Justia Construction Law Opinion Summaries

by
This case involved a dispute regarding developed property. Developer filed a complaint alleging that the project's general contractor (Contractor) and an engineering firm (Firm) had negligently provided recommendations with respect to site preparation. The circuit court granted partial summary judgment in favor Firm on Contractor's cross-claims against Firm that sought recovery of remediation costs incurred by Contractor, concluding (1) some of Contractor's cross-claims were time-barred by the applicable statute of limitations, and (2) W. Va. Code 55-2-21 did not apply to toll any limitations periods because Contractor's claims were independent causes of action as opposed to cross-claims. The Supreme Court reversed, holding (1) the circuit court prematurely found that section 55-2-21 did not apply because it failed to analyze whether the claims arose from the same transaction or occurrence and, thus, constituted cross-claims or independent causes of action; and (2) genuine issues of material fact existed so as to preclude summary judgment if Contractor's claim was an independent cause of action. Remanded. View "J. A. Street & Assocs. v. Thundering Herd Dev." on Justia Law

by
Plaintiff commenced a lawsuit against 96 Rockaway, LLC, Novalex Contracting Corp., and T-Construction Co., Inc., alleging among other things, violations of Labor Law 240(a) and 241(6). Discovery and a third-party action ensued. T-Construction moved for summary judgment, seeking dismissal of the complaint, and all cross-claims against it. 96 Rockaway and Novalex cross-moved for identical relief. Supreme Court granted defendants' motions, and dismissed plaintiff's complaint in its entirety. The Appellate Division reversed so much of Supreme Court's order as granted defendants' motions for summary judgment dismissing plaintiff's claims, denied the motions, and reinstated those claims. The court held that, given that Labor Law 240(1) should be construed with a common sense approach to the realities of the workplace at issue, defendants were entitled to summary judgment dismissing that claim. Plaintiff's Labor Law 241(6) cause of action, predicated on a violation of 12 NYCRR 23-1.7(b)(1)(i), failed for similar reasons. Accordingly, the order of the Appellate Division was reversed. View "Salazar v Novalex Contr. Corp." on Justia Law

by
The Supreme Court of Arizona answered questions that the court certified to that court. Specifically, it had determined that the rule of American Pipe & Construction Co. v. Utah did not toll the statute of repose for construction-defect claims set forth in Arizona Revised Statutes section 12-552. It also determined that Arizona's saving statute, Ariz. Rev. Stat. 12-504(A), did not operate to save appellants' claims. Both of the parties agreed that the Supreme Court of Arizona's answers to the court's certified questions put an end to the litigation that was before the court. Consequently, the court held that, for the reasons articulated by the Supreme Court of Arizona, appellants' claims were time-barred. Therefore, the judgment of the district court dismissing appellants' complaints was affirmed. View "Albano, et al. v. Shea Homes Ltd P'ship, et al." on Justia Law

by
Danny O'Neall was injured while working for Sadler Line Construction, a subcontractor of Alliance Construction. Sadler had commercial general liability (CGL) coverage with Federated Service Inusrance Company. In the underlying personal injury action, O'Neall sued Alliance and Sadler for negligence. In the instant action, Federated filed a declaratory judgment action against Alliance, alleging that it had no duty to defend or indemnify Alliance against O'Neall's personal injury action. The district court granted summary judgment for Federated. The Supreme Court reversed, holding (1) the parties, by requiring Sadler to name Alliance as an additional insured on its CGL policy, intended that Sadler would insure against loss caused by Alliance's negligence; and (2) Sadler's additional insured endorsement, which provided coverage for liability arising out of Sadler's operations, was broad enough to include coverage for Alliance's negligence even if Sadler was not negligent. Remanded. View "Federated Serv. Ins. Co. v. Alliance Constr." on Justia Law

by
This case arose from an award by Golden Valley Electric Association (GVEA) of two competitively bid construction contracts on its Northern Intertie Project. In November 2001 GVEA awarded Global Power & Communications, LLC (Global) a $39.4 million contract (Contract NI-8) for construction of the Northern Intertie’s Tanana River flats section. Later GVEA awarded Global an approximately $5.3 million contract (Contract NI-9) for construction of the Northern Intertie’s Tanana River crossing and Fairbanks sections. Subsequently, after Global had been awarded NI-9 and before it had completed work on NI-8, Global presented GVEA with requests for additional compensation (RFIs) totaling approximately $2.4 million in connection with NI-8. GVEA responded that it found "no legitimate basis" to justify Global’s RFIs and rejected Global’s request for additional payment. Global also notified GVEA that Global would submit more RFIs, arising out of both NI-8 and NI-9. In all, Global sought additional compensation totaling $5.7 million under the two contracts. GVEA responded to Global denying most of the RFIs but indicated that it would approve a few and consider partial payment for a few others. Global sued, and a trial court ultimately held in GVEA's favor, awarding it costs under both the contract and the applicable state law. Global appealed, arguing among other things, the trial court abused its discretion in ruling in favor of GVEA. Upon review of the lengthy record from the trial court, the applicable legal authority and legislative history, and the two contracts in question, the Supreme Court partly affirmed and partly vacated the trial court's decision. The case was remanded for: (1) a fee determination regarding GVEA’s "UTPA" claim against Global and (2) a new trial on causation and damages relating to GVEA’s breach of NI-9. View "ASRC Energy Services Power v. Golden Valley Electric" on Justia Law

by
In 2002, Defendant David Egan, a business manager for Defendant Foxhollow Construction and Trucking, Inc. (Foxhollow), met with Wayne Johnson of Defendant L.N. Johnson Paving, LLC (Johnson) to discuss a bid for excavation and paving work for a new public high school. Foxhollow wanted to bid on the project but lacked the requisite public works license. Johnson thought its license could cover Foxhollow if the two companies submitted a bid in Johnson's name. Egan submitted a subcontract bid in Johnson’s name to Plaintiff Harris, the general contractor for the school project, and was the successful bidder. Over the course of the business relationship, a contract dispute arose. Harris brought this action, alleging that (1) Foxhollow, Johnson, and another subcontractor breached their subcontracts with Harris. Egan filed a counterclaim for indemnification from Harris. The district court dismissed Foxhollow as a party for lack of proof of notice because there was no indication that Foxhollow was ever served. After a bench trial, the court granted Harris’ motion for "directed verdict" as to Egan’s counterclaim. The court concluded however that Harris failed to prove any of its remaining claims against any of the defendants and therefore was not entitled to relief. The court also awarded fees and costs to Johnson. On appeal to the Supreme Court, Harris argued that the district court: (1) erred in concluding Harris failed to prove contract damages; (2) erred in concluding that no defendant was unjustly enriched; (3) erred in concluding that no defendant is liable for fraud; (4) erred in concluding that Harris was not entitled to indemnity; (5) abused its discretion in denying Harris’ motion to amend findings and conclusion; (6) abused its discretion in granting fees and costs to Johnson; and (7) abused its discretion in denying Harris’ motion for a new trial. Upon review, the Supreme Court affirmed the district court's judgment except for its attorney fee awards, which were vacated. View "Harris, Inc. v. Foxhollow Construction & Trucking, Inc. " on Justia Law

by
The issue before the Supreme Court in this appeal was the City of Lewiston's rejection of a bid for a public works project on the grounds that the lowest bidder lacked sufficient experience for the project. In 2009, the City of Lewiston (City) advertised for bids to replace the irrigation system at the City golf course. Hillside Landscape Construction, Inc. (Hillside) desired to bid on the project, but prior to doing so it sent a letter to City stating that if City insisted upon having qualifications other than a current Idaho public works license to bid on the project, the City must follow the Category B procedures set forth in the Idaho Code and pre-qualify the bidders. Hillside asked that the qualification of prior experience be removed. City’s attorney denied the request, stating that City’s specifications and bidding process complied with state law. Hillside and four others submitted bids for the project. City notified the bidders that Hillside Landscape Construction submitted the lowest bid but that the company lacked the required experience specified within the bid documents. City awarded the contract to Landscapes Unlimited, the next lowest bidder. Hillside filed a complaint seeking injunctive relief, declaratory relief, and damages. The district court held that City complied with the bidding statutes, vacated a temporary restraining order, denied the motion for an injunction then dismissed Hillside’s complaint. In its review, the Supreme Court found that because the City chose to follow the "Category A" procedures set forth in the Idaho Code rather than the Category B procedures, the district court erred in holding that City could reject the bid on that ground. The Court therefore vacated the judgment of the district court and remanded the case for further proceedings. View "Hillside Landscape Construction, Inc. v. City of Lewiston " on Justia Law

by
The issue on appeal before the Supreme Court was the grant of summary judgment against Landscapes Unlimited, LLC (LU) in which the district court: (1) applied I.C. 45-508 to postpone LU’s lien claim in golf course property to Hopkins Northwest Fund, LLC’s (Hopkins) deed of trust covering the same, and (2) alternatively apportioned LU’s lien amount. Hopkins filed a complaint in district court seeking to foreclose on its deeds of trust because the borrowers were in default on both promissory notes. Hopkins alleged in the complaint that its interest in the subject properties had priority over LU’s lien claim. LU cross-claimed, alleging that its lien claim was superior to Hopkins’ deeds of trust because LU began work on the project in June 2006 and Hopkins did not record its first deed of trust until August. Accordingly, LU sought to foreclose its lien with respect to the parcels identified in its lien claim. LU filed a motion for summary judgment in December 2008 regarding the validity, superiority, and amount of its lien claim. Hopkins responded that LU’s lien, even if valid, did not have priority over Hopkins’ interest because LU failed to designate what portions of its lien amount are attributed to each parcel or improvement pursuant to I.C. 45-508. LU countered that a single lien claim could be filed, without segregating the amount, when the labor is provided pursuant to a single contract and the work provided amounts to a single improvement. The district court orally ruled that LU’s lien claim on the four parcels at issue was superior to Hopkins’ interest pursuant to I.C. 45-506. Because the Supreme Court found that I.C. 45-508 was inapplicable to LU’s lien claim and that equitable apportionment was not an appropriate alternative remedy where I.C. 45-508 does not apply, the Court vacated the judgment and remanded the case for further proceedings. View "Hopkins Northwest Fund, LLC v. Landscapes Unlimited, LLC " on Justia Law

by
A construction company solicited a bid from a subcontractor to perform concrete work. The construction company provided a plan and bid schedule. The subcontractor responded with a proposal, which the construction company accepted. The subcontractor carried out the subcontract as it understood the terms. After the work was completed, the subcontractor discovered it had inadvertently underbid on the project. In the ensuing lawsuit, the superior court granted partial summary judgment to the construction company with respect to all damages claimed in relation to the bidding error. The subcontractor appealed the partial summary judgment order, claiming breach of an implied warranty that the plans and specifications would be sufficient, and arguing that the superior court erred by applying the theory of unilateral mistake to the case. Because the construction company did not breach the implied warranty and the subcontractor committed a unilateral mistake for which it bore the risk, the Supreme Court affirmed. View "Handle Construction Co., Inc. v. Norcon, Inc." on Justia Law

by
The issue before the Tenth Circuit in this case centered on whether property damage caused by a subcontractor's faulty workmanship is an "ocurrence" for purposes of a commercial general liability (CGL) insurance policy. The issue arose from the appeals of Plaintiffs-Appellants Greystone Construction, Inc., The Branan Company, and American Family Mutual Insurance Company (American) who all appealed the district court’s grant of summary judgment in favor of Defendant National Fire & Marine Insurance Company (National). Greystone was the general contractor that employed multiple subcontractors to build a house in Colorado. As is common along Colorado’s front range, the house was built on soils containing expansive clays. Over time, soil expansion caused the foundation to shift, resulting in extensive damage to the home’s living areas. The homeowners sued Greystone for damages, alleging defective construction by the subcontractors who installed the foundation. Greystone was insured under CGL policies provided by two insurers. American provided policies for 2001 to 2003, and National provided policies for 2003 to 2006. The American and National policy periods did not overlap. Greystone tendered a claim to American and then National. National denied it owed Greystone any defense. In district court, the builders and American sought to recover a portion of their defense costs from National. Upon review, the Tenth Circuit concluded that damage arising from a poor workmanship may fall under a CGL policy’s initial grant of coverage, even though recovery may still be precluded by a business-risk exclusion or another provision of the policy. The case was remanded to the district court for further proceedings. View "Greystone Construction v. National Fire & Marine" on Justia Law