In re Individual 35W Bridge Litig.
This case arose out of the 2007 collapse of the Interstate 35W Bridge. Individual plaintiffs commenced lawsuits against a contractor that performed work on the bridge pursuant to a contract entered into with the State. The contractor brought a third-party complaint against Jacobs Engineering Group for indemnity and contribution on the basis that Jacobs' predecessor negligently designed the bridge. Jacobs moved to dismiss the lawsuits as time-barred and argued that the 2007 amendments to Minn. Stat. 541.051 did not revive actions for contribution or indemnity that had previously been extinguished by a prior version of the statute of repose. The district court denied the motion to dismiss, but the court of appeals reversed. The Supreme Court affirmed the court of appeals, holding that the 2007 amendments to section 541.051 did not retroactively revive the contractor's action for contribution against Jacobs. View "In re Individual 35W Bridge Litig." on Justia Law
500 James Hance Ct. v. Pa. Prevailing Wage Appeals Bd.
In 2006, Developer-Appellee 500 James Hance Court, LP entered into a construction management agreement with Contractor Gorman Construction Company, Inc., pertaining to the erection of a building at 500 James Hance Court, situated within the Oaklands Corporate Center in Exton, Chester County. According to the agreement, the contemplated, 68,000-square-foot structure was to be used as an elementary charter school, and the project was denominated "Collegium Charter School." Soon after the lease and related contracts were executed, the Bureau of Labor Law Compliance notified the School that it was investigating the project to determine whether prevailing wages were required. In this regard, the Bureau explained that charter school construction was treated the same as a traditional school project (re: public works project) for prevailing wage purposes. If the project's phases could be bifurcated, both the school and Appellee would be responsible. The issue between the parties centered on who was ultimately responsible for compliance with the prevailing wage law: the contractor or the school. The Commonwealth Court had found no evidence that the charter school had any role in determining space and performance goals for the project, and therefore the school was responsible for compliance. But upon review, the Supreme Court concluded that the Board’s determination that the lease was a disguised construction contract for the building as a whole, was based on legal error and essential findings which lacked substantial evidentiary support. Facially, the project was rationally divisible according to major phases of shell and fit-out construction. As to the shell, Appellees established the private character of the funding. Furthermore, in terms of economic reality, Appellees presented a prima facie case that Developer's only relationship with the School was per a bona fide pre-development lease. The Bureau failed to go forward with sufficient evidence to the contrary to overcome this prima facie case, and as such, affirmed the Commonwealth Court. View "500 James Hance Ct. v. Pa. Prevailing Wage Appeals Bd." on Justia Law
State ex rel. Richmond Am. Homes v. Jefferson County Circuit Court (Sanders)
Petitioner, a constructor, was sued by several people living in new homes built by Petitioner (Residents). Residents claimed they were injured by radon gas leaking into their homes because of improper construction by Petitioner. Petitioner argued that the agreement to purchase the new homes required Residents to arbitrate their claims, whether they signed the agreement or not. The circuit court found the arbitration provision ambiguous and unconscionable and refused to compel Residents into arbitration. Petitioner subsequently sought a writ of prohibition to compel Residents to arbitrate their claims. The Supreme Court denied the writ, holding that the circuit court was within its authority to refuse to enforce the arbitration clause against Residents because the arbitration provision was ambiguous, unconscionable, and unenforceable. View "State ex rel. Richmond Am. Homes v. Jefferson County Circuit Court (Sanders)" on Justia Law
J. A. Street & Assocs. v. Thundering Herd Dev.
This case involved a dispute regarding developed property. Developer filed a complaint alleging that the project's general contractor (Contractor) and an engineering firm (Firm) had negligently provided recommendations with respect to site preparation. The circuit court granted partial summary judgment in favor Firm on Contractor's cross-claims against Firm that sought recovery of remediation costs incurred by Contractor, concluding (1) some of Contractor's cross-claims were time-barred by the applicable statute of limitations, and (2) W. Va. Code 55-2-21 did not apply to toll any limitations periods because Contractor's claims were independent causes of action as opposed to cross-claims. The Supreme Court reversed, holding (1) the circuit court prematurely found that section 55-2-21 did not apply because it failed to analyze whether the claims arose from the same transaction or occurrence and, thus, constituted cross-claims or independent causes of action; and (2) genuine issues of material fact existed so as to preclude summary judgment if Contractor's claim was an independent cause of action. Remanded. View "J. A. Street & Assocs. v. Thundering Herd Dev." on Justia Law
Salazar v Novalex Contr. Corp.
Plaintiff commenced a lawsuit against 96 Rockaway, LLC, Novalex Contracting Corp., and T-Construction Co., Inc., alleging among other things, violations of Labor Law 240(a) and 241(6). Discovery and a third-party action ensued. T-Construction moved for summary judgment, seeking dismissal of the complaint, and all cross-claims against it. 96 Rockaway and Novalex cross-moved for identical relief. Supreme Court granted defendants' motions, and dismissed plaintiff's complaint in its entirety. The Appellate Division reversed so much of Supreme Court's order as granted defendants' motions for summary judgment dismissing plaintiff's claims, denied the motions, and reinstated those claims. The court held that, given that Labor Law 240(1) should be construed with a common sense approach to the realities of the workplace at issue, defendants were entitled to summary judgment dismissing that claim. Plaintiff's Labor Law 241(6) cause of action, predicated on a violation of 12 NYCRR 23-1.7(b)(1)(i), failed for similar reasons. Accordingly, the order of the Appellate Division was reversed. View "Salazar v Novalex Contr. Corp." on Justia Law
Albano, et al. v. Shea Homes Ltd P’ship, et al.
The Supreme Court of Arizona answered questions that the court certified to that court. Specifically, it had determined that the rule of American Pipe & Construction Co. v. Utah did not toll the statute of repose for construction-defect claims set forth in Arizona Revised Statutes section 12-552. It also determined that Arizona's saving statute, Ariz. Rev. Stat. 12-504(A), did not operate to save appellants' claims. Both of the parties agreed that the Supreme Court of Arizona's answers to the court's certified questions put an end to the litigation that was before the court. Consequently, the court held that, for the reasons articulated by the Supreme Court of Arizona, appellants' claims were time-barred. Therefore, the judgment of the district court dismissing appellants' complaints was affirmed. View "Albano, et al. v. Shea Homes Ltd P'ship, et al." on Justia Law
Posted in:
Construction Law, U.S. 9th Circuit Court of Appeals
Federated Serv. Ins. Co. v. Alliance Constr.
Danny O'Neall was injured while working for Sadler Line Construction, a subcontractor of Alliance Construction. Sadler had commercial general liability (CGL) coverage with Federated Service Inusrance Company. In the underlying personal injury action, O'Neall sued Alliance and Sadler for negligence. In the instant action, Federated filed a declaratory judgment action against Alliance, alleging that it had no duty to defend or indemnify Alliance against O'Neall's personal injury action. The district court granted summary judgment for Federated. The Supreme Court reversed, holding (1) the parties, by requiring Sadler to name Alliance as an additional insured on its CGL policy, intended that Sadler would insure against loss caused by Alliance's negligence; and (2) Sadler's additional insured endorsement, which provided coverage for liability arising out of Sadler's operations, was broad enough to include coverage for Alliance's negligence even if Sadler was not negligent. Remanded. View "Federated Serv. Ins. Co. v. Alliance Constr." on Justia Law
ASRC Energy Services Power v. Golden Valley Electric
This case arose from an award by Golden Valley Electric Association (GVEA) of two competitively bid construction contracts on its Northern Intertie Project. In November 2001 GVEA awarded Global Power & Communications, LLC (Global) a $39.4 million contract (Contract NI-8) for construction of the Northern Intertie’s Tanana River flats section. Later GVEA awarded Global an approximately $5.3 million contract (Contract NI-9) for construction of the Northern Intertie’s Tanana River crossing and Fairbanks sections. Subsequently, after Global had been awarded NI-9 and before it had completed work on NI-8, Global presented GVEA with requests for additional compensation (RFIs) totaling approximately $2.4 million in connection with NI-8. GVEA responded that it found "no legitimate basis" to justify Global’s RFIs and rejected Global’s request for additional payment. Global also notified GVEA that Global would submit more RFIs, arising out of both NI-8 and NI-9. In all, Global sought additional compensation totaling $5.7 million under the two contracts. GVEA responded to Global denying most of the RFIs but indicated that it would approve a few and consider partial payment for a few others. Global sued, and a trial court ultimately held in GVEA's favor, awarding it costs under both the contract and the applicable state law. Global appealed, arguing among other things, the trial court abused its discretion in ruling in favor of GVEA. Upon review of the lengthy record from the trial court, the applicable legal authority and legislative history, and the two contracts in question, the Supreme Court partly affirmed and partly vacated the trial court's decision. The case was remanded for: (1) a fee determination regarding GVEA’s "UTPA" claim against Global and (2) a new trial on causation and damages relating to GVEA’s breach of NI-9.
View "ASRC Energy Services Power v. Golden Valley Electric" on Justia Law
Harris, Inc. v. Foxhollow Construction & Trucking, Inc.
In 2002, Defendant David Egan, a business manager for Defendant Foxhollow Construction and Trucking, Inc. (Foxhollow), met with Wayne Johnson of Defendant L.N. Johnson Paving, LLC (Johnson) to discuss a bid for excavation and paving work for a new public high school. Foxhollow wanted to bid on the project but lacked the requisite public works license. Johnson thought its license could cover Foxhollow if the two companies submitted a bid in Johnson's name. Egan submitted a subcontract bid in Johnson’s name to Plaintiff Harris, the general contractor for the school project, and was the successful bidder. Over the course of the business relationship, a contract dispute arose. Harris brought this action, alleging that (1) Foxhollow, Johnson, and another subcontractor breached their subcontracts with Harris. Egan filed a counterclaim for indemnification from Harris. The district court dismissed Foxhollow as a party for lack of proof of notice because there was no indication that Foxhollow was ever served. After a bench trial, the court granted Harris’ motion for "directed verdict" as to Egan’s counterclaim. The court concluded however that Harris failed to prove any of its remaining claims against any of the defendants and therefore was not entitled to relief. The court also awarded fees and costs to Johnson. On appeal to the Supreme Court, Harris argued that the district court: (1) erred in concluding Harris failed to prove contract damages; (2) erred in concluding that no defendant was unjustly enriched; (3) erred in concluding that no defendant is liable for fraud; (4) erred in concluding that Harris was not entitled to indemnity; (5) abused its discretion in denying Harris’ motion to amend findings and conclusion; (6) abused its discretion in granting fees and costs to Johnson; and (7) abused its discretion in denying Harris’ motion for a new trial. Upon review, the Supreme Court affirmed the district court's judgment except for its attorney fee awards, which were vacated. View "Harris, Inc. v. Foxhollow Construction & Trucking, Inc. " on Justia Law
Hillside Landscape Construction, Inc. v. City of Lewiston
The issue before the Supreme Court in this appeal was the City of Lewiston's rejection of a bid for a public works project on the grounds that the lowest bidder lacked sufficient experience for the project. In 2009, the City of Lewiston (City) advertised for bids to replace the irrigation system at the City golf course. Hillside Landscape Construction, Inc. (Hillside) desired to bid on the project, but prior to doing so it sent a letter to City stating that if City insisted upon having qualifications other than a current Idaho public works license to bid on the project, the City must follow the Category B procedures set forth in the Idaho Code and pre-qualify the bidders. Hillside asked that the qualification of prior experience be removed. City’s attorney denied the request, stating that City’s specifications and bidding process complied with state law. Hillside and four others submitted bids for the project. City notified the bidders that Hillside Landscape Construction submitted the lowest bid but that the company lacked the required experience specified within the bid documents. City awarded the contract to Landscapes Unlimited, the next lowest bidder. Hillside filed a complaint seeking injunctive relief, declaratory relief, and damages. The district court held that City complied with the bidding statutes, vacated a temporary restraining order, denied the motion for an injunction then dismissed Hillside’s complaint. In its review, the Supreme Court found that because the City chose to follow the "Category A" procedures set forth in the Idaho Code rather than the Category B procedures, the district court erred in holding that City could reject the bid on that ground. The Court therefore vacated the judgment of the district court and remanded the case for further proceedings.
View "Hillside Landscape Construction, Inc. v. City of Lewiston " on Justia Law