A dispute arose between SunStone Realty Partners X LLC (SunStone) and Bodell Construction Company (Bodell) over the postjudgment interest rate applied to a domesticated Hawaii judgment in Utah. Following arbitration in Hawaii over construction defects in a condominium development, SunStone obtained a judgment against Bodell exceeding $9.5 million, which it domesticated in Utah. Bodell requested the Utah court to apply Utah's lower postjudgment interest rate instead of Hawaii's higher one. SunStone opposed this, arguing that the Utah Foreign Judgment Act (UFJA) required the application of Hawaii's rate, or alternatively, that their contract or principles of comity mandated the Hawaii rate.The Supreme Court of the State of Utah affirmed the district court's decision to apply Utah's postjudgment interest rate. The court found that the UFJA, which does not specifically address postjudgment interest, instructs Utah courts to treat a foreign domesticated judgment like a Utah judgment for enforcement purposes. Since postjudgment interest serves, at least in part, as an enforcement mechanism, the UFJA requires the imposition of Utah’s postjudgment interest rate. Further, the construction contract did not require the application of the Hawaii postjudgment interest rate. The court did not consider principles of comity because the UFJA mandates a result. View "Sunstone Realty v. Bodell Construction" on Justia Law

by
The Supreme Court reversed the decision of the district court granting summary judgment in favor of Plaintiffs in this action seeking to recover delinquent contributions to various trust funds for construction on a state construction project, holding that the right of action under a payment bond statute extends to any amount due an employee, meaning any amount that is traceable specifically to an employee.One of the subcontractors hired to work on the project failed to make contributions to various trust funds for its employees' work on the project, as required by trust agreements and a collective bargaining agreement. The trusts (Plaintiffs) sought to recover the delinquent contributions from the public payment bond associated with the project by suing Defendant, the surety for the payment bond. The district court granted summary judgment for Plaintiffs. On appeal, the parties disputed whether Utah Code 63G-6-505(4) limits the right of action on a payment bond to amounts due to an employee or encompasses claims for any amounts due for an employee or on the employee's behalf. The Supreme Court reversed, holding that the right of action under the public payment bond statute contemplates recovery of any specific benefit that is due a person in the sense of being traceable to that person. View "McDonald v. Fidelity & Deposit Co. of Maryland" on Justia Law

by
The Supreme Court dismissed the appeal from several orders related to the disposition of mechanic’s liens, holding that the Court lacked appellate jurisdiction because the Utah R. Civ. P. 54(b) certifications were flawed.Acting pursuant to Rule 54(b), the district court sought to certify as final and appealable the orders at issue. Plaintiff appealed those orders to the Supreme Court. The Court, however, found that the Rule 54(b) certifications were flawed and therefore dismissed the appeal, taking the opportunity of this case to readdress and refine the steps that parties and district courts must take to ensure proper certification under Rule 54(b) in order to avoid unnecessary remands. View "Copper Hills Custom Homes, LLC v. Countrywide Bank, FSB" on Justia Law

by
In holding that the successor judge in this case had authority to dismiss Plaintiff’s claims for breach of contract and consequential damages and committed no reversible error by doing so, the Supreme Court repudiated any language in its precedent that suggests that a successor judge on a case is bound by nonfinal decisions and rulings made by his predecessor.Plaintiff, who was hired by the Utah Department of Transportation (UDOT) to work on different construction projects, filed various claims against UDOT and other contractors on the projects. UDOT moved for summary judgment on claims for breach of contract on the “Arcadia” project and claims seeking consequential damages. Judge Kennedy, the original judge assigned to the case, denied both motions. Judge Kennedy was then replaced in this case by Judge Harris. Judge Harris ultimately dismissed Plaintiff’s claims for breach of contract and consequential damages. Plaintiff filed this interlocutory appeal, arguing that Judge Harris violated the so-called coordinate judge rule, which Plaintiff alleged limits the discretion of a successor judge to revisit decisions of a predecessor. The Supreme Court disagreed, holding (1) a successor judge has the same power to review nonfatal decisions that a predecessor would have had; and (2) Judge Harris did not commit reversible error by dismissing the claims at issue. View "Build v. Utah Department of Transportation" on Justia Law

by
An action is commenced under Utah law not by the filing of a motion for leave to amend but by the filing of a complaint.Many years after filing suit against other defendants a homeowners association sued the general contractor on a construction project. By the time the homeowners association finally filed an amended complaint naming the general contractor the statute of repose had run on six buildings in the project. The general contractor filed motion for summary judgment, asserting that the claims against it were time barred. The district court denied the motion, concluding that the amended complaint related back to the date the motion for leave to amend was filed. The Supreme Court reversed, holding that the homeowners association’s claims were time barred because no viable complaint was filed within the repose period and the complaint did not relate back to a timely pleading. View "Gables v. Castlewood" on Justia Law

by
The Supreme Court reversed the decision to award prejudgment interest to LeGrand and concluded that Celtic Bank was the prevailing party on the prejudgment interest issues.LeGrand Johnson Construction Company filed an action seeking to enforce its mechanic’s lien on property owned by B2AC, LLC for the unpaid value of construction services, and Celtic Bank, B2AC’s lender, sought to foreclose on the same property after B2AC failed to pay on its loan. The action resulted in a lien for $237,294 and an award of attorney fees and costs. Thereafter, the district court determined that LeGrand’s lien, rather than Celtic Bank’s lien, had priority and awarded LeGrand attorney fees and costs. The court then ruled that LeGrand was entitled to recover eighteen percent in prejudgment and postjudgment interest from Celtic Bank based on LeGrand’s contract with B2AC. The Supreme Court (1) reinforced its holding in Jordan Construction, Inc. v. Federal National Mortgage Ass’n, 408 P.3d 296 (Utah 2017), that prejudgment interest is not available under the 2008 version of the Utah Mechanic’s Lien Act; and (2) vacated the attorney fee award because it was based, in part, on the notion that LeGrand had succeeded in establishing its right to prejudgment interest. View "LeGrand Johnson Construction Co. v. Celtic Bank Corp." on Justia Law

by
In this action alleging, inter alia, breaches of fiduciary duty and the implied warranty of habitability, the Supreme Court affirmed the district court’s grant of summary judgment and a directed verdict against The Gables at Sterling Village Homeowner’s Association (the Association) but vacated the district court’s award of attorney fees.The Association filed this action against the property developer who built the Gables at Sterling Village, the builders, and their principles after property owners began to notice problems in the planned unit development. The property owner asserted a counterclaim for indemnification. The district court granted (1) summary judgment against the Association, concluding that the Association lacked contractual privity with the property developer; (2) the property developer’s motion for directed verdict on the Association’s claim for breach of fiduciary duty; and (3) the property developer’s post-trial motion for indemnification of attorney fees. The Supreme Court affirmed in part and vacated in part, holding (1) the district court did not err in granting summary judgment and directed verdict; but (2) the property developer should have tried his indemnification claim rather than raise it by post-trial motion. View "Gables at Sterling Village Homeowners Ass’n v. Castlewood-Sterling Village I, LLC" on Justia Law

by
In this action alleging, inter alia, breaches of fiduciary duty and the implied warranty of habitability, the Supreme Court affirmed the district court’s grant of summary judgment and a directed verdict against The Gables at Sterling Village Homeowner’s Association (the Association) but vacated the district court’s award of attorney fees.The Association filed this action against the property developer who built the Gables at Sterling Village, the builders, and their principles after property owners began to notice problems in the planned unit development. The property owner asserted a counterclaim for indemnification. The district court granted (1) summary judgment against the Association, concluding that the Association lacked contractual privity with the property developer; (2) the property developer’s motion for directed verdict on the Association’s claim for breach of fiduciary duty; and (3) the property developer’s post-trial motion for indemnification of attorney fees. The Supreme Court affirmed in part and vacated in part, holding (1) the district court did not err in granting summary judgment and directed verdict; but (2) the property developer should have tried his indemnification claim rather than raise it by post-trial motion. View "Gables at Sterling Village Homeowners Ass’n v. Castlewood-Sterling Village I, LLC" on Justia Law

by
The Supreme Court affirmed the district court’s dismissal of Homebuyer's construction defect claims against the Contractor that built his home on the ground that Homebuyer was not in privity with Contractor and had no right to sue as an assignee.Property Owner entered into an agreement with Contractor to build a house on the property and then assigned its rights to the home and the construction agreement to Company. Company then sold the home to Homebuyer but did not assign its interest in the construction agreement to Homebuyer. After discovering several purported construction defects, Homebuyer sued Contractor for breach of the construction agreement and breach of warranty. Homeowner was subsequently assigned Company’s interest in claims Company may assert against Contractor. The district court granted summary judgment to Contractor. The Supreme Court affirmed, holding that Homebuyer had no right to sue under Utah Code 78B-4-513 because he did not acquire a right to sue for breach of contract or warranty as an assignee - either at the time he purchased the home or at the time of the assignment. View "Tomlinson v. Douglas Knight Construction, Inc." on Justia Law

by
The Supreme Court reversed the district court’s denial of the motion to dismiss the lawsuit brought by several property developers (Developers) alleging that the City of West Jordan violated statutory provisions that regulate how a municipality may spend impact fees collected from developers. The court held (1) Developers had standing to challenge the constitutionality of the impact fees they were assessed; (2) Developers failed to state a takings claim for which relief can be granted because Developers’ allegations that West Jordan either failed to spend impact fees within six years or spent the fees on impermissible expenditures were inadequate to support a constitutional takings claim; and (3) Developers did not have standing to bring a claim in equity. View "Alpine Homes, Inc. v. City of West Jordan" on Justia Law