Justia Construction Law Opinion Summaries

Articles Posted in Government & Administrative Law
by
The Town of Kearny hired Brandt-Kuybida Architects to design and plan the construction of a new public safety facility. Construction began in 1994. The general contractor, Belcor Construction, signed a "Certificate of Substantial Completion" in late 1995. Approximately ten days later, the architects signed the same Certificate. The Certificate defined the date of substantial completion in language similar to that of the construction contract. The signatories to the Certificate, however, left the "date of issuance" and the "date of completion" of the project blank. In Spring1996, the Town's Construction Official issued the first Temporary Certificate of Occupancy (TCO), limited to the police section of the building. Structural defects in the facility surfaced shortly after the Kearny Police Department took occupancy, including leaks, buckled tiles and cracks in the walls. By 2007, ceilings in the facility had fallen and pipes had separated and pulled, all of which were attributed to uneven settlement. The Town never issued a final certificate of occupancy and on February 8, 2007, had the building vacated. Belcor initiated arbitration proceedings against the Town because the Town withheld final payment under the contract. Belcor and the Town resolved their dispute by Stipulation of Settlement. Both the Stipulation of Settlement and the related Town of Kearny Resolution identified the date of substantial completion of the facility as February 1, 1996. The issues before the Supreme Court were: (1) when could a building be considered substantially complete for purposes of calculating the ten-year period of the statute of repose; and (2) whether the Comparative Negligence Act and the Joint Tortfeasors Contribution Law authorized the allocation of fault to defendants who obtained dismissals pursuant to the statute of repose. The Supreme Court concluded after review that (1) the ten year period of the statute of repose started when the first Temporary Certificate of Occupancy was issued for the facility; and (2) when the claims against a defendant are dismissed on statute of repose grounds, fault may be apportioned to the dismissed defendant under the Comparative Negligence Act and the Joint Tortfeasors Contribution Law. View "Townof Kearny v. Brandt" on Justia Law

by
Ground Control, LLC appealed the grant of summary judgment in favor of Capsco Industries, W.G. Yates & Sons Construction and Harrah's Entertainment, Inc. The parties contracted to build the "Margaritaville Spa and Hotel" in Biloxi. The circuit court held in part that Ground Control's failure to obtain a certificate of responsibility rendered its contract with Capsco null and void. After its review of the circuit court record, the Supreme Court agreed (and affirmed) that the lack of the certificate of responsibility rendered the contract null and void. However, the Court reversed the grant of summary judgment in part so that the circuit court could determine whether Ground Control was entitled to recover based on claims of unjust enrichment and/or quantum meruit. View "Ground Control, LLC v. Capsco Industries, Inc." on Justia Law

by
Western Wyoming Construction Company (WWC) submitted a bid for a highway project in Sublette County. The Board of County Commissioners of Sublette County (Commissioners) awarded the contract to another resident contractor whose bid was higher than WWC's. WWC filed a complaint in district court for an order awarding it the contract for the project. The district court granted summary judgment in favor of the Commissioners. At issue on appeal was whether Wyo. Stat. 16-6-102(a) required the Commissioners to award the contract to the responsible certified Wyoming resident making the lowest bid. The Supreme Court reversed, holding (1) section 16-6-102 has no application in the context of two resident contractors; and (2) because no evidence was presented showing where the funds came from to pay for the project, (i) there could be no finding as to what statutory provision, if any, was applicable, and (ii) a judicial determination as to the appropriateness of the bid award was not possible. Remanded. View "W. Wyo. Constr. Co., Inc. v. Bd. of County Comm'rs" on Justia Law

by
The Steel institute appealed the district court's grant of the City's motion for summary judgment and dismissal of its complaint, which alleged that the City's regulation of cranes and other hoisting equipment was preempted by federal law. The court granted some weight to OSHA's view in reaching its conclusion that local regulatory schemes such as the City's crane regulations have the aim and primary effect of regulating conduct to secure the safety of the general public, rather than the safety of workers in the workplace. Therefore, the City's crane regulations were saved from preemption as laws of general applicability and the court affirmed the judgment. View "Steel Institute of New York v. City of New York" on Justia Law

by
Plaintiff brought this suit against the City and County of Honolulu and the State, challenging the approval of a rail project and arguing that state law required that an archaeological inventory survey be completed prior to any approval or commencement of the project. The circuit court granted summary judgment in favor of the City and State on all of Plaintiff's claims. The Supreme Court vacated the circuit court's judgment on Plaintiff's claims that challenged the rail project under Haw. Rev. Stat. 6E and remanded. Plaintiff subsequently requested that the Supreme Court award $255,158 in attorney's fees and $2,510 in costs against the City and State for work performed in the trial court. The Supreme Court (1) granted Plaintiff's request for appellate attorney's fees and costs against the City in the amount of $41,192 in attorney's fees and $343 in costs; (2) and denied Plaintiff's request for trial level fees and costs without prejudice, as Plaintiff's request for fees and costs attributable to work performed at the trial level was more properly within the trial court's discretion. View "Kaleikini v. Yoshioka" on Justia Law

by
The State contracted with a general contractor (Contractor) to complete the renovation of an elementary school. The project required extensive glazing work, specifically, the fabrication and installation of jalousie windows. Contractor held a C-5 specialty license in cabinet, millwork, and carpentry remodeling and repairs, but it did not hold a specialty glazing license. The Department of Commerce and Consumer Affairs' (DCCA) Contractors License Board (Board) determined that Contractor could complete the jalousie window work pursuant to its C-5 license. Specifically, the Board determined that the jalousie window work qualified as "incidental and supplemental" to the remodeling and repair work authorized under Contractor's C-5 license. The circuit court and intermediate court of appeals affirmed. The Supreme Court vacated the judgments of the lower courts, holding that because the Board did not consider the cost and extent of the jalousie window work when determining if that work qualified as "incidental and supplemental" to the project, the Board's interpretation of the "incidental and supplemental" exception was contrary to law and to the primary purpose of the legislation regarding contractor licensing. Remanded. View "Dist. Council 50 of Int'l Union of Painters & Allied Trades v. Lopez" on Justia Law

by
This appeal stemmed from a protracted contract dispute arising out of the construction of Meridian’s new City Hall. The City brought suit against the project’s construction manager, Petra, Inc., alleging that Petra breached the parties’ agreement in a number of ways. The City further claimed that Petra was not entitled to any additional fees for its work. Petra counterclaimed, seeking an equitable adjustment of its construction manager fee. After trial, the district court entered its findings of fact and conclusions of law, ruling against the City on all but one of its claims and awarding Petra an additional fee for its services. The court awarded Petra $595,896.17 in costs and $1,275,416.50 in attorney fees, but stayed enforcement of the judgment pending appeal. The City appealed. Finding no error in the district court's judgment in favor of Petra, the Supreme Court affirmed. View "City of Meridian v. PETRA Inc." on Justia Law

by
Robert Mesteller brought suit to challenge Gwinnett County and its Board of Commissioners' (County) Solid Waste Ordinance. He appealed a superior court's grant of summary judgment in favor of the County. Relying upon the Home Rule provision of the Georgia Constitution (among others), the County adopted the Solid Waste Collection and Disposal Ordinance of 2010. Under the Ordinance, the County was divided into five zones, each to be serviced by a private waste management company. The County collected fees for the waste collection services through annual tax assessment notices, which it then remits to the five service providers, minus the service fee. Mesteller received a property tax bill that showed a fee for solid waste collection services. Acting pro se, he sued the County and the members of its Board of Commissioners, individually and as members of the Board, alleging the assessment and collection of the fee violated the Georgia Constitution. After notice and a hearing, the superior court granted the County's motion for summary judgment. Mesteller contended on appeal that the County was without authority to use the annual property tax bill to assess or collect fees for solid waste services because by contracting with private waste management companies to collect solid waste, the County was not, in fact, "provid[ing] solid waste collection services" within the meaning of OCGA 12-8-39.3 (a), and therefore not authorized to place the collection fee on the tax bill of a property owner or to enforce the collection of the fee as set forth in the statute. The Supreme Court concluded that Mestellar's argument "reveal[ed] a misunderstanding of the precedents of [the] Court." As such, the Court affirmed the superior court's grant of summary judgment in favor of the County. View "Mestellar v. Gwinnett County" on Justia Law

by
The Bath Volunteer Fire Department (BVFD), a not-for-profit fire corporation, obtained its own financing for the construction of a new firehouse and hired Petitioner as the general contractor. The Department of Labor subsequently concluded that the firehouse project was a public work subject to the prevailing wage law. BVFD agreed to indemnify Petitioner and its subcontractors against any liability resulting from their failure to pay the prevailing wages, and thereafter, the project was completed. The Appellate Division confirmed the determination that the project was subject to the prevailing wage law. The Court of Appeals reversed, holding that because no public agency, as contemplated by N.Y. Labor Law 220, was a party to the contract, the prevailing wage law did not apply. View "M.G.M. Insulation, Inc. v. Gardner" on Justia Law

by
This action stemmed from a contract for construction of a baseball stadium and home field for the Seattle Mariners baseball team. In its first trip to the Supreme Court, "Washington State Major League Baseball Stadium Public Facilities District v. Huber, Hunt & Nichols-Kiewit Construction Company," (202 P.3d 924 (2009) (PFD I)), the Court held that the statute of limitations did not bar the owner’s suit against the general contractor because the action was brought for the benefit of the State, and therefore the exemption from the statute of limitations set out in RCW 4.16.160 applied. This case raised questions about whether the construction statute of repose barred suit against the general contractor and, if not, whether the general contractor may pursue third party claims against two of its subcontractors. The trial court granted summary judgment of dismissal in favor of the general contractor and the subcontractors on statute of repose grounds. Upon review of the matter, the Supreme Court reversed the trial court: "the statute of repose does not bar suit against the general contractor. In accord with several provisions in the subcontracts, the subcontractors are subject to liability to the same extent that the general contractor may be liable for any defective materials or work under the subcontracts. Thus, the trial court erred in holding that the statute of repose bars Hunt Kiewit’s third party claims against the subcontractors." View "Wash. State Major League Baseball Stadium v. Huber, Hunt & Nichols-Kiewit Constr. Co." on Justia Law