Justia Construction Law Opinion Summaries
Articles Posted in Government & Administrative Law
ASRC Energy Services Power v. Golden Valley Electric
This case arose from an award by Golden Valley Electric Association (GVEA) of two competitively bid construction contracts on its Northern Intertie Project. In November 2001 GVEA awarded Global Power & Communications, LLC (Global) a $39.4 million contract (Contract NI-8) for construction of the Northern Intertie’s Tanana River flats section. Later GVEA awarded Global an approximately $5.3 million contract (Contract NI-9) for construction of the Northern Intertie’s Tanana River crossing and Fairbanks sections. Subsequently, after Global had been awarded NI-9 and before it had completed work on NI-8, Global presented GVEA with requests for additional compensation (RFIs) totaling approximately $2.4 million in connection with NI-8. GVEA responded that it found "no legitimate basis" to justify Global’s RFIs and rejected Global’s request for additional payment. Global also notified GVEA that Global would submit more RFIs, arising out of both NI-8 and NI-9. In all, Global sought additional compensation totaling $5.7 million under the two contracts. GVEA responded to Global denying most of the RFIs but indicated that it would approve a few and consider partial payment for a few others. Global sued, and a trial court ultimately held in GVEA's favor, awarding it costs under both the contract and the applicable state law. Global appealed, arguing among other things, the trial court abused its discretion in ruling in favor of GVEA. Upon review of the lengthy record from the trial court, the applicable legal authority and legislative history, and the two contracts in question, the Supreme Court partly affirmed and partly vacated the trial court's decision. The case was remanded for: (1) a fee determination regarding GVEA’s "UTPA" claim against Global and (2) a new trial on causation and damages relating to GVEA’s breach of NI-9.
View "ASRC Energy Services Power v. Golden Valley Electric" on Justia Law
Hillside Landscape Construction, Inc. v. City of Lewiston
The issue before the Supreme Court in this appeal was the City of Lewiston's rejection of a bid for a public works project on the grounds that the lowest bidder lacked sufficient experience for the project. In 2009, the City of Lewiston (City) advertised for bids to replace the irrigation system at the City golf course. Hillside Landscape Construction, Inc. (Hillside) desired to bid on the project, but prior to doing so it sent a letter to City stating that if City insisted upon having qualifications other than a current Idaho public works license to bid on the project, the City must follow the Category B procedures set forth in the Idaho Code and pre-qualify the bidders. Hillside asked that the qualification of prior experience be removed. City’s attorney denied the request, stating that City’s specifications and bidding process complied with state law. Hillside and four others submitted bids for the project. City notified the bidders that Hillside Landscape Construction submitted the lowest bid but that the company lacked the required experience specified within the bid documents. City awarded the contract to Landscapes Unlimited, the next lowest bidder. Hillside filed a complaint seeking injunctive relief, declaratory relief, and damages. The district court held that City complied with the bidding statutes, vacated a temporary restraining order, denied the motion for an injunction then dismissed Hillside’s complaint. In its review, the Supreme Court found that because the City chose to follow the "Category A" procedures set forth in the Idaho Code rather than the Category B procedures, the district court erred in holding that City could reject the bid on that ground. The Court therefore vacated the judgment of the district court and remanded the case for further proceedings.
View "Hillside Landscape Construction, Inc. v. City of Lewiston " on Justia Law
Ivory Homes, Ltd. v. Utah Tax Comm’n
Ivory Homes purchased various concrete products from a company that, when it delivered the products, provided an invoice that charged a single sales price without indicating separate delivery charges. Ivory Homes then discovered if it structured its transactions with the company differently and bargained for separate and independent delivery charges, the charges would not be taxable. Subsequently, Ivory Homes filed a refund request with the Utah Taxpayer Services Division for sales tax it paid for several years on expenses associated with the concrete products. The Division denied the refund. The Utah State Tax Commission also denied the refund request. The Supreme Court affirmed the Tax Commission's decision that it did not erroneously receive any tax and that Ivory Homes was not entitled to a tax refund where (1) under a substantial evidence standard of review, the Commission correctly made findings of fact that the parties did not intend delivery charges in their original transactions; and (2) alternatively, a plain language interpretation of the Refund Statute requires that the Tax Commission commit some error in its receipt of taxes before a taxpayer is entitled to a refund. View "Ivory Homes, Ltd. v. Utah Tax Comm'n " on Justia Law
Wyle v. Lees
Defendants Scott and Christina Lees appealed a trial court decision that found in favor of Plaintiff Stephen Wyle on his claim of negligent misrepresentation. In 2002, Defendants purchased a two-unit apartment building. Defendants wished to expand the building, and approached a contractor to add a third apartment to the back of the property. Conditional approval for the site plan was granted in November 2003 and final approval was obtained in January 2004. However, Defendants did not obtain the proper permits prior to building or occupying the unit. As a result, the town's building inspector never inspected the unit. The Lees again hired the contractor both to complete a second addition to the property. Defendants again failed to secure the necessary building permits. After the completion of construction, town officials visited the property a number of times in 2006 and 2007. The town informed Defendants that "[s]ave for acceptable field changes[,] the site plan requirements have been satisfied." Defendants listed the property for sale in 2007. After entering into the agreement, Plaintiff had a comprehensive home inspection performed and sent a list of specific concerns regarding the property to Defendants. The concerns were either remedied by the Defendants or waived by Plaintiff prior to closing. Approximately six weeks after closing, the entire property was inspected by the town building inspector and fire chief which revealed numerous building and life safety code violations. Plaintiff was ordered not to occupy the unit until he corrected the violations and made the site compliant with site plan regulations. After correcting the violations, Plaintiff then brought a single claim against Defendants for negligent misrepresentation. Following a two-day bench trial, the trial court issued an order awarding damages to the Plaintiff. Upon review of the trial court record, the Supreme Court found that the evidence at trial established that Defendants negligently misrepresented that the premises were licensed for immediate occupancy and that they had obtained all the necessary permits. Accordingly, the Court found that the trial record supported the decision in favor of Plaintiff, and the grant of damages. View "Wyle v. Lees" on Justia Law
Renaissance v. Broida
A landowner submitted a site development plan to the county planning board, proposing to construct a mixed-use condominium building. Joel Broida, who lived across the street from the landowner's parcel of land, filed a motion to deny approval of the site development plan. The planning board approved the plan. Broida appealed. A hearing examiner dismissed the appeal, holding that Broida lacked standing. Broida appealed. The board of appeals (Board) split evenly on the issue of Broida's standing and decided to re-vote at a later date. The landowner then filed a complaint for a declaratory judgment, declaring that the Board's split decision was final and required the appeal to be dismissed. The circuit court granted summary judgment in favor of the landowner. The court of special appeals reversed, holding that Broida had standing to appeal. The court therefore did not address whether there was a final Board decision. The Court of Appeals reversed, holding (1) there was no final administrative decision and, therefore, the landowner failed to exhaust its administrative remedies; and (2) because there was no final administrative decision, the lower courts erred in reaching the merits of the case, and the declaratory judgment action should have been dismissed. Remanded. View "Renaissance v. Broida" on Justia Law
Sec’y of Labor v. ConocoPhillips Bayway Ref.
The Secretary of Labor cited the refinery for nine "serious" violations of the asbestos in construction standard, which prescribes protective requirements based on measurable concentration of asbestos fibers to which employees are or may be exposed. The ALJ affirmed the violations and the classification. The Occupational Safety and Health Review Commission reduced the classification to "other than serious" under 29 U.S.C. 666, in part because the Secretary failed to present case-specific evidence of possible employee exposure to asbestos. The Third Circuit vacated and remanded for the citations to be affirmed as "serious." Precedent only requires that there could be exposure to asbestos that is substantially probable to lead to serious harm. Applying this standard, the violations were "serious;" there is no need for case-specific evidence. If the Secretary has shown violations of regulations involving Class II work and the presence of asbestos, the burden shifts to the employer to show that the violations were not "serious." View "Sec'y of Labor v. ConocoPhillips Bayway Ref." on Justia Law
Meadow Valley v. UDOT
The Utah Department of Transportation (UDOT) contracted with Meadow Valley Contractors (MVC) for a highway construction project. MVC subcontracted the paving work to Southwest Asphalt Paving. After UDOT refused to allow Southwest to use ribbon paving and assessed MVC a thickness-laying penalty, MVC filed a compliant against UDOT, alleging that (1) it incurred costs not contemplated by the contract as a result of UDOT's prohibition on ribbon paving, and (2) the thickness penalty assessed by UDOT was unwarranted. UDOT denied MVC claims. Southwest then filed a complaint in district court in MVC's name against UDOT alleging breach of contract. The trial court (1) concluded that UDOT breached its contract with MVC by refusing to allow ribbon paving on the construction project, and (2) denied MVC's claim that UDOT had erroneously imposed a paving-thickness penalty. On appeal, the Supreme Court reversed in part and affirmed in part, holding (1) UDOT did did not breach its contract with MVC when it forbade MVC and Southwest from using ribbon paving, and (2) there was sufficient evidence to support the trial court's conclusion that UDOT's interpretation of the contract regarding paving thickness was more reasonable than MVC's interpretation. View "Meadow Valley v. UDOT" on Justia Law
City of Cohasset v. Minnesota Power, an Operating Division of Allete, Inc.
After respondent was granted a permit by the Minnesota Public Utilities Commission (âMPUCâ) for routing and construction of a pipeline to deliver natural gas to an energy center within appellantâs city limits, appellant commenced an action for declaratory and injunctive relief seeking to require respondent to obtain a franchise from appellant to operate the pipeline. The district court dismissed, concluding that appellant did not have franchise authority over respondentâs pipeline, and the appeals court affirmed. The Supreme Court reversed and remanded, holding (1) a municipality is authorized by Minn. Stat. 301B.01 to impose a franchise on a public utility that has constructed and operates a gas pipeline located on public property within the municipality, regardless of whether the pipeline itself supplies gas to the public; (2) a municipality is authorized by Minn. Stat. 216B.36 to impose a franchise on a public utility that serves customers within the municipality or that uses public property within the municipality to serve customers elsewhere; and (3) the issuance of a permit by the MPUC for the construction of a gas pipeline does not preempt pursuant to Minn. Stat. 216G.02 a municipal ordinance requiring a franchise for the operation of the pipeline after construction is complete.
Michaels v. CH2M Hill, Inc.
There was a catastrophic failure at the Spokane waste water treatment plant. One man was killed, and two others were severely injured. The survivors, including Respondent Larry Michaels, successfully sued Appellant CH2M Hill, the engineering firm that worked for the city at the time of the accident. The City of Spokane, as employer of Respondents, was immune from liability under the Industrial Insurance Act. All parties agreed that the City was negligent. The issue at trial was whether CH2M Hill was also negligent. On appeal to the Supreme Court, CH2M Hill challenged the trial judge's rulings on its liability as well as twenty-six other findings of fact. Of importance here was whether the City's immunity could be imputed to CH2M Hill under the same insurance act. The Supreme Court dissected all twenty-six points in its review, and concluded that CH2M Hill was not entitled to the same immunity as the City. The Court agreed with all rulings of the trial court. The Court affirmed the trial court's decision in the case.
Village of Hallam v. L.G. Barcus & Sons
L.G. Barcus & Sons, Inc. (Barcus) was held liable to the Village of Hallam under the state One-Call Notification System Act (Act) for damage to Hallamâs sanitary sewer system. The Act established a one-call notification center so that excavators can learn of any underground facilities in the area where excavation is planned. The general contractor in this case complied with the Act. Acting under its contractorâs compliance, Barcus excavated on a private landownerâs property that ultimately ruptured Hallamâs sewer lines. Among the issues Barcus raised on appeal is whether the excavator can delegate its duties under the Act to another party to escape liability. The Supreme Court found that Barcus could not rely on anotherâs compliance to excuse its own noncompliance. The Court affirmed the judgment of the district court.