Justia Construction Law Opinion Summaries

Articles Posted in Real Estate & Property Law
by
Brian Welken appealed after a jury returned a verdict in favor of Eugene Taszarek, Marlys Taszarek, Trina Schilling, Steven Taszarek, and Michael Taszarek ("Taszareks") and against Lakeview Excavating, Inc., ("Lakeview") and Welken. Lakeview was a corporation primarily involved in flood control projects, and Welken was Lakeview's president and sole shareholder. In the spring of 2012, German Township in Dickey County solicited bids for road construction projects to repair and raise the grade of a road near the Taszareks' property. Lakeview, acting through Welken, successfully bid and was selected as the contractor for the road projects. Lakeview obtained most of its field rock for the project from area farmers and ranchers with rock piles on their properties. Lakeview arranged with landowners to harvest rocks from their fields and reclaim the ground so it could again be farmed, and landowners allowed Lakeview to remove rock piles. Herb Buerkley owned land adjacent to land owned by the Taszareks, and Buerkley permitted Lakeview to enter his family's property to harvest field rock. While harvesting the rock piles from Buerkley's land, Lakeview's employees crossed into the Taszareks' land and harvested field rock. The Taszareks brought an action against both Lakeview and Welken, asserting claims of intentional trespass, conversion, and unjust enrichment arising from Lakeview's work on the German Township road-raising project. The district court held a jury trial on the Taszareks' trespass and conversion claims against Lakeview and Welken. During trial, the Taszareks' attorney asked the court to instruct the jury on the theory that Lakeview was the "alter ego" of Welken and that Welken should therefore be personally liable for any judgment. Over the objection of Welken's attorney, the court gave an instruction regarding the alter ego doctrine. After review, the Supreme Court concluded Welken failed to preserve whether the district court misapplied the law by allowing the jury to resolve whether Lakeview was the alter ego of Welken. Furthermore, the Court concluded that the trial court erred as a matter of law in inadequately instructing the jury regarding the alter ego doctrine. The Court therefore reversed the judgment and remanded for a new trial. View "Taszarek v. Welken" on Justia Law

by
Dickinson Elks Building, LLC, appealed after the district court forfeited a construction lien filed by Rick and Janan Snider, doing business as RJ Snider Construction, and awarded the Dickinson Elks attorney's fees. In December 2011, Snider contracted with Beaver Brinkman to perform work on real property owned by the Dickinson Elks. Snider recorded a construction lien in January 2013 against the property after it did not get paid for all of its work. In May 2014, the Dickinson Elks served Snider with a demand to start a lawsuit to enforce the lien and record a lis pendens within 30 days of the demand. Snider sued the Dickinson Elks in June 2014, seeking foreclosure of the construction lien and a money judgment. Snider recorded a notice of lis pendens in July 2014. The Dickinson Elks moved for summary judgment, arguing Snider's complaint should have been dismissed because Snider was not a licensed contractor when it started the work on the property. The Dickinson Elks also argued Snider did not have a valid construction lien, because Snider did not record a lis pendens within 30 days of receiving the demand to enforce the lien. The district court granted the motion in part and entered a judgment forfeiting Snider's construction lien because Snider did not record a lis pendens within 30 days of receiving the Dickinson Elks' demand to enforce the lien. After review, the Supreme Court concluded it did not have jurisdiction and dismissed the appeal. View "Snider v. Dickinson Elks Building, LLC" on Justia Law

by
This dispute arose from the construction of Cypress Point, a luxury condominium complex in Hoboken. Co-defendants Adria Towers, LLC, Metro Homes, LLC, and Commerce Construction Management, LLC (collectively, the developer) served as the project's developer and general contractor, and subcontractors carried out most of the work. During construction, the developer obtained four CGL policies from Evanston Insurance Company, covering a four-year period, and three from Crum & Forster Specialty Insurance Company, covering a subsequent three-year period (collectively, the policies). In this appeal, issue before the Supreme Court was whether rain water damage caused by a subcontractor's faulty workmanship constituted property damage and an occurrence under the developer's commercial general liability (CGL) insurance policy. In a published decision, the Appellate Division reversed, holding that, under the plain language of the CGL policies, the unintended and unexpected consequential damages caused by the subcontractors faulty workmanship constituted property damage and an occurrence. The Supreme Court agreed and affirmed, finding that the consequential damages caused by the subcontractors faulty workmanship constituted property damage, and the event resulting in that damage water from rain flowing into the interior of the property due to the subcontractors faulty workmanship was an occurrence under the plain language of the CGL policies at issue here. View "CypressPoint Condominium Association, Inc. v. Adria Towers, L.L.C., et al." on Justia Law

by
In August 2005, D.R. Horton, Inc. completed construction of the Smiths' home, and the Smiths closed on the property and received the deed. Thereafter, the Smiths experienced a myriad of problems with the home that resulted in severe water damage to the property. D.R. Horton attempted to repair the alleged construction defects on "numerous occasions" during the next five years, but was ultimately unsuccessful. In 2010, the Smiths filed a construction defect case against D.R. Horton and seven subcontractors. In response, D.R. Horton filed a motion to compel arbitration. The Smiths opposed the motion, arguing, inter alia, that the arbitration agreement was unconscionable and therefore unenforceable. The circuit court denied D.R. Horton's motion to compel arbitration, finding that the arbitration agreement was unconscionable. D.R. Horton appealed, but finding no error in the circuit court's decision, the South Carolina Supreme Court affirmed. View "Smith v. D.R. Horton, Inc" on Justia Law

by
In 2012, Lacey & Associates, LLC, contracted with Everest Homes, LLC, to purchase a commercial building. In addition, Lacey and Everest executed an escrow agreement for the release of additional funds to Everest if the roof was replaced after title had transferred to Lacey. After title passed to Lacey, Everest entered into a contract with the Williams Group, a contractor, to replace the roof. The Williams Group then hired Andrea Pizano to remove the old roof and HVAC units, which service she performed. In early 2013, Pizano sued alleging the Williams Group did not pay the contractual amount of $11,085, as agreed by the two parties. She filed a mechanic's lien on Lacey's building one day before she filed her petition. The lawsuit sought judgment against the Williams Group in the amount of $11,085, plus interest. The Williams Group never filed an answer. The trial court thereafter entered a default judgment against the Williams Group, awarding Pizano $11,085, an attorney's fee of $2,500.00 and court costs of $461.81. Pizano then sought to foreclose her lien against Lacey and be awarded court costs and attorney fees. She requested that the property be sold to satisfy the judgment. Lacey answered and included a "Cross-motion for Summary Judgment," contending that the new roof leaked so badly that large barrels had to be placed inside the building to catch the water. Therefore, no party was entitled to be paid for the roof. Lacey also asserted that Pizano's motion should be denied because Lacey had no contract with Pizano, and also that the plaintiff failed to file the required pre-lien notice. The trial court granted Pizano's summary judgment motion in part, and denied Lacey's counter-motion for summary judgment. Lacey appealed and Pizano counter-appealed. The Court of Civil Appeals held that Pizano successfully preserved her subcontractor's lien, but found that genuine disputes of fact remained as to the amount owed to Pizano and the enforceability of the lien. The Supreme Court found that the Legislature intended amounts less than $10,000 to be exempt from pre-lien notice. Having provided such an exception, the wording of the applicable statute persuaded the Court that "if a claimant filed a claim of $10,085 without a pre-claim notice, the claim would be enforceable up to $9,999. We do not believe that the claim would be completely unenforceable if it exceeded that legislatively-approved amount by a mere $86." The trial court's order entitling Pizano to a reduced judgment amount of $9,999.00 and an award of attorneys' fees and costs was affirmed. This case was remanded to the trial court to issue a judgment consistent with the law as expressed in the Supreme Court's opinion. View "Pizano v. Lacey & Assoc., LLC" on Justia Law

by
Plaintiff signed a contract with Defendant for the construction of a house. The contract contained an arbitration clause. Plaintiff later brought suit against Defendant, claiming that there were defects in the house. Defendant filed a motion to dismiss and compel arbitration. The circuit court denied the motion, finding that the arbitration clause was unconscionable. Defendant appealed, arguing that the circuit court erred by ruling on questions of arbitrability despite the existence of a delegation provision in the arbitration agreement that vested the arbitrator with authority to determine issues of arbitrability relating to the dispute. The Supreme Court determined that the circuit court was within its rights not to enforce the delegation language because the language did not reflect the parties’ clear and unmistakable intention to delegate issues about the validity, revocability, or enforceability of the arbitration agreement to an arbitrator. The United States Supreme Court granted Defendant’s requested writ of certiorari, vacated the Supreme Court’s opinion, and remanded for further consideration in light of their decision in DIRECTV, Inc. v. Imburgia. The Supreme Court reversed the circuit court’s order, holding that because Plaintiffs never specifically challenged the delegation language before the circuit court or Supreme Court, Plaintiffs waived any right to challenge the delegation language. Remanded for arbitration. View "Schumacher Homes of Circleville v. Spencer" on Justia Law

by
Contractor Anderson Carpentry and Construction built a home for Shad and Trisha Bates. Anderson contracted with Century Lumber Center to purchase supplies and materials to build the Bates home. The Bates paid Anderson for materials used on the home, but those funds were applied to other accounts, and the account with Century on the Bates job became delinquent. Century filed a material lien against the Bates property and filed a complaint seeking to foreclose the lien against the property. The district court ultimately enforced the lien. The Supreme Court reversed, holding that the lien was not timely filed as a matter of law. View "Bates v. Chicago Lumber Co. of Omaha" on Justia Law

by
In 2005, Masterklad built a house in Glenview, including a brick patio that extended off the rear of the house. Because the ground underneath the patio sloped down, dirt and gravel were placed underneath it to support the bricks and make them level with the house's rear entrance. A retaining wall was built to contain the fill. In 2007, the house was sold by Masterklad to a Lubeck for $1,710,000. In the contract Lubeck “knowingly, voluntarily, fully and forever,” waived the implied warranty of habitability in exchange for an express warranty provided by Masterklad, with a one-year term. In 2010, Lubeck sold the house to Fattah, for $1,050,000, with a document stating that the house was being sold “as is” and that the seller made no representations or warranty regarding its condition. In 2011, parts of the retaining wall around the rear patio gave way and part of the patio collapsed. The owner sued. The circuit court found that the patio wall had given way due to latent defects in its construction, but that plaintiff could not recover because Masterklad had executed a valid, enforceable waiver of the implied warranty of habitability with Lubeck. The appellate court reversed. The Illinois Supreme Court reversed. The implied warranty of habitability may not be extended to a second purchaser of a house when a valid, bargained-for waiver of the warranty has been executed between the builder-vendor and the first purchaser. View "Fattah v. Bim" on Justia Law

by
The utility and its insurers filed suit against BendTec for negligence, alleging that its pipes were the source of grit and had been improperly cleaned. The district court granted summary judgment to BendTec. The court affirmed the judgment, agreeing with the district court's conclusion that the negligence claim was barred under the two year limitations period in Minn. Stat. 541.051 since the installation of the turbine was an improvement to real property. Because the two year statute of limitations in Minn. Stat. 541.051 applies and the subdivision 1(e) exception does not, and plaintiffs did not file this lawsuit within the limitations period, the district court correctly granted summary judgment to BendTec. View "Associated Electric & Gas Ins. v. BendTec, Inc." on Justia Law

by
Picerne Construction Corp. agreed to build an apartment complex for Castellino Villas. After construction started, Castellino refinanced the property, replacing the original lender with Bank of the West. Picerne subsequently claimed money due, recorded a mechanic’s lien, and brought this action against Castellino and Bank of the West to foreclose on the lien. Following a bench trial, the trial court entered judgment in favor of Picerne. Castellino argued on appeal: (1) Picerne did not have a valid mechanic’s lien because it did not record its claim within 90 days after substantial completion of the project; (2) the doctrine of judicial estoppel prevented Picerne from taking contrary positions at arbitration and at trial; (3) Picerne did not timely record a claim of mechanic’s lien as to nine distinct buildings within the project; and (4) the trial court erred in calculating the amount of the lien. Bank of the West agreed that Picerne failed to timely record its claim of mechanic’s lien. In addition, Bank of the West contends (5) that Picerne’s complaint against it is time-barred because Picerne did not name Bank of the West as a defendant in the original complaint even though it was aware of facts indicating it had a claim against the bank. After review, the Court of Appeal concluded: (1) Picerne timely recorded its mechanic’s lien; (2) Castellino failed to demonstrate the applicability of judicial estoppel; (3) the property constituted one residential unit; (4) the trial court overstated the principal sum due and failed to subtract the $115,453.50 setoff from the principal sum, but the other claims of error with regard to the lien amount have no merit; and (5) the action against Bank of the West was not time-barred because Picerne timely substituted Bank of the West in place of a Doe defendant when Picerne learned of the bank’s interest in the property. The Court modified the judgment to provide that the mechanic’s lien was in the amount of $2,416,855.06 and affirmed the judgment as modified. View "Picerne Construction v. Castellino Villas" on Justia Law