Justia Construction Law Opinion Summaries

Articles Posted in Government & Administrative Law
by
Kadrmas, Lee & Jackson, Inc., ("KLJ") appealed a district court judgment awarding the City of Valley City ("City") costs and expenses the City incurred defending itself in the underlying lawsuit and pursuing its indemnity claim against KLJ. The City entered into a contract with KLJ to provide engineering services for a paving and sewer project. The City hired a general contractor for the project. The contract between the City and the contractor required the contractor to furnish all labor, materials, and equipment for the project. The contractor was required to provide a payment bond under the terms of its contract with the City, and St. Paul Fire & Marine Insurance Company ("St. Paul") was the surety under the bond. Specialized Contracting, Inc. ("SCI"), entered into a subcontract with the contractor to complete some of the work on the project. In 2007, SCI sued St. Paul for breach of its duties under the payment bond, seeking compensation for additional work SCI alleged it completed on the project for which the contractor refused to pay. St. Paul served a third-party complaint against the City for breach of contract and indemnity, alleging the concrete repair work was outside the scope of the City's contract with the contractor, the City was liable to the contractor for any additional compensation SCI was claiming against the payment bond if SCI established KLJ's decision to replace the concrete was beyond the scope of the contract, and the City was required to indemnify St. Paul for any judgments against it in favor of SCI arising from decisions made by KLJ. Upon review of the matter, the Supreme Court concluded KLJ did not have a duty to defend the City. The Court reversed the district court's judgment awarding the City costs and expenses, and remanded the case for a determination of whether KLJ was entitled to recover its costs and expenses as a prevailing party. View "Specialized Contracting, Inc. v. St. Paul Fire & Marine Ins." on Justia Law

by
Plaintiffs, in anticipation of Revett Silver Company and RC Resources, Inc. (collectively, "Revett") seeking approval for mine-related construction under a general permit, filed this action against the Department of Environmental Quality (DEQ) seeking a declaratory judgment that use of general permits to approve stormwater runoff from the Rock Creek Mine would violate Mont. Admin. R. 17.30.1341(4)(e) because Rock Creek is an area of "unique ecological significance" based on considerations of impacts on fishery resource and local conditions at proposed discharge. The district court granted summary judgment to Plaintiffs and declared the general permit void. The Supreme Court affirmed, holding that DEQ's approval of the use of the general permit to allow storm water discharges was arbitrary and capricious because DEQ failed to consider the relevant factors set forth in the law prior to its decision, and as a result, committed a clear error of judgment. View "Clark Fork Coalition v. Dep't of Envtl. Quality" on Justia Law

by
The Phenix City Board of Education ("the Board") sought mandamus relief from the Russell Circuit Court's denial of the Board's motion to dismiss or, in the alternative, for a summary judgment on claims brought against it by The Lisle Company, Inc. ("Lisle"). Because the Board is immune from suit pursuant to § 14, Ala. Const. 1901, the Supreme Court granted the Board's petition and issued the writ. View "Lisle Company, Inc. v. Phenix City Board of Education" on Justia Law

by
In this appeal, the issue before the Supreme Court was whether a contractor's bid was responsive to the Delaware Department of Transportation's (DelDOT) Request for Proposals (RFP). The contractor's bid did not include required paint certifications. In addition, the bid reflected the contractor's plan to use new steel beams, rather than refurbish the existing ones, as required by the RFP. The contractor chose to submit a bid that did not conform to the project specifications. The Supreme Court concluded that the contractor therefore did so at its own risk. DelDOT's decision that the bid was non-responsive was not arbitrary or capricious. Accordingly, the Court affirmed the trial court's entry of summary judgment in DelDOT's favor. View "Julian v. Delaware Dep't. of Transportation" on Justia Law

by
The Port Authority’s subsidiary, PATH, operates the Grove Street Station in Jersey City. The Station was built in 1910. In 2000 PATH planned to expand the Station to accommodate larger trains and persons with disabilities, a project that would have involved construction of a new entrance and two elevators. After September 11, 2001, and the resulting closure of two stations, ridership increased at the Station. Concerned about congestion and safety, PATH scrapped its renovation plans and undertook a “fast track” project. Construction began in 2002 and concluded in 2005. Plaintiffs alleged that the renovations triggered an obligation under the Americans with Disabilities Act, 42 U.S.C. 12101–12213, to make the Station accessible to handicapped persons. They also alleged violations under New Jersey’s Law Against Discrimination and certain state construction code provisions. The district court dismissed, state-law claims on the basis that allowing such claims to proceed would violate the interstate compact between New York and New Jersey that created the Authority, but ordered the Authority to make the east entrance accessible. The Third Circuit affirmed dismissal of the state law claims, but remanded the ADA issue for trial on the issue of feasibility. View "Hip Heightened Indep. & Progress, Inc. v. Port Auth. of NY & NJ" on Justia Law

by
The Wetlands Protection Act, G.L. c. 131, 40, requires a conservation commission to issue a decision on a requested order of conditions within 21 days after holding a public hearing on the applicant's notice of intent to perform work covered by the act. Following the owner’s request for an extension, a hearing on his application for construction of a pile-supported pier and floating dock was held on April 6; the commission voted to deny the application on April 27 and mailed notice on April 28, 22 days after the hearing. The department reversed, based on the commission’s failure to timely act. In the meantime, the commission issued an enforcement order, based on work being done on the applicant’s property. The Supreme Judicial Court held that an applicant may waive the statutory time restriction, but any waiver must be voluntary in fact, its duration defined and reasonable in length, and notice of the waiver's duration must be a matter of public record, available to all interested persons. In this case, the applicant is entitled to proceed under the order issued by the department. View "Garrity v. Conservation Comm'n of Hingham" on Justia Law

by
The issue before the Supreme Court in this petition was whether G.L. 1956 section 5-6-2 permits only licensed electricians to install underground hollow polyvinyl chloride (PVC) material that is devoid of any electrical wiring or conductors. The Board of Examiners of Electricians, the Rhode Island Department of Labor and Training (DLT), and the Superior Court all determined that 5-6-2 required a licensed electrician to perform such work. The petitioners, Reilly Electrical Contractors, Inc. (Relco), Michael McSheffrey, Robert Rutledge, John Brewer, and Ray Bombardier, disagreed and petitioned the Court for a writ of certiorari. Upon review of the statute at issue here, the Court affirmed the judgment of the Superior Court. View "Reilly Electrical Contractors, Inc. v. Rhode Island" on Justia Law

by
In 2008, the EPA issued a rule regulating renovation and remodeling activities that create health hazards arising from lead paint. The rule contained an "opt-out" provision, which exempted owner-occupied housing from the rule's requirements if the homeowner certified that no pregnant women or young children lived there. In 2010, EPA amended the rule to eliminate the opt-out provision. The National Association of Home Builders and other trade associations petitioned for review of the amended rule, arguing (1) the decision to abandon the opt-out provision was arbitrary and capricious, in violation of the APA; and (2) EPA failed to convene a panel of representatives of small businesses before issuing the new rule, in violation of the Regulatory Flexibility Act. The D.C. Circuit Court of Appeals denied the petition for review, holding (1) EPA's decision was not arbitrary or capricious; and (2) the Court lacked jurisdiction to entertain the petitioners' second challenge. View "Nat'l Ass'n of Home Builders v. EPA " on Justia Law

by
This case stemmed from the town's solicitation of bids for the construction of a new police station. Barr Inc. submitted the lowest bid but the town determined that Barr was not a "responsible and eligible bidder," and that the contract should instead be awarded to the next-lowest bidder. Under G.L.c. 149, 44A(2)(D), contracts for the construction of public buildings estimated to cost above $100,000 "shall be awarded to the lowest responsible and eligible general bidder." At issue was whether, when an awarding authority was making a determination as to bidder responsibility, it was constrained to look only at materials compiled as part of the Department of Capital Asset Management's (DCAM's) contractor certification process. The court concluded that the competitive bidding statute placed no such restriction on awarding authorities. Therefore, the court could not conclude that the town exceeded its statutory authority by conducting an investigation into Barr's performance in past projects. View "Barr Inc. v. Town of Holliston" on Justia Law

by
David Barno, a temporary worker on a construction project, alleged that he was injured as a result of Ruscilli Construction Company's violation of a specific safety requirement (VSSR) pertaining to floor openings on construction sites. After a workers' compensation claim was allowed, Barno filed an application for additional compensation with Industrial Commission of Ohio, alleging a violation of Ohio Admin. Code 4123:1-3-04(D). A Commission staff hearing officer (SHO) found that Ruscilli had violated section 4123:1-3-04(D)(1). The court of appeals vacated the SHO's order and remanded the cause to the Commission, finding that the order misinterpreted the applicable safety requirement and that it was based on significant mistakes of fact. The Supreme Court affirmed, holding that the SHO's order contained at least four major errors involving both law and fact, and therefore, the order was premised in findings that lacked evidentiary support. View "State ex rel. Ruscilli Constr. Co. v. Indus. Comm'n " on Justia Law