Justia Construction Law Opinion Summaries

Articles Posted in Real Estate & Property Law
by
The eight-acre San Jose City View Plaza contained nine buildings, including the Bank, built in 1971, which later housed the County Family Court. The Bank was eligible for listing on the California Register of Historic Resources and National Register of Historic Places. The site development permit provided for the demolition of all structures, followed by the construction of three, 19-story office towers, 65,000 square feet of ground-floor retail, and five levels of underground parking.The city council certified the Downtown Strategy 2040 final environmental impact report under the California Environmental Quality Act (Pub. Resources Code 21000 (CEQA)), finding that the Plaza required a supplemental environmental impact report (SEIR). The draft SEIR identified the proposed demolition of the buildings as a “significant unavoidable impact” and presented mitigation measures, to document the structures, advertise their availability for relocation, and otherwise make the structures available for salvage. The city voted not to designate the Bank as a city landmark and approved the permit, certifying the Final SEIR and rejecting project alternatives as infeasible because the “anticipated economic, social, and other benefits” of the project outweighed its “significant and unavoidable impacts.”After the trial court denied a mandate petition filed by opponents, the Bank was demolished. The court of appeal affirmed. The Final SEIR’s discussion of mitigation for the unavoidable loss of significant historic resources complied with CEQA. San Jose did not abuse its discretion by briefly considering and rejecting additional mitigation measures. View "Preservation Action Council of San Jose v. City of San Jose" on Justia Law

by
Nashville passed a “sidewalk ordinance.” To obtain a building permit, an owner must grant an easement across their land and agree to build a sidewalk on the easement or pay an “in-lieu” fee that Nashville will use to build sidewalks elsewhere.In a challenge to the ordinance under the Fifth Amendment’s Takings Clause, the landowner plaintiffs asked the court to apply the “unconstitutional-conditions” test that the Supreme Court adopted in 1987 to assess conditions on building permits (Nollan v. California Coastal Commission). Nashville argued that the Court has applied Nollan’s test only to ad hoc administrative conditions that zoning officials impose on specific permit applicants—not generally applicable legislative conditions that city councils impose on all permit applicants. For legislative conditions, Nashville argued in favor of the application of the deferential “balancing” test that the Court adopted to assess zoning restrictions in “Penn Central” (1978). The district court granted Nashville summary judgment.The Sixth Circuit reversed, agreeing with the landowners. Nothing in the relevant constitutional text, history, or precedent supports Nashville’s distinction between administrative and legislative conditions. Nollan’s test should apply to both types, including those imposed by the sidewalk ordinance. View "Knight v. e Metropolitan Government of Nashville and Davidson County" on Justia Law

by
Allie Construction, Inc., obtained writs of garnishment against the estate of Willard Mosier one day shy of the 20th anniversary of obtaining a judgment against his widow Debra Mosier, a beneficiary of his estate. The Alabama Supreme Court found Allie Construction properly commenced an enforcement action, and that action should be allowed to proceed. In reaching a contrary conclusion, the Supreme Court found the circuit court erred. The circuit court judgment was reversed and the matter remanded for further proceedings. View "Allie Construction, Inc. v. Mosier" on Justia Law

by
In 1985, Palo Alto established the Commercial Downtown zoning district with parking regulations that allowed for “payment of an in-lieu monetary contribution to the city to defray the cost” of new, off-site parking spaces for “sites which would otherwise be precluded from development due to parking constraints.” In 1995, the city recognized the need to further mitigate insufficient downtown parking facilities and established an in-lieu parking fee for new, nonresidential development in the “University Avenue parking assessment district.” City staff has periodically submitted “five-year findings” on the parking fund, consistent with the Mitigation Fee Act (Gov. Code, 66000).The plaintiffs, developers who paid the fees as a condition of approval of a building project, sued, seeking a refund of their unexpended fees. The city argued that the fee was not subject to the Mitigation Fee Act; that the five-year finding and refund provisions did not apply; that, even if the Act did apply, the claim was barred by the statute of limitations; and that it complied with the Act’s requirements by belatedly adopting five-year findings.The court of appeal reversed the trial court, ordering a refund of the plaintiffs’ unexpended fees. The fee is subject to the Act, and the action is not time-barred. The failure to timely make five-year findings triggered the refund provision. Section 65010(b), does not require that plaintiffs make an independent showing of prejudice for a violation of section 66001(d) View "Hamilton and High, LLC v. City of Palo Alto" on Justia Law

by
Government Code 65913.4 provides for streamlined, ministerial approval of affordable housing projects meeting specified requirements. Berkeley denied Ruegg’s application for ministerial approval of a mixed-use development under section 65913.4. Ruegg alleged violations of both section 65913.4 and the Housing Accountability Act (HAA, section 65589.5). The trial court found Berkeley was not required to approve the proposed project under section 65913.4 and denied Ruegg’s petition without reaching the HAA issues. The court of appeal, without addressing the HAA, directed the trial court to grant the writ petition.On remand, the trial court reasoned that it could not avoid ruling on the HAA issues. With respect to the section 65913.4 claim the court ordered Berkeley to issue the permits; it set a briefing schedule and hearing date concerning the HAA issues. The court of appeal declined to prohibit that hearing. Berkeley issued the permit. After a hearing, the trial court found that the disapproval of the application violated the HAA and that Ruegg was entitled to the “albeit duplicative” injunctive relief. The court of appeal affirmed, finding that the trial court had jurisdiction to address the HAA issue, which was not forfeited nor rendered moot by the prior order. View "Ruegg & Ellsworth v. City of Berkeley" on Justia Law

by
BrunoBuilt, Inc., was constructing a custom home on a vacant lot in 2016 when a landslide occurred beneath the Terra Nativa subdivision in the Boise foothills. Following damage to the lot, BrunoBuilt filed a professional negligence suit against numerous engineers and engineering firms involved in the construction of the subdivision, arguing that they failed to identify preexisting landslide conditions and other geological circumstances that made residential development unsafe at this site. In the fall of 2018, BrunoBuilt discovered additional damage to the finished custom home itself. It then brought suit against additional defendants, including Briggs Engineering, Inc., and Erstad Architects. Briggs Engineering moved for summary judgment, which the district court granted. The court concluded that BrunoBuilt’s action was time barred by the two-year statute of limitations under Idaho Code section 5-219(4). BrunoBuilt appealed this decision, arguing that the malpractice claim did not begin to accrue until there was damage to the custom home, rather than just the land. To this the Idaho Supreme Court disagreed with BrunoBuilt’s analysis and affirmed the district court that BrunoBuilt’s claim was time barred. View "Brunobuilt, Inc. v. Briggs Engineering, Inc." on Justia Law

by
Plaintiff River’s Side at Washington Square Homeowners Association was established to manage a development consisting of 25 residential units and common areas. It sued Defendants River’s Side LLC et al. for construction defects in the residential units. Defendants demurred to six of the seven causes of action asserted against them, arguing a homeowners association lacked standing to sue on behalf of its members for defects in residential units that it did not own and had no obligation to repair. Plaintiff alleged it had standing to bring this action on behalf of its members pursuant to Civil Code section 945, Civil Code section 5980, and Code of Civil Procedure section 382. The trial court sustained the demurrer without leave to amend, holding that Plaintiff lacked standing under Civil Code sections 945 and 5980, and that Code of Civil Procedure section 382 was inapplicable. Because the order sustaining the demurrer left one cause of action remaining, it was not immediately appealable, and Plaintiff thus challenged the order by petition for writ of mandate. The Court of Appeal concluded Plaintiff had standing to bring claims for damages to the common areas pursuant to Civil Code sections 945 and 5980, and that it at least nominally alleged such damages. The Court further concluded Plaintiff might have standing to bring claims for damages to the residential units that sound in contract or fraud if it could meet the requirements for bringing a representative action pursuant to Code of Civil Procedure section 382. The Court also determined Plaintiff should have been granted leave to amend to cure any standing defect. The Court thus granted the petition for mandamus relief and directed the trial court to reversed its order granting the demurrer. View "River's Side at Washington Sq. Homeowners Assn. v. Superior Court" on Justia Law

by
In this case concerning the meaning and application of a standard title insurance policy exclusion (Exclusion 3(a)) designed to cover any defects, encumbrances, or adverse claims created or suffered by the insured in the context of construction lending, holding that this Court's opinion in First American Title Insurance Co. v. Action Acquisitions, LLC, 218 Ariz. 394 (2008), sets forth the proper interpretation and application Exclusion 3(a).In its underlying rulings, the trial court invoked Action Acquisitions to interpret Exclusion 3(a) in the construction lending context. The court of appeals reversed, instead applying the bright-line rule articulated in BB Syndication Services, Inc. v. First American Title Insurance Co., 780 F.3d 825 (7th Cir. 2015). The Supreme Court reversed in part and vacated the judgment in part, holding (1) this Court adopts Action Acquisitions' causation test for Exclusion 3(a)'s applicability; and (2) the court of appeals erred in applying the BB Syndication approach. View "Fidelity National Title Insurance Co. v. Osborn III Partners, LLC" on Justia Law

by
The Supreme Court affirmed the judgment of the appellate court affirming the judgment of the trial court denying a property owner's motion for summary judgment in the underlying dispute with a contractor arising from a construction project, holding that the trial court correctly denied Defendants' motion for summary judgment.Defendants hired Plaintiff to serve as a general contractor to renovate a home located on Greenwich property. Defendants later terminated their contractual relationship with Plaintiff. Plaintiff served mechanics' liens on Defendants and brought this action to foreclose its lien. Defendants moved for summary judgment, arguing that the trial court was required to give res judicata effect to the findings of the trial court in a prior action between Plaintiff and one of Defendants' subcontractors. The trial court denied Defendants' summary judgment motion, determine that all four required elements of res judicata were not met. The appellate court affirmed. The Supreme Court affirmed, holding that the appellate court did not err in holding that the presumption of privity that the Supreme Court held to apply in Girolametti v. Michael Horton Associates, Inc., 208 A.3d 1223 (Conn. 2019), did not apply to the instant case. View "Strazza Building & Construction, Inc. v. Harris" on Justia Law

by
This case involved promises made and broken to homeowners by a developer and its affiliated entities. A jury returned verdicts on several causes of action in favor of the homeowners, and the developer appealed. The court of appeals initially upheld the jury's verdict for $1.75 million on the homeowners' breach of fiduciary claim and a verdict for $10,000 on a breach of contract claim by an individual homeowner. Thereafter, upon petitions for rehearing, the court of appeals completely reversed course, dismissing all of the homeowners' claims as a matter of law and reversing and remanding the breach of contract claim by the individual homeowner. The South Carolina Supreme Court granted certiorari and affirmed in part and reversed in part, thus reinstating the jury's verdicts. The Court: (1) reversed the court of appeals' ruling on the statute of limitations because the issue as to when Homeowners had adequate notice to begin the limitations clock was properly presented to the jury and resolved by it; (2) found any procedural issues related to the derivative claims either (a) moot as the HOA was realigned as a plaintiff and the trial court explicitly found it adopted its own claims against the Developers, or (b) demand was saved by futility due to the Developer's continuing veto power; (3) held that Developers breached the fiduciary duties owed to Homeowners; (4) reversed the court of appeals' decision that Developers could not be amalgamated, as there was more than enough evidence of bad faith, abuse, fraud, wrongdoing, or injustice resulting from the blurring of the entities' legal distinctions; and (5) affirmed the court of appeals that the recreational easement was invalid. View "Walbeck, et al. v. The I'On Company" on Justia Law