Justia Construction Law Opinion Summaries
Articles Posted in Real Estate & Property Law
Weitz Co., LLC v. Heth
Developer obtained a loan from Bank to construct a commercial and condominium project. Bank secured its loan with two deeds of trust, the first of which attached before construction began on the project. Developer failed to pay the general contractor (Contractor) several million dollars for the project, and after Developer had sold many of the units, Contractor recorded a mechanics’ lien against the project. Contractor then sought to foreclose on its lien against Developer, the unit owners, and their lenders. The Owners and Lenders contested the foreclosure, arguing that they were equitably subrogated to Bank’s first deed of trust and thus had priority over Contractor’s mechanics’ lien. The trial court concluded that Contractor’s lien had priority. The Supreme Court reversed, holding (1) Ariz. Rev. Stat. 33-992(A), which gives mechanics’ liens priority over liens recorded after construction begins on real property, does not preclude assignment by equitable subrogation of lien that attached before construction began on the project; and (2) when a single mortgage burdens multiple parcels, a third party may be entitled to equitable subrogation when that party has paid a pro rata amount of the obligation and obtained a full release of the parcel at issue from the mortgage. Remanded. View "Weitz Co., LLC v. Heth" on Justia Law
Nautilus Ins. Co. v. Bd. of Dirs. of Regal Lofts Condo Ass’n
The Developer converted a vacant building into a residential condominium by gutting and refitting it. The Developer purchased Commercial Lines Policies covering bodily injury and property damage from Nautilus, covering periods from June 1998 through June 2000. The policies define occurrence as “an accident, including continuous or repeated exposure to substantially the same general harmful conditions,” but do not define accident. The policies exclude damage to “that particular part of real property on which you or any contractors or subcontractors working directly or indirectly on your behalf are performing operations, if the ‘property damage’ arises out of those operations;” eliminate coverage for damage to “that particular part of any property that must be restored, repaired or replaced because ‘your work’ was incorrectly performed on it;” and contain an endorsement entitled “Exclusion—Products-Completed Operations Hazard.’ Construction was completed in 2000; the Developer transferred control to a board of owners. By May 2000, one homeowner was aware of water damage. In 2005, the Board hired a consulting firm, which found that the exterior brick walls were not fully waterproofed and concluded that the deterioration had likely developed over many years, even prior to the condominium conversion, but that the present water penetration was the result of inadequate restoration of the walls. The Board sued the Developer. Nautilus denied coverage and obtained a declaratory judgment. The Seventh Circuit affirmed, reviewing the policy and finding that the shoddy workmanship, of which the board complained, was not covered by the policies; that Nautilus did not unduly delay pursuing its declaratory suit; and that the alleged damage to residents’ personal property occurred after the portions of the building were excluded from coverage.View "Nautilus Ins. Co. v. Bd. of Dirs. of Regal Lofts Condo Ass'n" on Justia Law
Simmons Self-Storage Partners v. Rib Roof, Inc.
Respondent supplied steel for projects on six properties. Respondent was not fully paid for the steel delivered to the properties, and consequently, Respondent perfected mechanics’ liens on the six properties. Respondent then filed a complaint for foreclosure against each property. Thereafter, surety bonds were posted and recorded for four properties. Respondent then amended its complaint to dismiss its lien foreclosure claims against those four properties, replacing them with claims against the sureties and principles on the surety bonds. The district court concluded that Respondent established liens on the six properties. The district court ordered the sale of all six properties without demonstrating that each surety bond was insufficient to pay the sum due on its respective property. The Supreme Court affirmed in part and reversed in part, holding (1) a materialman has a lien upon a property and any improvements thereon for which he supplied materials in the amount of the unpaid balance due for those materials; (2) in this case, Respondent established a materialman’s lien on each of the six properties for the unpaid balance due on the steel delivered; and (3) the district court erred by ordering the sale of all six properties. View "Simmons Self-Storage Partners v. Rib Roof, Inc." on Justia Law
Posted in:
Construction Law, Real Estate & Property Law
Byrd Underground, LLC v. Angaur, LLC
The United States Bankruptcy Court for the District of Nevada certified three questions of law to the Supreme Court regarding the mechanic’s lien priority law, specifically, the visible-commencement-of-construction aspect of the law, which states that a mechanic’s lien takes priority over other encumbrances on a property that are recorded after construction of a work of improvement visibly commences. The Supreme Court answered (1) the Court’s holding in J.E. Dunn Northwest, Inc. v. Corus Construction Venture, LLC does not preclude a trier of fact from finding that grading property for a work of improvement constitutes visible commencement of construction; (2) the contract dates and permit issuance dates are irrelevant to the visible-commencement-of-construction test, even in this case where dirt material was placed on a future project site before building permits were issued and the general contractor was hired; and (3) the Court declined to answer the third certified question because it asked the Court to make findings of fact that should be left to the bankruptcy court. View "Byrd Underground, LLC v. Angaur, LLC" on Justia Law
Shafer Electric & Construction v. Mantia
In August, 2010, Appellants, Washington County residents Raymond and Donna Mantia, hired Appellee, West Virginia contractor Shafer Electric & Construction, to build a 34 foot by 24 foot, two-car garage addition onto their house. The proposals for the garage did not comply with several requirements of Section 517.7 of the Home Improvement Consumer Protection Act. Specifically, any home improvement contract, in order to be valid and enforceable against the owner of real property, had to be legible, in writing, and contain thirteen other specific requirements. Despite the detail in the specifications for the work to be completed, the contract here only complied with subsections (5), (7), and (8) of Section 517.7(a). Notwithstanding these deficiencies, work on the project began in October, 2010, when Appellants, who owned their own excavation business, began the foundation excavation. When Appellee commenced construction of the addition, it contended that problems surfaced because of Appellants' failure to complete the excavation work properly. During the subsequent months, Appellants eventually reexcavated the foundation area for the addition and, in the process (according to Appellee), changed the design of the addition several times. Negotiations into these design changes and other necessary alterations as a result of the excavation problems occurred, but ultimately failed when Appellants apparently refused to enter into a new contract with Appellee. Upon the breakdown of the negotiations, the parties mutually agreed that Appellee would invoice Appellants for the work completed, and that Appellee would discontinue efforts on the project. Appellants refused to pay the bill. Appellee responded by filing a mechanic's lien in the Washington County Court of Common Pleas. When Appellants still had failed to satisfy the outstanding balance, Appellee filed a civil action in the common pleas court, alleging both breach of contract and quantum meruit causes of action. The Supreme Court granted allowance of appeal in this matter to determine whether the Act barred a contractor from recovery under a theory of quantum meruit in the absence of a valid and enforceable home improvement contract as defined by the Act. The Superior Court held that the Act did not bar a cause of action sounding in quantum meruit and, for slightly different reasons, the Supreme Court affirmed.
View "Shafer Electric & Construction v. Mantia" on Justia Law
The Cote Corp. v. Kelley Earthworks, Inc.
The Cote Corporation filed a mechanic’s lien against real property owned by Kelley Earthworks, Inc. Cote subsequently brought a complaint to enforce the lien against Kelley. Kelley did not respond to the complaint or to Cote’s motion for summary judgment. The superior court entered Kelley’s default and then entered judgment for Cote, plus interest and attorney fees, and ordered that the property be sold to satisfy the judgment. Kelley appeared ten days after the judgment was entered on the docket and filed motions to set aside its default and for relief from the judgment. The court declined to set aside the default but did strike its order to sell the real property, instead awarding Cote a money judgment. The Supreme Court vacated the judgment, holding that the court erred in striking the provision of its order requiring a sale of the property. Remanded for entry of an order for the sale of at least a portion of Kelley’s land. View "The Cote Corp. v. Kelley Earthworks, Inc." on Justia Law
Posted in:
Construction Law, Real Estate & Property Law
United States v. Mathis
The Fillers planned to demolish an unused Chattanooga factory. They knew the site contained asbestos, a hazardous pollutant under the Clean Air Act. Environmental Protection Agency regulations require removal of all asbestos before any demolition. Asbestos materials must be wetted, lowered to the ground, not dropped, labeled, and disposed of at an authorized site. Fillers hired AA, a certified asbestos surveying company, which estimated that it would cost $214,650 to remove the material safely. Fillers hired Mathis to demolish the factory in exchange for salvageable materials. Mathis was required to use a certified asbestos contractor. Mathis applied for an EPA demolition permit, showing an estimated amount of asbestos far less than in the AA survey. The agency’s asbestos coordinator contacted Fillers to verify the amount of asbestos. Fillers did not send the survey, but provided a revised estimate, far less than the survey’s estimate. After the permit issued, the asbestos contractor removed “[m]aybe, like, 1/100th” of the asbestos listed in the AA survey. Temporary laborers were hired, not equipped with protective gear or trained to remove asbestos. Fillers supervised. The work dispersed dust throughout the neighborhood. An employee of a daycare facility testified that the children were unable to play outside. Eventually, the EPA sent out an emergency response coordinator and declared the site an imminent threat. Mathis and Fillers were convicted of conspiracy, 18 U.S.C. 371, and violations of the Clean Air Act, 42 U.S.C. 7413(c). Fillers was also convicted of making a false statement, 18 U.S.C. 1001(a)(2), and obstruction of justice, 18 U.S.C.1519. The district court sentenced Mathis to 18 months’ imprisonment and Fillers to 44 months. The Seventh Circuit affirmed.View "United States v. Mathis" on Justia Law
Goldman v. Gagnard
The Gagnards built a house in Los Altos, California, then sold the home to Goldman in January, 2004. Since then, Goldman has sued the Gagnards and those involved with the construction and sale of the house in various tribunals. In 2011, Goldman registered a foreign arbitral award in Illinois. She then sought citations to discover and collect assets. The district court issued denied reconsideration motions and granted a turnover order. After filing an appeal, the Gagnards paid $1.3 million to Goldman in satisfaction of the judgment. Goldman accepted the payment, and refunded money she had collected in excess of the judgment balance. The district discharged all pending citations and allowed the Gagnards to file a counterclaim against Goldman, claiming unjust enrichment, but subsequently dismissed the counter-complaint. The Seventh Circuit affirmed, based on the failure, by the Gagnards to act in a timely manner. View "Goldman v. Gagnard" on Justia Law
C&C Plumbing and Heating, LLP v. Williams County
American General Contractors, Inc. ("AGC"), appealed a judgment assessing liability and awarding damages and interest for the cost of delays in the construction of the Williams County Law Enforcement Center in Williston. C&C Plumbing and Heating, LLP ("C&C"), the successful bidder for the mechanical prime contract, filed suit when construction the center was delayed approximately two years after "substantial completion" was supposed to have happened. The district court concluded it was appropriate for the County and AGC to share responsibility for providing temporary shelter and heat on the project. The court apportioned 47 percent of the liability for the costs of the delay for the three and one-half months of active interference to the County and 53 percent to AGC, for the four months delay inherent to the industry. The court awarded C&C approximately $73,000 on its claim against the County. After offsetting amounts owed between the parties, the court awarded AGC approximately $424,000 on its claim against the County. The court awarded Davis Masonry approximately $96,000 from AGC for masonry work completed under its subcontract with AGC, and rejected AGC's claimed offsets to that amount. Davis had provided heat, cover and shelter for the project during cold weather and sought $649,000 from the County and AGC for that expense including prompt payment interest. Davis had settled with the County for $530,000, and the court ruled AGC was responsible for 53 percent of the remaining $119,000, or $63,070. AGC argues the district court erred in determining AGC was liable for any of the costs incurred from the delay under its contract with the County. Finding no reversible error, the Supreme Court affirmed the district court.
View "C&C Plumbing and Heating, LLP v. Williams County" on Justia Law
Block v. City of Lewiston
In 2005, John Block purchased property in Lewiston from Jack Streibick to develop. Block submitted an application to resubdivide the property into three residential lots, which Lewiston approved. Prior to Block's purchase of the property, Lewiston issued two separate permits to Streibick allowing him to place and grade fill in the area of those lots. In 2006, Block received permits from Lewiston to construct homes on each of the three lots. During construction of the homes, Block hired engineering firms to test compaction of the finished grade for the footings on the lots. Following the construction of the homes, Lewiston issued Block certificates of occupancy for each of the homes after conducting inspections that found the homes to be constructed in accordance with applicable building codes and standards. In April 2007, Block sold the home and property at 159 Marine View Drive. In November of that year, the owner reported a crack in the home's basement. Around that same time, settling was observed at the other two properties. In early December 2007, Block repurchased 159 from the owners. He also consulted with engineers regarding options for immediate repair to the homes. As early as February 2009, further settling problems were reported at the properties. After Lewiston inspected the properties in May following a gas leak at 153, it posted notice that the residential structures on 153 and 159 were unsafe to occupy. Block ultimately filed a Notice of Claim for Damages with Lewiston that also named City Engineer Lowell Cutshaw as a defendant, but did not effectuate process on Lewiston and Cutshaw until ninety days had elapsed from the date he had filed the Notice of Claim. The City defendants filed a motion for summary judgment, arguing that Block's claims should be dismissed because he failed to timely file a Notice of Claim with Lewiston. This first motion for summary judgment was denied because a question of material fact existed concerning whether Block reasonably should have discovered his claim against Lewiston prior to 2009. The City defendants filed a second motion for summary judgment seeking dismissal of all of Block's claims against them, arguing that they were immune from liability for all of these claims under the Idaho Tort Claims Act (ITCA) and that Block could not establish that he was owed a duty. The district court granted this second summary judgment motion dismissing Block's claims based on the application of the economic loss rule. The court also held that immunity under the ITCA and failure to establish a duty provided alternate grounds for dismissal of Block's claims. Block appealed on the issue of immunity. Finding no reversible error as to that issue, the Supreme Court affirmed the district court's decision.
View "Block v. City of Lewiston" on Justia Law