Justia Construction Law Opinion Summaries

Articles Posted in Contracts
by
This case arose out of plaintiff Ferguson Fire's efforts to obtain payment for materials it supplied to defendant Preferred Fire Protection, LLC for defendant Immedion's data center. In 2007, Immedion, a telecommunications company, hired Rescom, L.L.C. to be the general contractor for improvements planned for its data center on property Immedion leased in Greenville. Rescom, in turn, hired Preferred Fire, a fire sprinkler company, as a subcontractor. In addition, Immedion directly hired Preferred Fire under a separate contract to install a special "pre-action" fire suppression system1 in its data center. To complete this work, Preferred Fire purchased materials from Ferguson Fire. Ferguson Fire began delivering materials to Preferred Fire in August, 2007, and the deliveries continued through October. In September, while its deliveries were in progress, Ferguson Fire sent a "Notice of Furnishing Labor and Materials" to Immedion advising it in relevant part that it had been employed by Preferred Fire to deliver labor, services, or materials with an estimated value of $15,000.00 to Immedion's premises. The Notice of Furnishing advised that it was being given as "a routine procedure to comply with certain state requirements that may exist," and that it was not a lien, nor any reflection on Preferred Fire's credit standing. Immedion paid Preferred approximately half of the contract price for installation of the system before receiving Ferguson Fire's Notice of Furnishing. After receiving the Notice, Immedion issued two additional checks to Preferred Fire for the unpaid balance of the contract price. Immedion paid everything it owed to Rescom, and it also paid its contractor Preferred Fire in full under the separate contract for the fire suppression system. However, Preferred Fire never paid Ferguson Fire for the materials it furnished. Ferguson brought a mechanic's lien foreclosure action against Immedion and Preferred Fire. Ferguson Fire contended (and the Supreme Court agreed) that the Court of Appeals erred in adding requirements to S.C Code Ann. 29-5-40 (2007) (governing a notice of furnishing) that were not in the statute itself and in concluding Ferguson Fire did not establish an effective lien upon which a foreclosure action could be premised. The Supreme Court reversed and remanded for further proceedings. View "Ferguson Fire v. Preferred Fire" on Justia Law

by
Defendant, Suzynne D. Cumminngs and S.D. Cummings & Co., PC, appealed a Superior Court order awarding $44,403 to plaintiffs, Robert Audette and his company, H&S Construction Services, LLC (H&S), for breach of contract. Defendants provided various accounting and business services to Audette and his then-partner, Paul Fogarty, including helping them to start their construction business partnership, as well as preparing tax returns for both the business and Audette and Fogarty personally. In 2007, defendants helped Audette and Fogarty dissolve their partnership. One of the final acts defendants worked on for H&S was the placement of a mechanic's lien on a property on which H&S worked: the municipality halted construction on the project when H&S was approximately ninety-five percent complete. The lien placed on the property was for $44,403. Ultimately, plaintiffs’ 120-day statutory lien had not been timely secured or recorded, therefore it had lapsed. Plaintiffs brought suit against defendants in November 2009 for failing to secure the lien. The trial court found for plaintiffs and awarded damages in the amount of $44,403. Finding no error in the Superior Court's judgment, the Supreme Court affirmed. View "Audette & v. Cummings" on Justia Law

by
Gambro Renal Products, Inc. hired The Facility Group, Inc. ("TFG"), as the general contractor for the construction of a facility designed to produce kidney dialysis filters in Opelika. TFG contracted with the Hardy Corporation for specialized piping work on the project. Absolute Welding Services, Inc. ("AWS"), is a subsidiary of Rayco Industrial, Inc., a subsubcontractor hired by Hardy. Although the negotiations on the subcontract at issue in these appeals were between AWS and Hardy, the subcontract was executed by Rayco and Hardy. A dispute arose over whether the exclusion of "passivation" and the installation of piping in Rayco's offer was incorporated into its subcontract. Rayco filed a complaint against Hardy, Gambro and 15 fictitiously named parties, seeking an accounting, a declaratory judgment, a reformation of the contract, and perfection of a lien. Rayco asserted claims for damages for breach of contract, unjust enrichment/quantum meruit, and "work and labor done." Both parties unhappy with the eventual trial court order resolving the dispute, appealed the order. After careful consideration of the contracts and the trial court record, the Supreme Court reversed in part, and affirmed in part. The case was remanded with instructions for further proceedings.View "Hardy Corporation v. Rayco Industrial, Inc. " on Justia Law

by
American General Contractors, Inc. ("AGC"), appealed a judgment assessing liability and awarding damages and interest for the cost of delays in the construction of the Williams County Law Enforcement Center in Williston. C&C Plumbing and Heating, LLP ("C&C"), the successful bidder for the mechanical prime contract, filed suit when construction the center was delayed approximately two years after "substantial completion" was supposed to have happened. The district court concluded it was appropriate for the County and AGC to share responsibility for providing temporary shelter and heat on the project. The court apportioned 47 percent of the liability for the costs of the delay for the three and one-half months of active interference to the County and 53 percent to AGC, for the four months delay inherent to the industry. The court awarded C&C approximately $73,000 on its claim against the County. After offsetting amounts owed between the parties, the court awarded AGC approximately $424,000 on its claim against the County. The court awarded Davis Masonry approximately $96,000 from AGC for masonry work completed under its subcontract with AGC, and rejected AGC's claimed offsets to that amount. Davis had provided heat, cover and shelter for the project during cold weather and sought $649,000 from the County and AGC for that expense including prompt payment interest. Davis had settled with the County for $530,000, and the court ruled AGC was responsible for 53 percent of the remaining $119,000, or $63,070. AGC argues the district court erred in determining AGC was liable for any of the costs incurred from the delay under its contract with the County. Finding no reversible error, the Supreme Court affirmed the district court. View "C&C Plumbing and Heating, LLP v. Williams County" on Justia Law

by
The issue before the Supreme Court in this matter centered on whether defects in load-bearing walls were a result of "any defect" due to noncompliance with the buildings standards subject to a one year peremptive period, or whether they constituted a "major structural defect" subject to a peremptive period of five years. This case stemmed from damages caused by a home flooding. The District Court found the defects in the four exterior load-bearing walls constituted a major structural defect under the Act to which the five-year warranty period applied and awarded plaintiff Barbara Shaw damages. The Court of Appeal reversed, finding the plaintiff's claim was for a defect in workmanship subject to a one year peremptive period. After review, the Supreme Court reversed, finding the record supported the failure of the load-bearing walls affected the "load-bearing functions to the extent the home becomes unsafe, unsanitary, or is otherwise unlivable," as provided by La. Rev. Stat. 9:3143. Thus, it constituted a major structural defect and the five-year warranty applied. View "Shaw v. Acadian Builders & Contractors, LLC" on Justia Law

by
A subcontractor on a public project filed suit against the general contractor and an insurance company that provided a payment bond seeking to recover money owed under the subcontract after the general contractor defaulted. The subcontractor asserted a payment-bond claim against the insurance company and breach of contract, unjust enrichment, and other claims against the general contractor. The insurance company filed a motion for summary judgment on the payment-bond claim because the subcontractor mailed its pre-suit notice of claim to the general contractor listed on the subcontract rather than the address listed on the payment bond. The district court denied the motion and granted judgment against the insurance company. The court of appeals reversed. The Supreme Court affirmed, holding (1) pursuant to Minn. Stat. 574.31(2)(a), a claimant must serve notice on the contractor at its address as stated in the bond as a prerequisite to filing suit; and (2) the subcontractor in this case did not comply with the statutory notice requirements. View "Safety Signs, LLC v. Niles-Wiese Constr. Co., Inc." on Justia Law

by
MMS Construction & Paving, L.L.C. entered into a subcontract with Head, Inc. to pave asphalt runway shoulders at Altus Air Force Base in Oklahoma. The project was delayed and MMS, expressing concern that Head had not been making agreed payments, quit the job. MMS also complained that completing the job would be more expensive than it originally believed because certain requirements were being imposed that Head said would be waived. After MMS quit, Head finished the job, relying on other subcontractors. MMS sued Head on state-law claims of breach of contract, tortious breach of contract, quantum meruit, and misrepresentation, and brought a claim under the federal Miller Act on Head’s surety bond for the project. Head filed a counterclaim, alleging that MMS breached the contract. After a jury trial, MMS was awarded damages and attorney fees. Head filed a motion for judgment as a matter of law or for a new trial, both of which the district court denied. Head appealed, arguing: (1) the evidence at trial was insufficient to show that Head breached the contract; (2) if there was a breach, it was not material; (3) an Oklahoma statute limited MMS’s breach-of-contract damages to the amount unpaid plus interest; (4) the evidence was not sufficient to establish MMS’s alleged lost-profits damages for breach of contract; (5) MMS did not present sufficient evidence to prove misrepresentation or any damages from misrepresentation, MMS waived the misrepresentation claim, and the award of misrepresentation damages duplicated the award of damages for breach of contract; and (6) MMS was not entitled to attorney fees from Head because the Miller Act does not allow recovery of those fees. Upon careful consideration of the district court record, the Tenth Circuit reversed damages award based on the misrepresentation claim because the jury’s award was not supported by any evidence at trial. On all other issues, the Court affirmed. View "MMS Construction & Paving v. Head, Inc., et al" on Justia Law

by
Robert and Tracy Barrett appealed the grant of two summary judgments in favor of Carlos Roman d/b/a Carlos Roman Roofing ("Roman") and Bobby Beach d/b/a Just Brick Masonry ("Beach") on all of the Barretts' claims against Roman and Beach. The issues before the Supreme Court in this appeal required resolution of the same issues that were in claims pending in the circuit court against a third party. A November 2012 judgment disposed of all of the Barretts' claims against Beach and Roman, but it did not dispose of the Barretts' claims against the third party. Thus, the Court's consideration of the circuit court's summary judgments in favor of Beach and Roman as final would mean that the intertwined claims against the subcontractors named as defendants in this action would have been litigated in piecemeal fashion. "The piecemeal adjudication of the claims against the subcontractors pose[d] an unreasonable risk of inconsistent results. Therefore, we must conclude that the circuit court exceeded its discretion in certifying the summary judgments in favor of Beach and Roman as final." Accordingly, the Court dismissed the Barretts' appeal.View "Barrett v. Roman" on Justia Law

by
Lakeview Reserve Homeowners Association filed an action against Maronda Homes, Inc. for breach of the implied warranties of fitness and merchantability (referred to as the implied warranty of habitability in the residential construction context) arising from alleged defects in the development and construction of a residential subdivision that Maronda Homes developed. Maronda Homes filed a third-party complaint against T.D. Thomson Construction Company for indemnification based on the alleged violation of the implied warranties. The trial court entered summary judgment in favor of Maronda Homes and T.D. Thompson on the basis that the common law implied warranties of fitness and merchantability do not extend to the construction and design of the infrastructure, private roadways, drainage systems or other common areas in a residential subdivision because those structures do not immediately support the residences. The court of appeal reversed, holding that the common law warranty of habitability was applicable in this case. The Supreme Court affirmed, holding that the implied warranties of fitness and merchantability applied to the improvements that provided essential services to the homeowners association. Remanded.View "T.D. Thomson Constr. Co. v. Lakeview Reserve Homeowners Ass'n, Inc." on Justia Law

by
Johnson Controls, Inc. contracted with a school district (the District) to provide design services. Johnson then subcontracted with Architectural Resources, Inc. Marshall Helmberger subsequently submitted a request to Johnson under the Data Practices Act for a copy of the subcontract. Johnson denied the request and withheld the contract. Thereafter, Helmberger filed a complaint with the Office of Administrative Hearings (OAH). An administrative law judge (ALJ) dismissed the complaint after a hearing, concluding that Helmberger did not establish that Johnson was performing a governmental function for the District within the meaning of Minn. Stat. 13.05(11)(a). The court of appeals reversed. The Supreme Court reversed, holding that Johnson was not obligated to disclose the subcontract under the Act because the subcontract was not public data under section 13.05(11)(a).View "Helmberger v. Johnson Controls, Inc." on Justia Law