D.C. Pruett Contracting Company, Inc. v. Jackson County Board of Education
The Jackson County Board of Education petitioned for a writ of mandamus to direct the Circuit Court to enter an order dismissing the complaint of D.C. Pruett Contracting Company, Inc. on the ground of sovereign immunity. Pruett Contracting submitted a proposal for renovations to the Pisgah High School gymnasium. The Jackson County superintendent of education executed a purchase order authorizing Pruett Contracting to make certain renovations to the gymnasium, totaling $231,309. Pruett Contracting then began renovating the gymnasium. The Superintendent later received a letter from the State of Alabama Building Commission stating that "all work on the renovation of the Pisgah High School gymnasium [was] to stop immediately" because the project had not been submitted to or approved by the Building Commission. The Board instructed Pruett Contracting to cease all work on the gymnasium. Pruett Contracting submitted an invoice to the Board for the work that had been performed prior to the letter. Months later, because it had not received payment for its work, Pruett Contracting sued the Board, alleging breach of contract and unjust enrichment and seeking recovery of damages on theories of quantum meruit, work and labor done, open account, and account stated. The Board moved the court to dismiss the complaint, arguing that it was entitled to sovereign immunity as to the claims alleged by Pruett Contracting and that the court therefore lacked subject-matter jurisdiction over the action. Pruett Contracting responded, arguing that this case involved a protected property interest, that immunity was thus precluded, and that the court had subject-matter jurisdiction over the action. The Supreme Court concluded the Board established that it was entitled to sovereign immunity and that the trial court did not have subject-matter jurisdiction over this action; therefore, the action had to be dismissed. Because the Board demonstrated a clear legal right to an order directing the Circuit Court to dismiss Pruett Contracting's complaint, the Supreme Court granted the Board's petition for a writ of mandamus and directed the Circuit Court to dismiss Pruett Contracting's complaint.
View "D.C. Pruett Contracting Company, Inc. v. Jackson County Board of Education" on Justia Law
Georgia Dept. of Corrections v. Developers Surety & Indemnity Co.
The Georgia Department of Corrections (GDOC) entered into a construction contract with Lewis Walker Roofing (Walker Roofing) to re-roof several buildings at Valdosta State Prison. The Contract contained two “no assignment” clauses, and as a prerequisite to contracting with GDOC, Walker Roofing was required to obtain payment and performance bonds. It obtained such payment and performance bonds from Developers Surety and Indemnity Company. Walker Roofing did not complete its work within the time frame required by the Contract, and GDOC declared Walker Roofing in default. Developers Surety did not notify GDOC within 25 days of receipt of GDOC's notice of default regarding whether it would remedy the default or perform the contract. However, approximately three months after the declaration of default, Developers Surety gave GDOC the option of entering into a contract with another company for the completion of the work. GDOC then contracted with that company to finish the project. Under the payment and performance bonds and prior to Walker Roofing's default, Developers Surety had provided financial assistance to Walker Roofing. Developers Surety filed suit against GDOC for breach of contract and for a declaratory judgment that it had no obligation under the payment and performance bond it issued to Walker Roofing on behalf of GDOC. GDOC filed a counterclaim for breach of contract. The parties filed cross-motions for summary judgment, and the trial court determined that Developers Surety's claims were not barred by sovereign immunity and that GDOC had breached the construction contract as a matter of law. It concluded that GDOC waived its sovereign immunity by entering into the contract with Walker Roofing, and that the doctrine of equitable subrogation gave Developers Surety the ability to file suit against GDOC once it incurred liability and paid the obligations of its principal under the bond. Consequently, the trial court granted summary judgment to Developers Surety and denied it to GDOC; in the same order, the trial court entered judgment in favor of Developers Surety in the amount equal to the "financial assistance" Developers Surety provided to Walker Roofing. The Supreme Court granted certiorari to the Court of Appeals to consider whether the State’s sovereign immunity was waived for the claim Developers Surety made on its contract with the State. The Supreme Court found that immunity was indeed waived in this instance, and accordingly, it affirmed the judgment of the Court of Appeals.
View "Georgia Dept. of Corrections v. Developers Surety & Indemnity Co." on Justia Law
Redondo Constr. Corp. v. Izquierdo
In 1999, Redondo Construction Corporation pled guilty to aiding and abetting the making of false statements during its work on a federal highway project. The Puerto Rico Highway and Transportation Authority (“PRHTA”) and the Puerto Rico Public Guildings Authority (“PBA”) subsequently revoked the bids it had awarded Redondo before the plea and suspended Redondo from bidding on new contracts. Redondo challenged both decisions, which resulted in settlement agreements with both agencies allowing Redondo to resume bidding for contracts. After Puerto Rico passed Law 458, which prohibited Puerto Rico agencies from awarding contracts corporations convicted of offenses involving public funds, the PBA cancelled several of Redondo’s bids and the contract it had executed with Redondo, and the PRHTA withdrew from its settlement with Redondo. Redondo sued PRHTA, PBA, and several officials at both agencies, alleging that Defendants were in breach of the settlement agreements, that this caused Redondo’s bankruptcy, and that Defendants were liable in damages. The district court granted the PRHTA’s and the individual defendants’ motions for summary judgment and sua sponte dismissed Redondo’s claims against the PBA. The First Circuit Court of Appeals (1) affirmed the entry of summary judgment as to the PRHTA and the individual defendants, as Redondo had no record of evidence of damages against these defendants; but (2) vacated the dismissal of the claim against the PBA, as the court did not meet the necessary conditions for entering judgment sua sponte.View "Redondo Constr. Corp. v. Izquierdo" on Justia Law
Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia
The respondents, two developers and an architectural firm, Stevens & Wilkinson of South Carolina, Inc. (S&W), entered into a Memorandum of Understanding (MOU) with the City of Columbia as part of a larger project team to develop a publicly-funded hotel for the Columbia Metropolitan Convention Center. The City eventually abandoned its plan under the MOU, and the respondents brought suit on several causes of action including breach of contract and equitable relief. The City moved for summary judgment arguing the MOU was not a contract and therefore the contract claims failed. The circuit court agreed and, rejecting the equitable claims as well, granted summary judgment in favor of the City. The respondents appealed and the court of appeals affirmed in part and reversed in part. The Supreme Court reversed. Because the MOU was comprised of agreements to execute further agreements, there was no meeting of the minds on numerous material terms which had not yet been defined. Accordingly, the court of appeals was reversed with respect to that portion of the court's judgment; the Supreme Court held the MOU was unenforceable as a matter of law. The Supreme Court agreed with the circuit court and reinstated its judgment in favor of the City.
View "Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia" on Justia Law
Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia
In April 2003, the City of Columbia entered into a Memorandum of Understanding (MOU) with Stevens & Wilkinson of South Carolina, Inc. (S&W) and several other parties, to develop a publicly-funded hotel adjacent to the Columbia Metropolitan Convention Center. As architect, S&W was to complete sufficient preliminary design work to determine a guaranteed maximum price for the project, which would be used by the City to obtain municipal bond funding to cover the cost of the hotel. Pursuant to the MOU, the construction company was to pay S&W directly. On June 26, 2003, the City received a letter stating S&W would complete its preliminary design on July 10, 2003, and would then stop working until the bond financing for the hotel was finalized. Realizing this could delay the start of construction, S&W offered to continue working the remaining ninety days until the anticipated bond closing date of October 13, 2003, but required assurance it would be compensated for the work it performed during this time frame. It provided an estimate requiring $650,000 and $75,000 per week after that. On July 30, the City approved "$650,000 for interim architectural design services for a period of 90 days prior to bond closing." The bond closing did not occur as scheduled, but S&W nevertheless continued to work. S&W submitted an invoice to the City for $697,084.79 for work that took place from July 10 to December 15, 2003. By letter dated December 17, 2003, S&W informed the construction company that the City had voted that day "to advance [$705,000.000] to the design team for design services and expenses. Because under the MOU the construction company was to pay S&W, not the City, the construction company agreed to reimburse the City for the funds paid to S&W after the bond closing. The City paid S&W's invoice. S&W continued to work on the project, but in March 2004, the City abandoned its plans under the MOU and ended its relationship with S&W. S&W received no further compensation and sued the City for breach of contract under the MOU and the July 2003 agreement. The City argued there was no separate agreement and the payment of interim fees was merely an advance on fees under the MOU and furthermore, the MOU provided that S&W was to be paid by the construction company, not the City. The trial court granted partial summary judgment in favor of S&W, finding a contract existed between it and the City. On certiorari, the City conceded a contract exists, but argued the contract terms have been satisfied. The Supreme Court found the City's arguments were unpreserved and affirmed as modified.
View "Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia" on Justia Law
Kellogg Brown & Root Servs. v. United States
In 2001 KBR agreed to provide the Army with logistics support services during Operation Iraqi Freedom. Individual task orders required KBR to install, operate and maintain dining services near Mosul, Iraq on a cost-plus-award-fee basis. KBR selected ABC, a subcontractor, to build a prefabricated metal dining facility and to provide dining services for a camp population of 2,573. In June 2004, the Army ordered KBR to stop construction of the metal facility and begin construction of a reinforced concrete facility for an estimated 2,573 to 6,200+ persons. Instead of requesting bids for the new work, KBR kept ABC as the subcontractor due to the urgency of the request. ABC submitted a new proposal with a total monthly cost about triple the monthly cost initially quoted. ABC attributed the increased costs to additional labor and equipment to serve a larger population and to a drastic increase in the cost of labor and a severe shortage of staff willing to work in Iraq. Due to a calculation error, it was determined that ABC’s proposal was reasonable. KBR’s management reviewed and approved a change order, embodying ABC’s proposal. In 2005 the subcontract ended and title to the dining facility passed to the Army. In 2007, the Defense Contract Auditing Agency suspended payment of certain costs paid by KBR to ABC pursuant to the change order. KBR prepared a new price justification for the concrete dining facility and ultimately filed suit, seeking recovery of the $12,529,504 in costs disapproved for reimbursement. The Claims Court awarded $6,779,762. The Federal Circuit affirmed.View "Kellogg Brown & Root Servs. v. United States" on Justia Law
Golden State v. Eastern Municipal Water Dist.
The Eastern Municipal Water District (EMWD) hired general contractor S.J. and Burkhardt, Inc. (SJB) for a public works construction project in 2006. Safeco Insurance Company (Safeco) executed performance and payment bonds for the project. Plaintiff Golden State Boring & Pipe Jacking, Inc. (GSB) was a subcontractor for the project, completing its work by September 2006, but it did not receive payment. In March 2008, SJB sent a voluntary default letter to Safeco. In July 2008, GSB sued SJB, EMWD, and Safeco for the unpaid amounts under the contract, separately seeking payment from Safeco under its payment bond. EMWD filed a cross-complaint to interplead retained sums. Safeco made a motion for summary judgment on the cause of action for payment under the bond on the ground that GSB’s claim was untimely. The trial court granted the motion, finding that there had been three cessations of labor that triggered GSB’s duty to file a stop notice in order to secure payment under Safeco's payment bond. At a subsequent court trial on the contract claims, GSB was awarded judgment against SJB, and Safeco was awarded judgment on the interpleader action. GSB appealed the summary judgment ruling, arguing: (1) the trial court erroneously overruled its objections to evidentiary matters presented in support of Safeco’s summary judgment; and (2) the court erred in finding the action was untimely. Finding no reversible error, the Court of Appeal affirmed.
View "Golden State v. Eastern Municipal Water Dist." on Justia Law
Latin Ams. for Social & Econ. Dev. v. Adm’r of Fed. Highway Admin.
Various Community Groups and the Detroit International Bridge Company sued the Federal Highway Administration (FHWA), challenging the Record of Decision (ROD) issued in 2009, selecting the Delray neighborhood of Detroit as the preferred location alternative for a new international bridge crossing between the U.S. and Canada. The Bridge Company owns and operates the existing Ambassador Bridge, about two miles from the proposed new crossing. The Bridge Company also owns property in the Delray neighborhood. The complaint alleged that selecting the Delray neighborhood as the preferred alternative violated the National Environmental Policy Act (NEPA); Section 4(f) of the Department of Transportation Act; Section 106 of the National Historic Preservation Act (NHPA); and “applicable legal authorities” on environmental justice, essentially because the decision was arbitrary and capricious.” The district court held that the Bridge Company had prudential standing to challenge the ROD and affirmed the ROD. The Sixth Circuit affirmed, noting extensive study of the project. View "Latin Ams. for Social & Econ. Dev. v. Adm'r of Fed. Highway Admin." on Justia Law
Block v. City of Lewiston
In 2005, John Block purchased property in Lewiston from Jack Streibick to develop. Block submitted an application to resubdivide the property into three residential lots, which Lewiston approved. Prior to Block's purchase of the property, Lewiston issued two separate permits to Streibick allowing him to place and grade fill in the area of those lots. In 2006, Block received permits from Lewiston to construct homes on each of the three lots. During construction of the homes, Block hired engineering firms to test compaction of the finished grade for the footings on the lots. Following the construction of the homes, Lewiston issued Block certificates of occupancy for each of the homes after conducting inspections that found the homes to be constructed in accordance with applicable building codes and standards. In April 2007, Block sold the home and property at 159 Marine View Drive. In November of that year, the owner reported a crack in the home's basement. Around that same time, settling was observed at the other two properties. In early December 2007, Block repurchased 159 from the owners. He also consulted with engineers regarding options for immediate repair to the homes. As early as February 2009, further settling problems were reported at the properties. After Lewiston inspected the properties in May following a gas leak at 153, it posted notice that the residential structures on 153 and 159 were unsafe to occupy. Block ultimately filed a Notice of Claim for Damages with Lewiston that also named City Engineer Lowell Cutshaw as a defendant, but did not effectuate process on Lewiston and Cutshaw until ninety days had elapsed from the date he had filed the Notice of Claim. The City defendants filed a motion for summary judgment, arguing that Block's claims should be dismissed because he failed to timely file a Notice of Claim with Lewiston. This first motion for summary judgment was denied because a question of material fact existed concerning whether Block reasonably should have discovered his claim against Lewiston prior to 2009. The City defendants filed a second motion for summary judgment seeking dismissal of all of Block's claims against them, arguing that they were immune from liability for all of these claims under the Idaho Tort Claims Act (ITCA) and that Block could not establish that he was owed a duty. The district court granted this second summary judgment motion dismissing Block's claims based on the application of the economic loss rule. The court also held that immunity under the ITCA and failure to establish a duty provided alternate grounds for dismissal of Block's claims. Block appealed on the issue of immunity. Finding no reversible error as to that issue, the Supreme Court affirmed the district court's decision.
View "Block v. City of Lewiston" on Justia Law
Johnson Controls, Inc. v. Liberty Mutual Insurance Company
This case arose from a contract between Roanoke Healthcare Authority (doing business as Randolph Medical Center) and Batson-Cook Company, a general contractor, to renovate the medical center, located in Roanoke. Batson-Cook received written notice from Roanoke Healthcare that work on the renovation project had been suspended. Batson-Cook notified one of its subcontractors, Hardy, of the suspension and stated that "[t]he contract has been suspended by [Roanoke Healthcare] through no fault of Batson-Cook ... or its subcontractors. [Roanoke Healthcare] is currently out of funding and has subsequently closed the facility while seeking a buyer." Liberty Mutual, the project's insurer, alleged in its answer that Roanoke Healthcare failed to pay Batson-Cook $241,940.51 for work performed pursuant to the contract. Batson-Cook sent Hardy a change order the change order deducted from the subcontract the $147,000 in equipment and materials another subcontractor Hardy hired, Johnson Controls, Inc. (JCI), had furnished for the renovation project and for which it has not received payment. JCI notified Liberty Mutual, Roanoke Healthcare, Batson-Cook, and Hardy by certified letters of its claim on a payment bond. The letters identified Batson-Cook as the general contractor and Hardy as the debtor. Liberty Mutual denied the claim. JCI sued Liberty Mutual, alleging JCI was entitled to payment on the payment bond Liberty Mutual had issued to Batson-Cook. Upon review, the Supreme Court concluded JCI was a proper claimant on the payment bond. Therefore, the circuit court erred in entering a summary judgment in favor of Liberty Mutual and denying JCI's summary judgment motion. View "Johnson Controls, Inc. v. Liberty Mutual Insurance Company " on Justia Law