Justia Construction Law Opinion Summaries

Articles Posted in Contracts
by
The issue before the Supreme Court in this case was whether a limitations period applied to an action for breach of a construction contract. The Court of Appeals held that the limitations period applied in this case, and that the statute's six-year limit expired before Plaintiff Miller-Davis Company filed its complaint. The appellate court reversed the judgment of the trial court that had awarded Plaintiff damages. Plaintiff argued on appeal to the Supreme Court that a different statute of limitations for breach of contract controlled, and the period prescribed by that statute was the applicable statute for this action. Upon review of the two statutes of limitations, the Supreme Court agreed with Plaintiff. The limitation in both statutes is six years, however, the period runs from "the date the claim first accrued." The Court reversed the appellate court's judgment because there was a question about the date Plaintiff's action accrued. The Court remanded the case for further proceedings. View "Miller-Davis Co. v. Ahrens Construction, Inc." on Justia Law

by
The Utah Department of Transportation (UDOT) contracted with Meadow Valley Contractors (MVC) for a highway construction project. MVC subcontracted the paving work to Southwest Asphalt Paving. After UDOT refused to allow Southwest to use ribbon paving and assessed MVC a thickness-laying penalty, MVC filed a compliant against UDOT, alleging that (1) it incurred costs not contemplated by the contract as a result of UDOT's prohibition on ribbon paving, and (2) the thickness penalty assessed by UDOT was unwarranted. UDOT denied MVC claims. Southwest then filed a complaint in district court in MVC's name against UDOT alleging breach of contract. The trial court (1) concluded that UDOT breached its contract with MVC by refusing to allow ribbon paving on the construction project, and (2) denied MVC's claim that UDOT had erroneously imposed a paving-thickness penalty. On appeal, the Supreme Court reversed in part and affirmed in part, holding (1) UDOT did did not breach its contract with MVC when it forbade MVC and Southwest from using ribbon paving, and (2) there was sufficient evidence to support the trial court's conclusion that UDOT's interpretation of the contract regarding paving thickness was more reasonable than MVC's interpretation. View "Meadow Valley v. UDOT" on Justia Law

by
In 1995, Charles and Charlene Ebinger contracted with Venus Construction Corporation to build a home. The couple moved into their new residence in 1997. In 2003, the Ebingers filed suit against Venus alleging defects in the home's foundation. Venus sought indemnification from one of its subcontractors. At issue in this case is whether the construction company's third-party demand against its subcontractor was time-barred by state law that established a peremptive period for actions against residential building contractors. The peremptive period was established originally at ten years, but subsequent amendments shortened its duration. A 1999 amendment reduced the period to seven years; a 2003 amendment reduced it to five years. Upon consideration of the trial record and the applicable legal authority, the Supreme Court found that the latest version of the statute applied in this case (2003). Consequently, the court held that the construction company's right to indemnity from its subcontractor was extinguished and its third party demand was perempted. View "Ebinger v. Venus Construction Corp." on Justia Law

by
Plaintiffs William and Vivian Allen contracted defendant V and A Brothers, Inc. (V&A) to landscape their property and build a retaining wall to enable the installation of a pool. At the time, V&A was wholly owned by two brothers, Defendants Vincent DiMeglio, who subsequently passed away, and Angelo DiMeglio. The corporation also had one full-time employee, Defendant Thomas Taylor. After V&A completed the work, Plaintiffs filed a two-count complaint naming both corporate and individual defendants. The first count was directed solely to V&A and alleged that the corporation breached its contract with Plaintiffs by improperly constructing the retaining wall and using inferior backfill material. The second count was directed to the corporation and Vincent's estate, Angelo, and Taylor individually, alleging three "Home Improvement Practices" violations of the state Consumer Fraud Act (CFA). Before trial, the trial court granted the individual defendants' motion to dismiss the complaint against them, holding that the CFA did not create a direct cause of action against the individuals. Plaintiffs' remaining claims were tried and the jury returned a verdict in favor of plaintiffs on all counts, awarding damages totaling $490,000. The Appellate Division reversed the trial court's order dismissing the claims against the individual defendants under the CFA. The panel remanded the matter to determine whether any of the individual defendants had personally participated in the regulatory violations that formed the basis for Plaintiffs' CFA complaint. The panel precluded relitigation of the overall quantum of damages found by the jury in the trial against the corporate defendant. Upon review, the Supreme Court held that employees and officers of a corporation might be individually liable under the CFA for acts they undertake through the corporate entity. Furthermore, individual defendants are not collaterally estopped from relitigating the quantum of damages attributable to the CFA violations. The Court remanded the case for further proceedings. View "Allen v. V & A Bros., Inc." on Justia Law

by
The hospital engaged a contractor for renovations and expansion. Before occupancy the hospital noted problems with the flooring in operating rooms; the contractor completed some repairs. After the project was complete, new problems continued to appear and the contractor repeatedly repaired the floors. All of the problems documented by January 2005, the expiration of a one-year warranty period, were repaired. The contractor continued to perform repairs through early 2006, when the hospital conducted its own investigation and replaced the floors at a cost of $398,070, without involving the contractor. The cost was higher than the original installation because of the need for containment systems so that the facility could continue to operate. A jury awarded $331,835 in damages on the warranty plus pre-judgment interest. The First Circuit affirmed. A reasonable jury could find that the problems were due to faulty workmanship or materials for which the contractor was responsible under the warranty, that the hospital properly invoked the warranty, and that the hospital was not required to give the contractor the option of doing the job. View "Berkshire Med. Ctr., Inc. v. U.W. Marx, Inc." on Justia Law

by
At issue in this case was whether the trial court abused its discretion when it concluded that Defendants Richco Construction, Inc. (Richco) and Ronald Richards, Jr. were personally notified of the default judgment against them and denied their motion to set aside that judgment. The suit arose from a contractual relationship between Plaintiff Lawrence M. Clarke, Inc. (Clarke) and Defendant. Clarke worked on a residential subdivision in 2003, and hired Richco as a subcontractor to work on the sewer system. Richco's work did not satisfy the local governing municipality, and after efforts to repair were unfruitful, Clarke contracted with another party to finish the work. Clark filed a breach of contract and fraud complaint against Richco. The process server attempted to serve Richco at its business address on file with the state, but Richco had vacated the premises and left no forwarding address. Clarke continued in its efforts to locate Richco and refiled its complaint. The trial court permitted alternative service through mailing notice to last-known addresses and a classified advertisement in the local paper. With no response, Clarke moved for a default judgment that the court granted. Upon review of the trial court record, the Supreme Court found that the trial court abused its discretion by finding that Richco was personally notified, and that Richco was entitled to relief from the default judgment. The Court reversed and remanded the case back to the trial court for further proceedings. View "Lawrence M. Clarke, Inc. v. Richco Construction, Inc." on Justia Law

by
Plaintiffs Stephen and Marilee Bell hired contractor Defendant Perception Construction Management, Inc. (PCM) to build a log home. The parties' relationship deteriorated, and the Plaintiffs terminated the contract before construction was complete. Plaintiffs refused to pay PCM's final invoices, and PCM filed suit to enforce a lien it placed on the home for the unpaid invoices. Plaintiffs filed multiple counterclaims, including construction defect and breach of contract. PCM prevailed at trial, and the district court found PCM was entitled to damages, prejudgment interest and attorney fees. Plaintiffs appealed, contending that the district court erred by excluding certain evidence relating to their defense against the lien, and in its determination of the monies allegedly owed under the lien. The Supreme Court found that the district court impermissibly excluded Plaintiffs' evidence, and as such, the Court vacated the district court's judgment and remanded the case for further proceedings. View "Perception Construction Management, Inc. v. Bell" on Justia Law

by
Ron and Linda Reece and Greg and Staci Hunter agreed to flip a house and put their agreement in writing. Mr. Reece supplied the labor and submitted invoices for expenses incurred to Mrs. Hunter. Later, the Hunters became dissatisfied with the progress on the project, told Mr. Reece to stop working on the project, and hired other contractors to complete the project. The Reeces then filed suit against the Hunters, alleging that, under the contract, the Reeces were entitled to payment for Mr. Reece's labor on the project in addition to one half of the profits. The district court found that the parties' contract was not valid because there had been no meeting of the minds regarding an essential term of the agreement, that being whether Mr. Reece was to be paid for his work in addition to receiving one half of the profits. The court then invoked the theory of unjust enrichment to award all of the profits to the Reeces. The Hunters appealed. The Supreme Court reversed, holding that, given the language of the written agreement and the parties' stipulation that it was a valid contract, the district court erred in finding there was no contract. View "Hunter v. Reece" on Justia Law

by
In 2003, the Division of Highways (DOH) let out a public highway construction contract to Nicewonder Contracting. The Affiliated Construction Trades Foundation (ACT) filed a declaratory judgment action against the DOH and Nicewonder, alleging that the construction contract violated state and federal law because the DOH did not seek public bids for the project and there was no prevailing wage clause in the contract. Upon remand from the district court, the circuit court granted Nicewonder's motion for summary judgment, finding ACT lacked standing. The Supreme court reversed, holding that the appropriate standard to determine if an organization has representative standing to sue on behalf of its members is when the organization proves that (1) at least one of its members would have standing to sue in their own right; (2) the interests it seeks to protect are germane to the organization's purpose; and (3) neither the claim asserted nor the relief requested requires the participation of individual members in the lawsuit. The Court found that ACT met all three prongs and thus had representative standing to seek the declarations contained in its petition.

by
Plaintiffs-Appellants Doug Zink and Ted Keller appealed a district court judgment that dismissed their complaint, denied their motions, and awarded Enzminger Steel attorney's fees and costs. Enzminger Steel contracted with Doug Zink to supply components for a new grain drying site. The contract listed Zink as the purchaser, but Zink and his son Jeremy signed the contract. Doug Zink and Keller contend that they had formed a partnership for the purposes of constructing and operating the site. They further alleged that it was this partnership and not the Zinks separately, that entered into the contract with Enzminger Steel. Sometime after construction began, Zink and Keller learned that certain unsuitable components had been used in the site's construction. Zink and Keller refused to make payments under the contract. Two separate breach of contract actions followed, one brought by Enzminger Steel and one brought by Zink and Keller. At trial, the district court repeatedly questioned whether the alleged partnership between Zink and Keller was a ruse to allow Keller to practice law without a license. Keller later told the court that he and Zink had entered into an unwritten partnership agreement to share profits and losses. The court replied, "[T]he agreement that you are in is to share profits off this lawsuit which is not allowed." Neither Zink nor Keller produced any documents to prove the partnership. The district court entered an order denying all of the motions in this case and dismissed the action brought by Zink and Keller with prejudice. On appeal, Zink and Keller argued that the district court abused its discretion by denying the various motions in this case, ordering them to prove that a partnership existed, and awarding attorney's fees and costs to Enzminger Steel. Upon review, the Supreme Court found that while the district court had the power to dismiss a case in the absence of a party's motion, it must provide the parties with adequate notice and an opportunity to respond. Because Doug Zink did not have adequate notice or an opportunity to respond, the dismissal of his case with prejudice was reversed. The Court remanded the case for further proceedings.