Justia Construction Law Opinion Summaries
Articles Posted in North Dakota Supreme Court
Shift Services v. Ames Savage Water Solutions
In February 2020, Shift Services, LLC (Shift) was contracted by Ames Savage Water Solutions, LLC (Ames) to repair a liner inside a water tank operated by Ames. The agreement was for a fixed price of $39,500.00, which included all labor, material, and travel time. When Shift began the work, they found a more significant amount of ice in the tank than initially observed. Shift communicated with Ames about the issue and decided to subcontract a hot oil truck company to melt the ice. Upon completion of the project, Ames paid the contracted amount but refused to pay an additional $31,705.00 bill from Shift related to the ice removal. Shift claimed that the contract was modified to include these additional costs, which Ames had allegedly approved. The district court dismissed Shift's breach of contract claim and terminated the construction lien it had placed on the property, finding that there was a lack of mutual assent to modify the contract.The Supreme Court of North Dakota affirmed the district court's decision. The court found that Shift did not provide sufficient evidence to demonstrate mutual assent for the modification of the original contract. The court pointed out that Shift had not disclosed to Ames that they intended to add an additional charge for the increased cost associated with the ice removal, nor did they discuss the details of the subcontractor, the equipment to be used, or the estimated number of hours that the removal would take. In conclusion, the court found no error in the district court's finding of a lack of mutual assent to modify the contract, thereby confirming that Ames did not breach the contract. View "Shift Services v. Ames Savage Water Solutions" on Justia Law
L&C Expedition, et al. v. Swenson, Hagen and Co., et al.
L&C Expedition, LLC (“L&C”) appealed the grant of summary judgment in favor of International Fidelity Insurance Company (“IFIC”) and denying summary judgment to L&C. L&C contracted with Unlimited Excavating (“Unlimited”) to perform work on a residential development project. Unlimited completed its work in November 2016 and received final payment in July 2017. In 2019, L&C learned of major problems in the construction and notified Unlimited it needed to make repairs. Unlimited did not make the repairs and L&C demanded IFIC arrange for performance of Unlimited’s work per the terms of the performance bond. IFIC refused to arrange for performance. L&C subsequently initiated suit against IFIC in May 2020 arguing L&C is entitled to recover $393,000 under the terms of the performance bond. The performance bond provided the following: “[a]ny suit under this bond must be[] [i]nstituted before the expiration of two years from the date on which final payment under the subcontract falls due.” The parties do not dispute the district court’s finding L&C initiated its action outside the limitation period provided within the terms of the bond. L&C argued the district court erred in finding a contractual limitation on the period to assert a claim was enforceable, erred in failing to apply N.D.C.C. § 9-08-05 to preclude modification of the applicable statute of limitations, and erred in interpreting N.D.C.C. § 22-03-03 as providing an exception to the prohibition against modifying the applicable statute of limitations. Finding no reversible error, the North Dakota Supreme Court affirmed. View "L&C Expedition, et al. v. Swenson, Hagen and Co., et al." on Justia Law
Shafer v. Scarborough, et al.
Justin Shafer appealed a district court judgment confirming an arbitration award against Diamond Development & Custom Homes, L.L.C. Shafer argued the district court erred by failing to increase the amount of damages he was awarded. He also argued the North Dakota Supreme Court should narrowly expand the standard for reviewing an arbitration award. The Court declined Shafer’s request to expand the standard of review, and concluded the district court did not err in confirming the arbitration award. View "Shafer v. Scarborough, et al." on Justia Law
Blue Appaloosa v. NDIC
Blue Appaloosa, Inc., appealed a judgment affirming an Industrial Commission order determining it violated N.D. Admin. Code ch. 43-02-03 by beginning construction of a treating plant prior to obtaining a permit or filing a bond with the Commission. Finding no reversible error, the North Dakota Supreme Court affirmed. View "Blue Appaloosa v. NDIC" on Justia Law
Toman Engineering Co. v. Koch Construction, et al.
Koch Construction, Inc.; Marilyn Koch, Personal Representative of the Estate of Michael P. Koch; and Koch Property Investments, Inc. (collectively “appellants”) appealed the judgment and amended judgment entered in favor of Toman Engineering Company (“Toman”). Michael Koch owned and operated Koch Construction and Koch Property Investments (“KPI”). Toman provided engineering services to Koch Construction on various projects, including designing a stormwater management system for the Koch Meadow Hills residential development project in Dickinson, North Dakota. Michael died in August 2017. The stormwater management system included a detention pond referred to as the Marilyn Way Stormwater Pond, which was the detention pond at issue in this case. In 2016, Janet Prchal, Dean Kubas, and Geraldine Kubas, owners of property near the Koch Meadow Hills development, sued the City of Dickinson and KPI for damages, alleging the development of Koch Meadow Hills caused water to drain and collect on their properties. The Prchal lawsuit was settled in September 2018, and the settlement required modifications to be made to the Marilyn Way Stormwater Pond before June 30, 2019. The reconstruction work on the detention pond occurred during the summer and fall of 2019. Toman served a summons and complaint on Koch Construction and Marilyn Koch, to collect unpaid amounts for engineering services Toman provided to the defendants in 2017. Toman filed the complaint in the district court in June 2019. The appellants argued the district court erred in deciding they committed intentional spoliation of evidence and dismissing their counterclaim as a sanction. After review of the district court record, the North Dakota Supreme Court concluded the district court abused its discretion when it dismissed the appellants’ counterclaim as a sanction for spoliation of evidence. Judgment was reversed and the matter remanded for a new trial. View "Toman Engineering Co. v. Koch Construction, et al." on Justia Law
Pavlicek v. American Steel Systems, Inc., et al.
Grinnell Mutual Reinsurance Company appealed a district court judgment ordering it to pay Larry Pavlicek $214,045.55 under a commercial general liability insurance (CGL) policy Grinnell had with JRC Construction. Grinnell argued the district court misinterpreted the insurance policy, and that it was not required to indemnify JRC Construction because its work product was defective. In 2013, Pavlicek hired a contractor to construct a steel building on his property. JRC Construction installed the concrete floor and floor drain for the project. Another subcontractor installed the in-floor heating system for the concrete floor. After JRC completed the floor drain, it failed to properly install the concrete floor, and its attempts to repair the concrete damaged the drain. Pavlicek sued JRC for breach of contract relating to the defective work. In February 2020, Pavlicek filed a supplemental complaint against Grinnell, alleging it was required to satisfy the judgment as JRC’s insurer. Grinnell claimed it had no obligation to indemnify JRC under the CGL policy. The district court concluded JRC’s defective work on the concrete floor was not covered under the CGL policy, but damage to the floor drain was covered. Because removal and replacement of the floor and in-floor heat were necessary to repair the drain the court concluded the CGL policy covered all of those costs. The North Dakota Supreme Court found that although the CGL policy provided coverage to repair the floor drain, it did not cover the cost of replacing the concrete floor because that damage was the result of JRC’s defective work. The district court erred in finding the CGL policy covered the entire concrete floor replacement because replacement of the floor was the only way to repair the floor drain. Further, the Supreme Court found the district court erred in concluding the CGL policy provided coverage for replacement or repair of the in-floor heating system beyond that which may be necessary to repair the drain. View "Pavlicek v. American Steel Systems, Inc., et al." on Justia Law
Tergesen, et al. v. Nelson Homes
Jeanne and Nevin Tergesen appealed a judgment dismissing their complaint and awarding Nelson Homes, Inc. damages for its breach of contract counterclaim. The Tergesens argued the district court erred in dismissing their rescission and breach of contract claims, and the court erroneously found the Tergesens breached the contract. After review, the North Dakota Supreme Court concluded the district court did not err in dismissing the Tergesens’ claims or finding the Tergesens breached the contract, but the court did err in calculating the amount of prejudgment interest on Nelson Homes’ damages. View "Tergesen, et al. v. Nelson Homes" on Justia Law
Wades Welding v. Tioga Properties
Tioga Properties, LLC, appealed a district court judgment awarding Wades Welding, LLC $27,669.90 relating to Wades Welding’s lawsuit for enforcement of construction liens and unjust enrichment. Janice Ellsworth owned Tioga Properties. Tioga Properties owned a restaurant and home (referred to by the parties as a “mobile home”) adjacent to each other in Tioga, North Dakota. Susan Gordon leased the restaurant from Tioga Properties. Gordon delivered rent payments to John Ellsworth Jr., Janice Ellsworth’s son. Gordon resided in the home but had no written lease for that property. In late 2016 and early 2017, Gordon hired Wades Welding to repair the home and restaurant. Wades Welding performed $19,840 of work on the home and $2,500 of work on the restaurant. Wades Welding delivered the invoices for its work to Ellsworth Jr. A day after Wades Welding completed its work at the home, Ellsworth evicted Gordon from the restaurant and home. Ellsworth Jr.
supervised the eviction and Gordon left both properties within 48 hours. In December 2017, Wades Welding recorded construction liens against the properties after Tioga Properties failed to pay for the repairs. Tioga Properties sold the restaurant in July 2019. In September 2019, Tioga Properties served on Wades Welding a demand to enforce the home lien. In October 2019, Wades Welding sued Tioga Properties for breach of contract, foreclosure of the construction liens and unjust enrichment. Tioga Properties denied the allegations, claiming it did not authorize Wades Welding's work on the properties. The district court found Wades Welding's construction liens on both properties were valid, and ordered foreclosure of the home lien. The court found the lien on the restaurant was unenforceable due to a service error, but nonetheless awarded Wades Welding the amount of the repaired under the doctrine of unjust enrichment. Finding no reversible error in the district court's judgment, the North Dakota Supreme Court affirmed judgment in favor of Wades Welding. View "Wades Welding v. Tioga Properties" on Justia Law
Woodrock, Inc. et al. v. McKenzie Cty.
Woodrock, Inc. appealed the grant of summary judgment dismissing its negligence and other claims against McKenzie County, North Dakota. In September 2018, Woodrock sued the County for violations of N.D.C.C. ch. 48-01.2 and negligence. Woodrock alleged the County hired Edwards Gravel & Trucking, LLC to supply aggregate to aggregate stockpiles, the County did not obtain a payment bond from Edwards Gravel, Woodrock furnished materials for use in the project, and Edwards Gravel did not pay Woodrock for the materials. Woodrock claimed that the County violated N.D.C.C. section 48-01.2-10 and was negligent by failing to obtain a bond from Edwards Gravel and that the County was liable to the subcontractors and material suppliers who worked on the project. Woodrock requested damages in the amount of $298,629.54. On appeal to the North Dakota Supreme Court, Woodrick argued the district court erred in concluding a project to stockpile aggregate materials was not a public improvement and the bond requirement under N.D.C.C. 48-01.2-10 did not apply. The Supreme Court concluded supplying aggregate materials to stockpiles for general use in maintaining and repairing county roads did not constitute “construction of a public improvement.” Therefore, the Court affirmed the district court's judgment. View "Woodrock, Inc. et al. v. McKenzie Cty." on Justia Law
Minn-Kota Ag Products, Inc. v. N.D. Public Service Commission, et al.
Minn-Kota Ag. Products, Inc. appealed a district court order dismissing Minn-Kota’s appeal of findings of fact, conclusions of law and order issued by the North Dakota Public Service Commission (PSC) for lack of standing and affirming an administrative law judge’s (ALJ) order denying Minn-Kota’s petition to intervene. In 2017, Minn-Kota began construction of a large, $20 million grain handling facility near the municipalities of Barney and Mooreton, North Dakota. During construction of the facility, Minn-Kota received proposals to provide electric power to the facility from Otter Tail Power Co., an electric public utility, and Dakota Valley Electric Cooperative, a rural electric cooperative. Minn-Kota determined Otter Tail would provide cheaper and more reliable electric service and chose Otter Tail as its preferred provider. Dakota Valley protested Otter Tail’s application and requested a hearing. Otter Tail and Dakota Valley were represented at the hearing, and each offered evidence and testimony. Minn- Kota was not a formal party represented at the hearing and, other than the testimony offered by Schuler, Minn-Kota did not contribute to the hearing. In December 2017, the PSC held a work session to contemplate and discuss Otter Tail’s application. The concerns expressed by the PSC at the work session made it clear the PSC was likely going to deny Otter Tail’s application. As a result, Minn-Kota submitted a petition to intervene, which an ALJ determined Minn-Kota submitted after the deadline to intervene had passed, and denied it. Minn-Kota argued it has standing to appeal the PSC’s decision because it participated in the proceedings before the PSC, and the PSC’s decision should be reversed because it was not supported by the facts or law. In the alternative, Minn-Kota argued the case should have been remanded to the PSC and it should have been allowed to intervene and introduce additional evidence into the record. The North Dakota Supreme Court determined Minn-Kota had standing, but did not provide a compelling argument on how Otter Tail did not adequately represent its interests at the administrative hearing or throughout the entirety of the proceedings. Therefore, the Court affirmed in part, reversed in part, and thus affirmed the PSC's order. View "Minn-Kota Ag Products, Inc. v. N.D. Public Service Commission, et al." on Justia Law