Justia Construction Law Opinion Summaries

Articles Posted in US Court of Appeals for the Fifth Circuit
by
In March 2013, Woodsboro Farmers Cooperative contracted with E.F. Erwin, Inc. to construct two grain silos. Erwin subcontracted AJ Constructors, Inc. (AJC) for the assembly. AJC completed its work by July 2013, and Erwin finished the project in November 2013. However, Woodsboro noticed defects causing leaks and signed an addendum with Erwin for repairs. Erwin's attempts to fix the silos failed, leading Woodsboro to hire Pitcock Supply, Inc. for repairs. Pitcock found numerous faults attributed to AJC's poor workmanship, necessitating complete deconstruction and reconstruction of the silos, costing Woodsboro $805,642.74.Woodsboro sued Erwin in Texas state court for breach of contract, and the case went to arbitration in 2017. The arbitration panel found AJC's construction was negligent, resulting in defective silos, and awarded Woodsboro $988,073.25 in damages. The Texas state court confirmed the award in September 2022. In December 2018, TIG Insurance Company, Erwin's insurer, sought declaratory relief in the United States District Court for the Southern District of Texas, questioning its duty to defend and indemnify Erwin. The district court granted TIG's motion for summary judgment on the duty to defend, finding no "property damage" under the policy, and later ruled there was no duty to indemnify, as the damage was due to defective construction.The United States Court of Appeals for the Fifth Circuit reviewed the case. The court found that there were factual questions regarding whether the damage constituted "property damage" under the insurance policy, as the silos' metal parts were damaged by wind and weather due to AJC's poor workmanship. The court determined that the district court erred in granting summary judgment for TIG and concluded that additional factual development was needed. The Fifth Circuit reversed the district court's decision and remanded the case for further proceedings. View "TIG Insurance Company v. Woodsboro Farmers Coop" on Justia Law

by
A sub-subcontractor, Diamond Services Corporation, entered into a contract with Harbor Dredging, a subcontractor, to perform dredging work in the Houston Ship Channel. The prime contract for the project was awarded to RLB Contracting by the U.S. Army Corps of Engineers, and RLB obtained a surety bond from Travelers Casualty and Surety Company of America. During the project, unexpected site conditions, including the presence of tires, caused delays and increased costs. Diamond continued working based on an alleged agreement that it would be compensated through a measured-mile calculation in a request for equitable adjustment (REA) submitted by RLB to the Corps. However, RLB later settled the REA for $6,000,000 without directly involving Diamond in the negotiations and issued a joint check to Harbor and Diamond for $950,000.The United States District Court for the Southern District of Texas dismissed some of Diamond's claims, including those for unjust enrichment and express contractual claims against RLB, but allowed Diamond's quantum meruit claim to proceed. The court also denied Travelers' motion to dismiss Diamond's Miller Act claims but required Diamond to amend its complaint to include proper Miller Act notice, which Diamond failed to do timely. Subsequently, the district court granted summary judgment in favor of RLB and Harbor, dismissing Diamond's remaining claims and striking Diamond's untimely second amended complaint.The United States Court of Appeals for the Fifth Circuit reviewed the case. The court affirmed the district court's summary judgment against Diamond's quantum meruit claims, holding that the express sub-subcontract covered the damages Diamond sought and that Diamond failed to provide evidence of the reasonable value of the work performed. The court also affirmed the dismissal of Diamond's Miller Act claim, as the damages sought were not recoverable under the Act. The court dismissed Diamond's appeal regarding the tug-expenses claim due to untimeliness. View "Diamond Services v. RLB Contracting" on Justia Law

by
Keiland Construction, L.L.C. entered into a construction subcontract with Weeks Marine, Inc. for a project in Louisiana. Weeks terminated the contract for convenience, leading to a dispute over compensation. Keiland submitted pay applications and demobilization costs, which Weeks partially paid. The disagreement centered on whether the contract required lump-sum payments for work completed before termination or if it converted to a cost-plus basis upon termination.The United States District Court for the Western District of Louisiana held a bench trial and found the contract ambiguous. It construed the ambiguity against Keiland, the drafter, and ruled in favor of Weeks. The court awarded Keiland damages based on Weeks’s interpretation of the contract but denied Keiland’s claims for direct employee and demobilization costs. The court also awarded Weeks attorneys’ fees and costs, though less than requested, and denied Weeks’s motion for post-offer-of-judgment fees and costs.The United States Court of Appeals for the Fifth Circuit reviewed the case. It affirmed the district court’s findings, agreeing that the contract was ambiguous and that the ambiguity should be construed against Keiland. The appellate court upheld the district court’s rulings on damages, attorneys’ fees, and costs, including the denial of post-offer-of-judgment fees and costs. The court also affirmed the award of prejudgment interest to Keiland, finding no abuse of discretion.In summary, the Fifth Circuit affirmed the district court’s judgment in all respects, including the interpretation of the contract, the award of damages, attorneys’ fees, costs, and prejudgment interest. View "Keiland Construction v. Weeks Marine" on Justia Law

by
The case revolves around a dispute between SR Construction (SRC), a construction company, and RE Palm Springs II, L.L.C. (RPS), a company formed to take title to a hotel property. SRC was hired to build a hotel in California but was terminated before completion, leaving it with a demand for $14 million in unpaid work. After several failed attempts to recover its dues, SRC held onto certain personal property left over from the hotel project. The bankruptcy court ordered SRC to turn over the personal property, which SRC appealed.The lower courts had a series of interactions with this case. The bankruptcy court initially ordered SRC to turn over the personal property. SRC appealed this decision, challenging the bankruptcy court's power to order the turnover and the validity of the most recent hotel owner's claim to the personal property. The district court affirmed the bankruptcy court's decision, concluding that the bankruptcy court had jurisdiction to interpret and enforce the Sale Order. It also affirmed the bankruptcy court's conclusion that Hall had obtained title to the Personal Property and had not waived its right to the Personal Property by taking it "as is."The United States Court of Appeals for the Fifth Circuit affirmed the lower courts' decisions. The court concluded that the bankruptcy court's order was part of its undisputed power to order the sale of a bankruptcy debtor's assets. It also rejected SRC's arguments about ownership of the assets in this case. The court found that the bankruptcy court had jurisdiction to enter the Turnover Order because that order interpreted and enforced the Sale Order. It also concluded that because the Turnover Order is integral to and inseparable from RPS's bankruptcy, it is a core matter. Therefore, issuing the Turnover Order was entirely within the bankruptcy court's authority. The court also affirmed the conclusion that title to the Personal Property passed from SRC to Palm Springs, then to RPS, and finally to Hall. View "SR Construction v. RE Palm Springs II" on Justia Law

by
In this case, the United States Court of Appeals for the Fifth Circuit considered an appeal by Colony Insurance Company against First Mercury Insurance Company related to a settlement agreement for an underlying negligence case. Both companies had consecutively insured DL Phillips Construction, Inc. (DL Phillips) under commercial general liability insurance policies. After the settlement, Colony sued First Mercury, arguing that First Mercury needed to reimburse Colony for the full amount of its settlement contribution, as it contended that First Mercury's policies covered all damages at issue. The district court granted summary judgment in favor of First Mercury, prompting Colony's appeal.In the underlying negligence case, DL Phillips was hired to replace the roof of an outpatient clinic in Texas. Shortly after completion, the roof began leaking, causing damage over several months. The clinic's owner sued DL Phillips for various claims, including breach of contract and negligence. A verdict was entered against DL Phillips for over $3.7 million. Both Colony and First Mercury contributed to a settlement agreement, and then Colony sued First Mercury, arguing it was responsible for all the property damage at issue.The appellate court held that under the plain language of First Mercury's policies and relevant case law, First Mercury was only liable for damages that occurred during its policy period, not all damages resulting from the initial roof defect. The court also found that Colony failed to present sufficient evidence to create a genuine dispute of material fact about whether there was an unfair allocation of damages, which would be necessary for Colony's contribution and subrogation claims. As such, the court affirmed the district court's decision to grant summary judgment in favor of First Mercury and denied summary judgment for Colony. View "Colony Insurance Company v. First Mercury Insurance Company" on Justia Law

by
The Housing Authority of New Orleans (HANO) agreed to pay Parkcrest $11 million to build affordable housing. Liberty was Parkcrest’s surety. HANO terminated Parkcrest before the project was done. Parkcrest sued, alleging breach of contract. Liberty and HANO executed a “Takeover Agreement,” incorporating the original contract; Liberty stepped into Parkcrest’s shoes to finish the project. Liberty hired Parkcrest as its completion contractor. HANO claimed that Liberty had forfeited any right to continue working on the project and requested that it relinquish control of the site. Liberty claimed the termination was wrongful. Rather than following the contract’s dispute resolution procedures, Liberty filed a complaint-in-intervention in the HANO-Parkcrest litigation.The district court concluded that HANO had breached the Takeover Agreement and the underlying HANO Contract by terminating Liberty for convenience after Liberty had substantially completed the project, awarded Liberty and Parkcrest damages, and held HANO liable to Liberty for attorney’s fees, but left those fees unquantified. The Fifth Circut affirmed but concluded it lacked jurisdiction to consider the fee award because a fee award is not a final judgment under 28 U.S.C. 1291 until reduced to a sum certain. The district court then awarded Liberty $526,192.25 in fees. The Fifth Circuit reversed. Liberty’s claim for fees arises from the contract, which authorizes fee-shifting “upon the receipt by [HANO] of a properly presented claim.” Liberty breached the contract’s dispute-resolution procedures, this breach was unexcused, so Liberty is entitled to nothing. View "Liberty Mutual Insurance Co. v. Housing Authority of New Orleans" on Justia Law

by
In 2012, the Archdiocese purchased a roof membrane system from Siplast, for installation at a Bronx high school. Siplast guaranteed that the system would “remain in a watertight condition for a period of 20 years.” In 2016, school officials observed water damage in the ceiling tiles after a rainstorm and notified the installing contractor and Siplast. A designated Siplast contractor unsuccessfully attempted to repair the damage and prevent leaks. The Archdiocese ultimately obtained an estimate for remediation and replacement of approximately $5,000,000.The ensuing lawsuit alleged “Breach of the Guarantee” Siplast submitted a claim to its insurer, EMCC, asserting coverage under commercial general liability policies that covered “property damage” caused by an “occurrence,” defined as “an accident, including continuous or repeated exposure to substantially the same general harmful conditions.” The policies were subject to exclusions for “Your Product/Your Work” and “Contractual Liability.” The district court granted EMCC summary judgment, finding that while the complaint did allege property damage that was caused by an “occurrence,” the alleged damage fit within the Your Product/Your Work Exclusion. The Fifth Circuit reversed, finding that EMCC had a duty to defend. The underlying complaint contains allegations of damage to property other than Siplast’s roof membrane as part of the claim against Siplast; the exclusion does not apply. View "Siplast, Inc. v. Employers Mutual Casualty Insurance Co." on Justia Law

by
A federal district court in Texas does not have jurisdiction to vacate an arbitration award in Florida. The Fifth Circuit affirmed the district court's dismissal of the action based on lack of personal jurisdiction over the subcontractors. The court held that the subcontractors did not have the minimum contacts in Texas such that a Texas court could exercise specific personal jurisdiction over them. In this case, the place of contractual performance was Florida—not Texas, after plaintiff allegedly failed to pay its subcontractors' invoices, the parties met in Florida to discuss the dispute, then they arbitrated the dispute in Florida, and Florida's courts have determined that Florida is a proper venue for the subcontractors to seek enforcement of the arbitration awards. Therefore, the subcontractors did not purposefully avail themselves to being sued in Texas courts. View "Sayers Construction, LLC v. Timberline Construction, Inc." on Justia Law

by
Waypoint, the project owner, entered into a construction contract with Team Contractors, the general contractor, and entered into an architectural contract with HCA. HCA then retained KLG as the project's engineer. Team filed suit and subsequently prevailed against the engineers and architects for negligence, but not against the owner for breach of contract. After a finding that the initial verdict had an irreconcilable conflict, a second trial was held just on the breach of contract claim. The jury then reached a verdict for the general contractor, and the owner appealed.The Fifth Circuit vacated the district court's judgment and remanded for the district court to reinstate the original verdict. The court held that if the answers to written questions require jurors to apply the instructed law to their fact-findings, thereby fully explaining who prevails on all claims against a single defendant, and if relevant, the amount of any monetary award, that is sufficient for a Federal Rule of Civil Procedure 49(b) verdict. Though in this case the jurors were not given, as Rule 49(b) states, "forms for a general verdict" and also for answers to written questions, jurors applied their instructions on the law to their fact finding and found there had been no breach of contract. The court held that the result fully resolved the claim against Waypoint. The court stated that the general verdict is incomplete in Rule 49(b) terms, but it is sufficient. The court also held that Team waived any argument to have the verdict set aside. Finally, the court remanded for the district court to consider attorneys' fees. View "Team Contractors, LLC v. Waypoint NOLA, LLC" on Justia Law

by
D2 filed suit for breach of contract, quantum meruit, violations of the Texas prompt pay statute, and to foreclose on a statutory and constitutional lien. Thompson, in turn, alleged that D2 breached the excavation contract between the parties. The district court held in D2's favor on all claims and ordered Thompson to pay for unpaid work and for "excess" excavating work, as well as interest and attorneys' fees.The Fifth Circuit held that the district court did not clearly err by finding that management of the site was so deficient that D2 had to regrade the same areas as many as six times and was unable to complete its work in other parts of the site, justifying D2's cessation of work. Therefore, the court affirmed the district court's judgment for the $81,068 in unpaid work and the related prompt payment statute and lien remedies for that breach of contract. However, the court held that neither breach of contract nor quantum meruit allows D2 to recover for "excavation of unanticipated excess soil." Thus, the court reversed the district court's judgment of $257,588.53 for the "excavation of unanticipated excess soil" and rendered judgment for Thompson on those breach of contract and quantum meruit claims. The court remanded for modification of the judgment. View "D2 Excavating, Inc. v. Thompson Thrift Construction, Inc." on Justia Law