred supplier-to-supplier liens. The Supreme Court reversed, holding (1) under Indiana's mechanic's lien statute a supplier that furnished materials for the erection of a building, regardless of the recipient, can have a lien on that building and the accompanying land; and (2) because the supplier furnished steel for the project, the supplier could have a lien on the project site. View "Service Steel Warehouse Co., L.P. v. United States Steel Corp." on Justia Law
Posted in:
Construction Law, Supreme Court of Indiana
FieldTurf USA, Inc. v. Pleasant Grove Independent School District
The Supreme Court reversed in part the decision of the court of appeals reversing the trial court's summary judgment in this case involving a school district's breach of warranty claims against a general contractor and an artificial-field-turf manufacturer, holding that the court of appeals erred.The Supreme Court reversed in part and reinstated the trial court's summary judgment in favor of the contractor, holding (1) a trial court’s on-the-record, oral ruling sustaining an objection to summary judgment evidence suffices to strike the evidence from the summary judgment record when the ruling is not reduced to a written order; and (2) the court of appeals erred in reversing the trial court's summary judgment in favor of the contractor and remanding the claims against the turf manufacturer for a new trial without addressing the merits of the issues on appeal that could result in rendition of judgment in favor of the manufacturer. View "FieldTurf USA, Inc. v. Pleasant Grove Independent School District" on Justia Law
Maxim Crane Works, LP v. Zurich American Insurance Co.
The Supreme Court held that the Texas Workers' Compensation Act (TWCA) does not affect the enforceability of an additional-insured provision under the Texas Anti-Indemnity Act (TAIA).A general contractor's employee injured in an accident obtained a negligence judgment in Texas state court against the subcontractor that operated the crane (Berkel) and the company that leased the crane (Maxim). Berkel was an indemnity and Maxim was an indemnity for TAIA purposes because Berkel had provided Maxim with coverage as an additional insured. After the injured worker settled with Maxim, Maxim unsuccessfully sought reimbursement from Berkel's insurer (Zurich). The court of appeals reversed the judgment against Berkel, concluding that Berkel and the injured worker were "statutory co-employees" of the general contractor under the TWCA, and therefore, the TWCA provided the worker's exclusive remedy. In a separate suit in federal court, Maxim and Zurich disputed over whether the additional-insured coverage was enforceable. The Supreme Court answered a certified question by holding that the word "employee" in Tex. Ins. Code 151.103 bears its common meaning, which is not affected by whether the indemnity and injured employee are considered co-employees for purposes of the TWCA. View "Maxim Crane Works, LP v. Zurich American Insurance Co." on Justia Law
Fountain v. Fred’s, Inc., et al.
The South Carolina Supreme Court granted review of a court of appeals' decision affirming a trial court's finding that Respondents Fred's, Inc. (Fred's) and Wildevco, LLC (Wildevco) were entitled to equitable indemnification from Petitioner Tippins-Polk Construction, Inc. (Tippins-Polk). Respondent Fred's was a Tennessee corporation that operated a chain of discount general merchandise stores in several states, including South Carolina. Respondent Wildevco is a South Carolina limited liability company that owned a tract of undeveloped commercial property in Williston, South Carolina. In February 2005, Wildevco and Fred's entered into a lease agreement in which Wildevco agreed to construct a 16,000-square-foot commercial space located in Williston, South Carolina, according to Fred's conceptual design specifications. In turn, Fred's agreed to lease the property for ten years. In April 2005, Wildevco entered into a contract with general contractor Tippins-Polk for the construction of the Fred's store and adjoining strip center. Pursuant to the lease agreement between Wildevco and Fred's, Wildevco was the party responsible for "keep[ing] and repair[ing] the exterior of the [] Premises, including the parking lot, parking lot lights, entrance and exits, sidewalks, ramps, curbs," and various other exterior elements. Fred's was responsible for maintenance of the interior of the premises. Five years after the Fred's store opened, on a sunny day in March, Martha Fountain went to the Williston Fred's to purchase light bulbs. Her toe caught the sloped portion of the ramp at the entrance of the store, causing her to trip and fall. Fountain sustained serious injuries to her hand, wrist, and arm and has undergone five surgeries to alleviate her pain and injuries. Fountain and her husband filed a premises liability suit against Fred's and Wildevco, alleging Respondents breached their duty to invitees by failing to maintain and inspect the premises and failing to discover and make safe or warn of unreasonable risks. Pertinent to this appeal, Tippins-Polk argued the court of appeals erred in finding a special relationship existed between it and Fred's and in finding Respondents proved they were without fault as to the Fountain premises liability claim. Because the Supreme Court found Respondents failed to establish they were without fault in the underlying action, judgment was reversed. View "Fountain v. Fred's, Inc., et al." on Justia Law