The Supreme Court reversed the decision to award prejudgment interest to LeGrand and concluded that Celtic Bank was the prevailing party on the prejudgment interest issues.LeGrand Johnson Construction Company filed an action seeking to enforce its mechanic’s lien on property owned by B2AC, LLC for the unpaid value of construction services, and Celtic Bank, B2AC’s lender, sought to foreclose on the same property after B2AC failed to pay on its loan. The action resulted in a lien for $237,294 and an award of attorney fees and costs. Thereafter, the district court determined that LeGrand’s lien, rather than Celtic Bank’s lien, had priority and awarded LeGrand attorney fees and costs. The court then ruled that LeGrand was entitled to recover eighteen percent in prejudgment and postjudgment interest from Celtic Bank based on LeGrand’s contract with B2AC. The Supreme Court (1) reinforced its holding in Jordan Construction, Inc. v. Federal National Mortgage Ass’n, 408 P.3d 296 (Utah 2017), that prejudgment interest is not available under the 2008 version of the Utah Mechanic’s Lien Act; and (2) vacated the attorney fee award because it was based, in part, on the notion that LeGrand had succeeded in establishing its right to prejudgment interest. View "LeGrand Johnson Construction Co. v. Celtic Bank Corp." on Justia Law

by
Scott and Anne Davison appealed the grant of summary judgment in favor of DeBest Plumbing (DeBest). In 2012, the Davisons hired Gould Custom Builders, Inc. (Gould) to perform an extensive remodel of their vacation home in Idaho. Gould hired DeBest as the plumbing subcontractor. A bathtub installed by DeBest developed a leak that caused significant damage before it was noticed and repaired. The Davisons sought damages based upon the contract between Gould and DeBest and for negligence. The district court granted DeBest’s motion for summary judgment on the contract claims because the Davisons were not in privity of contract with DeBest. Later, the district court granted summary judgment in favor of DeBest on the negligence claim, finding that the Davisons had failed to comply with the requirements of the Notice and Opportunity to Repair Act (NORA), Idaho Code sections 6-2501–2504. On appeal, the Davisons argued they satisfied the requirements of NORA because DeBest received actual notice of the claim and sent a representative to inspect the damage. Finding that the Davidsons satisfied the requirements of NORA when they gave DeBest actual notice, and DeBest had an opportunity to inspect the defect, the Idaho Supreme Court determined the district court erred in granting DeBest's motion for summary judgment on the Davidsons' negligence claim. The Supreme Court reversed as to negligence, but affirmed the district court in all other respects. View "Davison v. DeBest Plumbing" on Justia Law

by
Dickinson Elks Building, LLC, appealed a judgment awarding Rick and Janan Snider, doing business as RJ Snider Construction ("RJ Snider"), $198,255.08 for unjust enrichment and quantum meruit claims. In 2011, RJ Snider contracted with Granville Brinkman to furnish materials and labor for construction work on real property owned by Dickinson Elks. RJ Snider's principal place of business was located in Washington. In 2012, RJ Snider applied for a contractor license from the North Dakota Secretary of State, and the license was issued on in February 2012. RJ Snider provided services and materials for Dickinson Elks' property from December 26, 2011, to November 30, 2012. Dickinson Elks paid RJ Snider for all of the services and materials it provided between December 26, 2011, and February 1, 2012. RJ Snider billed Dickinson Elks $174,642.10 for the services and materials it provided from March 15, 2012, until November 30, 2012. Dickinson Elks did not pay any of this amount. In January 2013, RJ Snider recorded a construction lien against Dickinson Elks' property. In May 2014, Dickinson Elks served RJ Snider with a demand to start a lawsuit to enforce the lien and record a lis pendens within 30 days of the demand. RJ Snider sued Dickinson Elks in June 2014, seeking foreclosure of the construction lien and a money judgment. RJ Snider recorded a notice of lis pendens on July 28, 2014. Dickinson Elks moved for summary judgment, arguing RJ Snider's complaint should be dismissed under N.D.C.C. 43-07-02 because RJ Snider was not a licensed contractor when it started work on the property. Dickinson Elks also argued RJ Snider did not have a valid construction lien, because RJ Snider did not record a lis pendens within 30 days of receiving the demand to enforce the lien. The district court partially granted the motion and entered a judgment forfeiting RJ Snider's construction lien because RJ Snider did not record a lis pendens within 30 days of receiving Dickinson Elks' demand to enforce the lien as required under N.D.C.C. 35-27-25. The court concluded RJ Snider's claims were not precluded under N.D.C.C. 43-07-02. RJ Snider amended its complaint, claiming it was entitled to a money judgment against Dickinson Elks under the principles of quantum meruit and unjust enrichment. The North Dakota Supreme Court concluded RJ Snider was not precluded from maintaining its claims; however, the Court reversed and remanded for the district court to determine whether any of the damages awarded were for services and materials provided before RJ Snider was licensed. View "Snider v. Dickinson Elks Building, LLC" on Justia Law

by
At issue was whether this common law action alleging construction defects resulting in both economic loss and property damage was subject to the prelitigation notice and cure procedures set forth in the Right to Repair Act, Cal. Civ. Code 895-945.5. After noting that the answer depended on the extent to which the Act was intended to alter the common law, the Supreme Court held that the Legislature intended that the Act was to supplant the common law with new rules governing the method of recovery in actions alleging property damage rather than to supplement common law remedies with a statutory claim for purely economic loss. Thus, the court held that the present suit for property damage was subject to the Act’s prelitigation procedures, and the court of appeal properly ordered a stay until those procedures were followed. View "McMillin Albany LLC v. Superior Court of Kern County" on Justia Law

by
In 2015, Wichita and affiliated tribes made plans to build a History Center on a plot of land held by the federal government in trust for the Wichita Tribe, Delaware Nation, and Caddo Nation jointly. One of those neighbors, the Caddo Nation, claimed the land may contain remains of ancestral relatives. Before the Wichita Tribe began construction, Caddo Nation sued the Wichita Tribe for allegedly violating the procedures required by the National Historic Preservation Act (NHPA) and the National Environmental Policy Act (NEPA) throughout the planning process. Caddo Nation sought an emergency temporary restraining order preventing Wichita Tribe from continuing construction until it complied with those procedures. When the district court denied that request, Caddo Nation appealed to the Tenth Circuit Court of Appeals without seeking further preliminary relief. In the intervening year while the case was on appeal with the Tenth Circuit, Wichita Tribe completed construction of the History Center. The Tenth Circuit concluded it had no jurisdiction over this appeal because the relief Caddo Nation requested from the district court was moot. View "Caddo Nation of Oklahoma v. Wichita & Affiliated Tribes" on Justia Law

by
Thrasher Construction, Inc. (Thrasher) brought a third-party beneficiary action against Bruce Cope, Mary Cope, and Ike Thrash (the Copes and Thrash). Thrasher sought damages for payments owed for waterproofing the Inn by the Sea, a condominium in which the Copes and Thrash had acquired a full ownership interest by agreeing, in part, to pay all outstanding bills for work previously performed on the property. During trial, the county court dismissed the third-party beneficiary claim but allowed Thrasher to proceed on a quantum meruit theory of the case. The jury returned a verdict in favor of Thrasher for $69,290, and the county court entered judgment based on that verdict. The Copes and Thrash appealed the judgment to the Circuit Court, which affirmed the judgment of the county court. The Copes and Thrash then appealed to the Court of Appeals, arguing the facts did not support a recovery on quantum meruit. Thrasher cross-appealed, arguing the trial court erred in dismissing its third-party beneficiary claim. The Court of Appeals held quantum meruit was not the proper method of relief because the action should have proceeded as a third-party beneficiary claim. The Court of Appeals reversed the judgment and remanded for further proceedings consistent with its opinion. The Mississippi Supreme Court agreed the third-party beneficiary action was the appropriate basis for Thrasher’s recovery; however, because the trial court ultimately reached the correct result, no further proceedings were needed in this case. View "Cope v. Thrasher Construction, Inc." on Justia Law

by
In 2001, plaintiffs Margaret and John Abajian hired architectural firm TruexCullins, Inc., to design additions to their home. Plaintiffs hired Thermal Efficiency Construction, Ltd. (TEC) to serve as the general contractor for the project. TEC contracted with Murphy’s Metals, Inc. to do the roofing work. The roof was installed during the winter of 2001-2002. Plaintiffs had experienced problems with ice damming on their old roof, which was shingled. Defendants recommended that plaintiffs install a metal roof to alleviate the problem. Plaintiffs accepted the suggestion, hoping that the metal roof would result in fewer ice dams. Mr. Abajian testified in his deposition that he “thought that the metal roof was going to eliminate” the ice damming. In 2014, after the roof turned out to be defective, plaintiffs sued the architecture and construction firms that designed and installed the roof for negligence and breach of contract. The trial court granted summary judgment to defendants on the ground that the action was barred by the statute of limitations. Finding no reversible error in the grant of summary judgment to defendants, the Vermont Supreme Court affirmed. View "Abajian v. TruexCullins, Inc." on Justia Law

by
The Supreme Court reversed the district court’s denial of the motion to dismiss the lawsuit brought by several property developers (Developers) alleging that the City of West Jordan violated statutory provisions that regulate how a municipality may spend impact fees collected from developers. The court held (1) Developers had standing to challenge the constitutionality of the impact fees they were assessed; (2) Developers failed to state a takings claim for which relief can be granted because Developers’ allegations that West Jordan either failed to spend impact fees within six years or spent the fees on impermissible expenditures were inadequate to support a constitutional takings claim; and (3) Developers did not have standing to bring a claim in equity. View "Alpine Homes, Inc. v. City of West Jordan" on Justia Law

by
In 2004, Hesperia began acquiring vacant property in its downtown for development of a Civic Plaza, with a city hall, public library, other government buildings and “complimentary retail, restaurant, and entertainment establishments.” Cinema West articulated a plan to develop a cinema immediately west of the Civic Plaza Park: the city would convey 54,000 square feet of real property to Cinema for $102,529, the property‘s fair market value; Cinema would construct a 38,000-square foot, 12-screen digital theatre; the city would construct the necessary parking lot, develop a water retention system for the theater and the parking lot, and install off-site improvements including curb, gutter and sidewalks. Cinema would execute a 10-year operating agreement with the city. The city later made a $250,000 forgivable loan to Cinema to aid with a $700,000 anticipated shortfall. As development of the theater and parking lot was nearing completion, the Electrical Workers Union requested a public works coverage determination under California‘s prevailing wage law (Lab. Code, 1720–18611 ) The State Department of Industrial Relations concluded that the project was subject to the prevailing wage requirement. The court of appeal affirmed, noting that Cinema received the benefit of a new, publicly-funded parking lot adjacent to the theater, which, though owned by the city, is Cinema‘s to use for as long as it operates the theater. View "Cinema West v. Baker" on Justia Law

by
Charges that constitute compensation for the use of government property are not subject to Proposition 218’s voter approval requirements. To constitute compensation for a property interest, however, the amount of the charge must bear a reasonable relationship to the value of the property interest, and to the extent the charge exceeds any reasonable value of the interest, it is a tax and requires voter approval.Plaintiffs contended that a one percent charge that was separately stated on electricity bills issued by Southern California Edison (SCE) was not compensation for the privilege of using property owned by the City of Santa Barbara but was instead a tax imposed without voter approval, in violation of Proposition 218. The City argued that this separate charge was the fee paid by SCE to the City for the privilege of using City property in connection with the delivery of electricity. The Supreme Court held that the complaint and stipulated facts adequately alleged the basis for a claim that the surcharge bore no reasonable relationship to the value of the property interest and was therefore a tax requiring voter approval under Proposition 218. The court remanded the case for further proceedings. View "Jacks v. City of Santa Barbara" on Justia Law