Justia Construction Law Opinion Summaries

by
Appellant, an LLC, purchased an "all-risks" insurance policy for an office building it owned from Insurer. The building was significantly damaged after a general contractor Appellant had hired to renovate the building removed the waterproof membrane on the roof and the building was exposed to substantial rainfall. Insurer denied coverage, concluding that the damage did not result from a covered cause of loss. Appellant sued Insurer, alleging that Insurer breached the insurance policy and denied coverage in bad faith. The district court granted summary judgment in favor of Insurer, concluding that the policy unambiguously excluded from coverage for the damage sustained to the building. The Supreme Court affirmed, holding that the damages sustained by the building were excluded from coverage based on the policy's rain limitation and the contractor's faulty workmanship in repairing the roof. In addition, although the doctrine of efficient proximate cause did not provide relief under the facts of this case, the Court adopted the doctrine of efficient proximate cause in Nevada. View "Fourth St. Place v. Travelers Indem. Co." on Justia Law

by
Pro se prisoner Plaintiff Stephen Burnett appealed a district court’s order dismissing his civil-rights complaint and denying his motion to add a defendant. Plaitiff's case arose from a six-week lockdown at the Cimmaron facility in which Plaitiff was incarcerated. "The linchpin of [Plaintiff's] suit was not whether prison officials had the authority to impose a lockdown, but instead whether the restrictions imposed during the lockdown so altered the conditions of his confinement as to violate his constitutional rights." The magistrate judge issued a report and recommendation which concluded that Plaintiff's claims against Warden Joseph Taylor were moot and should have been dismissed without prejudice. As to the director of the Oklahoma Department of Corrections Justin Jones, the magistrate found that even if the claims against him were not moot, those claims should have been dismissed with prejudice because the complaint failed to state any claims upon which relief could be granted and would have been futile to amend. The magistrate also denied Plaintiff's motion to add Warden Robert Ezell as a defendant. The district court adopted the report and recommendation, effectively ending Plaintiff's case. Upon review, the Tenth Circuit partly affirmed, partly reversed the district court (and magistrate judge's) decision. Because the Court's conclusion that the claims against Mr. Jones were moot but for different reasons than the district court, it reversed the decision for dismissal without prejudice. The Court affirmed the district court in all other respects. View "Burnett v. Jones" on Justia Law

by
Appellant Ryan Nelson agreed to perform an errand for his employer, a subcontractor, on the Appellant's day off. While on in the errand, the Appellant was injured at the job site. His employer filed a "notice of controversion" on the basis that Appellant was intoxicated at the time of the injury and his injuries were proximately caused by his intoxication. Appellant sued the general contractor and the Municipality of Anchorage (the owner of the job site) for negligence. The defendants asked the superior court to dismiss the action under the exclusive remedy provision of the Alaska Workers' Compensation Act. The superior court granted summary judgment to the general contractor and the Municipality. Appellant appeals, arguing that lack of a workers' compensation remedy permits him to bring a common law negligence action or, alternatively, that the exclusivity provision of the Alaska Workers' Compensation Act denied him due process. He also argued as a matter of statutory construction, that the Municipality could not be a project owner. Because the worker has not shown that the employer’s controversion of benefits left him to his common law remedies, the Supreme Court determined Appellant's statutory construction and constitutional claims were not ripe. The Court also held that the Municipality could be a project owner. View "Nelson v. Municipality of Anchorage" on Justia Law

by
Excel Construction entered into a contract with the Town of Lovell to replace the Town's water and sewer system mains and service connections. Excel subsequently filed a complaint against the Town of breach of contract and related claims. The district court dismissed Excel's claims for failure to submit a governmental notice of claim that met the itemization requirements of the Wyoming Constitution and Wyoming Governmental Claims Act. The Supreme Court reversed, holding (1) Excel's notice of claim met the itemization requirements of Wyo. Stat. Ann. 1-39-113(b)(iii) and Wyo. Const. art. XVI, 7; (2) Excel complied with the service requirements of Wyo. Const. art. XVI, 7 when it served its notice of claim on the mayor, town administrator, town attorney, and town project engineer; and (3) the district court had jurisdiction to consider Excel's motion for leave to file a second amended complaint. Remanded. View "Excel Constr., Inc. v. Town of Lovell" on Justia Law

by
Border States Paving was awarded the prime contract by the state DOT for a road project. Border States entered into a subcontract with Morris, Inc. for aggregates and work on the project. During work on the project, the DOT orally informed Morris that certain materials passed the soundness test. However, the materials actually failed. Ultimately, the paving was not completed by the seasonal deadline. When the project was completed the next year, the DOT paid Border States in full. Border States withheld several thousand dollars from Morris for costs associated with the project because it believed Morris defaulted in its contractual obligations under the subcontract. Morris brought suit against the DOT, alleging that the DOT breached its express and implied contractual obligations owed to Morris and that the DOT breached its implied contractual obligation of good faith and fair dealing. The circuit court ruled in favor of Morris and awarded Morris damages. The Supreme Court reversed, holding that there was insufficient evidence that the DOT's erroneous pass report proximately damaged Morris where there was no evidence in the record that this error alone caused the project to not get completed by the deadline. View "Morris, Inc. v. State ex rel. Dep't of Transp." on Justia Law

by
After Leon Coleman failed to perform eight construction contracts for detached homes, he was convicted of eight counts of theft by deception and eight counts of failure to escrow under Deposits on New Homes Subtitle (Act). The court of special appeals reversed, holding that the Act did not apply and that there was insufficient evidence of intent to support the theft convictions. The Court of Appeals affirmed, holding (1) the evidence was insufficient to conclude that Coleman intentionally deprived buyers of their property, as required under the theft statute; and (2) the plain meaning of the Act indicated that it did not apply to Coleman. View "State v. Coleman" on Justia Law

by
A construction company (Contractor) entered into a contract with the State to restructure an interstate interchange. The contract contained an incentive clause stating that no incentive payment would be made if work was not completed in its entirety by December 15, 2006. After the work was completed, Contractor filed a complaint alleging that the State had breached the contract by refusing to grant an appropriate time extension of the completion date, the disincentive date, and the incentive date. The claims commission (1) found that the contract contained a latent ambiguity requiring extrinsic evidence to interpret the contract, and (2) considered extrinsic evidence in concluding that Contractor was entitled to the maximum incentive payment and an extension of the contract completion date. The court of appeals affirmed. The Supreme Court reversed, holding (1) the contract was unambiguous and did not permit an extension of the incentive date, and (2) therefore, Contractor was not entitled to an incentive bonus. Remanded. View "Ray Bell Constr. Co. v. State" on Justia Law

by
Plaintiffs sued defendant in contract and tort, alleging that defendant failed to take necessary precautions to protect its premises from water damage. At issue on appeal was the trial judge's decision not to grant prejudgment interest on the amounts that were awarded by the jury to plaintiffs. The court held that plaintiffs were entitled to prejudgment interest as a matter of right and remanded to the Superior Court to determine the amount of prejudgment interest owed. View "Brandywine Smyrna, Inc., et al. v. Millennium Builders, LLC" on Justia Law

by
The Weitz Company sued MacKenzie House and MH Metropolitan for breach of construction contract. Arrowhead and Concorde were third-party defendants. MH Metropolitan counterclaimed for breach of the same contract, seeking liquidated damages and the cost to complete the project. Arrowhead also counterclaimed. The jury returned a verdict for MH Metropolitan, Arrowhead, and Concorde on Weitz's claim. The district court denied post-judgment motions and Weitz appealed. The court held that there was a legally sufficient evidentiary basis for the jury's verdict; the district court properly exercised its discretion in excluding the evidence of other projects; the district court correctly decided that the issue of liquidated damages and completion costs were issues of fact that were properly submitted to the jury; there was a legally sufficient evidentiary basis for the district court to deny judgment as a matter of law for Weitz's breach-of-contract claims against Arrowhead; the district court did no err in refusing to enter a default judgment against Concorde when it failed to appear at trial, or in the alternative, refusing to grant Weitz judgment as a matter of law on its claims against Concorde; and because the district court properly found against Weitz on all issues, there was no reason to consider the issue of vicarious liability. View "The Weitz Co. v. MacKenzie House, et al." on Justia Law

by
This case arose out of the 2007 collapse of the Interstate 35W Bridge. Individual plaintiffs commenced lawsuits against two contractors that performed work on the bridge pursuant to contracts entered into with the State. The contractors brought third-party complaints against Jacobs Engineering Group on the basis that Jacobs' predecessor negligently designed the bridge. One contractor also filed a third-party complaint against the State. The State cross-claimed against Jacobs for contribution, indemnity, and statutory reimbursement. Jacobs moved to dismiss the State's cross-claim as time-barred, arguing that the reimbursement provision of the compensation statutes compensating survivor-claimants of the collapse did not retroactively revive causes of action against Jacobs that had been previously extinguished by a prior version of the statute of repose. The district court denied the motion, and the court of appeals affirmed. The Supreme Court affirmed, holding (1) the provision retroactively revived the State's action for statutory reimbursement against Jacobs; (2) the provision did not violate Jacob's constitutional right to due process; and (3) revival of the action for statutory reimbursement did not unconstitutionally impair Jacobs' contractual obligations. View "In re Individual 35W Bridge Litig." on Justia Law