Conway v. The Cutler Group, Inc.
In September 2003, appellant The Cutler Group, Inc. sold a new house in Bucks County to Davey and Holly Fields. After living in the house for three years, the Fields sold the house to appellees Michael and Deborah Conway. In 2008, Appellees discovered water infiltration around some of the windows in the home, and, after consultation with an engineering and architectural firm, concluded that the infiltration was caused by several construction defects. In 2011, Appellees filed a one-count complaint against Appellant, alleging that its manner of construction breached the home builders' implied warranty of habitability. Appellant filed a demurrer, arguing, inter alia, that, as a matter of law, the warranty rextended from the builder only to the first purchaser of a newly constructed home because there was no contractual relationship between the builder and second or subsequent purchasers of the home. Recognizing that courts have traditionally required a showing of privity of contract before permitting a party to proceed with a warranty claim, the trial court concluded that the question presented was "one of policy as to who will bear the burden for damages caused by latent defects [in] relatively new residential dwellings." The trial court sustained Appellant's demurer based on lack of privity, and dismissed Appellees' complaint with prejudice. After an unsuccessful appeal to the Superior Court, appellees petitioned the Supreme Court. Finding no reversible error, the Supreme Court affirmed, holding that a subsequent purchaser of a previously inhabited residence may not recover contract damages for breach of the builder's implied warranty of habitability. View "Conway v. The Cutler Group, Inc." on Justia Law
Posted in:
Construction Law, Contracts
Legacy Builders, LLC v. Andrews
The Andrews, a married couple, contracted to purchase a newly constructed home from Appellants, Joe Seneshale and his company, Legacy Builders, LLC (together, Legacy). After the Andrews took possession of the property, they discovered that the house had numerous structural and cosmetic flaws. The Andrews filed a complaint against Legacy alleging breach of contract and breach of implied warranty of habitability. The trial court entered judgment in favor of the Andrews and awarded a total of $319,302 in damages. The Supreme Court affirmed but remanded with instructions to correct the damage award, holding (1) when the cost of repairs in a homeowners’ construction case alleging breach of contract and breach of warranty may be disproportionate to the loss in value to the home resulting from the breach, the plaintiff has the burden of proving damages at trial, and the defendant has the burden of challenging the reasonableness or disproportionality of the plaintiff’s method; and (2) the district court did not commit clear error when it relied upon the majority of the Andrews’ cost of repair expert’s testimony and when it found that expansive soils caused damages to the home’s foundation. View "Legacy Builders, LLC v. Andrews" on Justia Law
Posted in:
Construction Law, Contracts
C & H Elec., Inc. v. Town of Bethel
Plaintiff contracted with the Town of Bethel to perform electrical work in connection with the Town’s renovation of its high school. Plaintiff later sued the Town, alleging breach of contract and unjust enrichment and claiming that the Town must reimburse it for additional costs incurred due to the Town’s ongoing asbestos abatement work at the school. The trial court rendered judgment for the Town in part, concluding that the Town's conduct did not fall within either of two judicial created exceptions to the enforcement of “no damages for delay” clauses adopted by the Court in White Oak Corp. v. Dep’t of Transportation. The Supreme Court affirmed the trial court’s decision that Plaintiff was not entitled to compensation under any of the “no damages for delay” exceptions at issue, holding (1) the term “active interference,” as used in the contract, did not require a showing of bad faith or gross negligence; but (2) the Town’s conduct in this case did not rise to the level of active interference or fall within either of the White Oak exceptions. View "C & H Elec., Inc. v. Town of Bethel" on Justia Law
Posted in:
Construction Law, Contracts
Nautilus Ins. Co. v. Lexington Ins. Co.
VP & PK purchased an insurance policy from Lexington Insurance Company for work on a construction site. Kila Kila, one of VP & PK’s subcontractors, purchased an insurance policy from Nautilus Insurance Company. Both policies contained an “other insurance” provision and included duties to defend and indemnify. When VP & PK and Kila Kila were sued for damages resulting from the construction, Nautilus funded the defense of both Kila Kila and VP & PK. Lexington satisfied the judgment against VP & PK but did not contribute to the defense costs. Nautilus filed a complaint seeking (1) a declaration that Lexington owed VP & PK a duty to defend, which it breached; and (2) equitable contribution from Lexington for defense costs. The U.S. district court granted summary judgment for Lexington, holding that Lexington’s policy was in excess to Nautilus’s policy, and therefore, Lexington’s duty to defend was not triggered. The Hawaii Supreme Court accepted certified questions from the court of appeals and held, inter alia, that (1) an “other insurance” clause purporting to release an otherwise primary insurer of the duty to defend if the insurer becomes excess as to liability is enforceable, but only as between two or more insurers seeking to allocate or recover defense costs; and (2) an otherwise primary insurer who becomes an excess insurer by operation of an “other insurance” clause has a duty to defend as soon as a claim is tendered to it and there is the mere possibility that coverage of that claim exists under its policy.View "Nautilus Ins. Co. v. Lexington Ins. Co." on Justia Law
DTJ Design, Inc. v. First Republic Bank
Downing, Thorpe & James Design, Inc. (DTJ) was an architectural firm incorporated in Colorado. Thomas Thrope, one of DTJ’s three founding principals, was allowed to practice individually as a foreign architect in Nevada, but DTJ was not allowed to practice as a foreign corporation in Nevada. In 2004, DTJ contracted with a Nevada developer to provide architectural services for a Las Vegas subdivision owned by Prima Condominiums, LLC (Prima). Prima obtained a loan from First Republic Bank in exchange for a promissory note secured by a deed of trust on one of the subdivision’s units. After Prima defaulted on its payments, DTJ recorded a notice of mechanic’s lien against the property for unpaid services. First Republic then foreclosed and purchased the property. DTJ subsequently brought an action against First Republic for lien priority and unjust enrichment. The district court granted summary judgment for First Republic. The Supreme Court affirmed, holding (1) because DTJ had failed to comply with Nevada’s statutory registration and filing provisions, it was barred from maintaining an action in Nevada for compensation for its architectural services; and (2) Thorpe’s individual status had no bearing on whether DTJ could bring or maintain an action for compensation for its services.View "DTJ Design, Inc. v. First Republic Bank" on Justia Law
Metcalf Const. Co., LLC v. United States
In 2002, the Navy awarded Metcalf a contract to design and build 212 housing units in Hawaii by October, 2006, for $50 million. Problems arose involving soil conditions. The request for proposals stated that the “soil reconnaissance report” was “for preliminary information only” and required that the contractor conduct independent soil investigation, incorporating 48 C.F.R. 52.236-2, concerning site conditions that differ materially from those disclosed. Discussions delayed construction for a year. Metcalf implemented its preferred changes by over-excavating and using non-expansive fill, without a contract modification. The Navy denied that there was any material difference between pre-bid and post-award soil assessments, but approved some modifications. Metcalf was about 200 days behind schedule and began using “post-tension” concrete, which was more expensive but avoided the additional time and cost of over-excavation. The Navy amended the contract to approve use of post-tension concrete slabs. Metcalf claims additional delays resulting from the presence of more of a chemical contaminant than was expected. With respect to contamination, the Navy granted a 286-day extension and reimbursed $1,493,103. The Navy accepted the buildings in March, 2007. Metcalf alleged that its final cost was $76 million. The government paid less than $50 million. The Claims Court ruled in favor of the government, under the Contract Disputes Act, 41 U.S.C. 7104. The Federal Circuit vacated, holding that the court misconstrued what Metcalf needed to show to prove that the government breached its duty of good faith and fair dealing and misinterpreted certain contractual provisions.View "Metcalf Const. Co., LLC v. United States" on Justia Law
Intervest Constr. of Jax, Inc. v Gen. Fidelity Ins. Co.
ICI Homes, Inc. (ICI) had a general liability insurance policy with General Fidelity Insurance Company. In 2007, Katherine Ferrin, the owner of a residence constructed by ICI, was injured while using stairs installed by Custom Cutting, Inc. Ferrin filed suit against ICI. ICI, in turn, sought indemnification from Custom Cutting. The parties agreed to a $1.6 million settlement of Ferrin’s claim. ICI accepted $1 million from Custom Cutting’s insurer to settle its indemnification claim, which it paid to Ferrin. ICI and General Fidelity then claimed the other was responsible for paying Ferrin the remaining $600,000. Both parties paid $300,000 to Ferrin to settle Ferrin’s claim. ICI then filed suit against General Fidelity seeking return of the $300,000 ICI paid above the $1 million indemnification payment. General Fidelity counterclaimed seeking return of the $300,000 it had paid to Ferrin. The district court entered judgment for General Fidelity. The court of appeals certified two questions to the Supreme Court for resolution. The Supreme Court answered (1) the General Fidelity policy allowed ICI to apply indemnification payments received from Custom Cutting’s insurer towards satisfaction of its $1 million self-insured retention; and (2) the transfer of rights provision in the policy did not abrogate the made whole doctrine.View "Intervest Constr. of Jax, Inc. v Gen. Fidelity Ins. Co." on Justia Law
Travelers Cas. Ins. Co. of America v. Williams Co. Construction
In Spring 2008, Williams Company Construction, Inc. entered into a construction contract to remodel the Friendly Smiles Cosmetic Dentistry Office owned by Dr. Brenda Barfield. Dr. Barfield previously leased the building from Williams Company owner Glen Williams for approximately five years before she purchased the property from him in 2008. Dr. Barfield hired Williams to remodel the building because of its construction experience and familiarity and knowledge of the building. When Dr. Barfield hired Williams, she did not know whether the remodeling work would be done by Williams or subcontractors. Dr. Barfield did not deal directly with any subcontractors during the remodeling project nor did she direct Williams to hire any specific subcontractors. During the remodel, Williams served as the general contractor and hired subcontractors to do various construction tasks. In December 2008, a section of a copper water pipe froze and burst. The frozen water pipe caused minor water damage and was repaired by plumbing subcontractor Home Heating. During the repair process, a Home Heating employee cut a hole in the wall to locate the leak and discovered that the air in the plumbing wall was cold. The employee was concerned the pipe could freeze again and notified the Friendly Smiles Cosmetic Dentistry Office about the cold air. Dr. Barfield contacted Williams to express her concern about the pipes re-freezing from the cold air. According to testimony, Williams told Dr. Barfield not to worry about the pipes freezing again because of circulating warm air around the hole. Dr. Barfield also wanted the hole in the wall patched, but had difficulty in securing Williams or Home Heating to fix it. Dr. Barfield made repeated requests for Williams or Home Heating to resolve the cold air issue, but they did not fix the problem. Approximately one week after the pipe was fixed, the water pipe froze and broke again, this time causing extensive water damage to the dental office. Dr. Barfield and her insurance company, Travelers Insurance, brought suit against Williams, Home Heating (and other subcontractors) for negligence, and breach of contract. Before trial, the parties stipulated that the total amount of damages was $220,046.09. Williams requested the trial court to include a jury instruction concerning the independent contractor distinction (C-55.25), and a jury instruction pertaining to the failure of a party to produce witnesses (C-80.30). The court denied the two requests. At the pretrial hearing, the parties stipulated that the case would be tried before the jury based on comparative fault. The jury was given a special verdict form and found Williams seventy percent at fault, Home Heating twenty-five percent at fault, and Dr. Barfield five percent at fault. Judgment was entered against Williams. Williams subsequently filed a motion for a new trial arguing the court erred in denying its requested jury instructions and there was insufficient evidence for the jury to find Williams seventy percent at fault for the damages. Following a hearing, the district court denied the motion. Williams appealed the district court's judgment, but finding no reversible error, the Supreme Court affirmed.
View "Travelers Cas. Ins. Co. of America v. Williams Co. Construction" on Justia Law
Kellogg Brown & Root Servs. v. United States
In 2001 KBR agreed to provide the Army with logistics support services during Operation Iraqi Freedom. Individual task orders required KBR to install, operate and maintain dining services near Mosul, Iraq on a cost-plus-award-fee basis. KBR selected ABC, a subcontractor, to build a prefabricated metal dining facility and to provide dining services for a camp population of 2,573. In June 2004, the Army ordered KBR to stop construction of the metal facility and begin construction of a reinforced concrete facility for an estimated 2,573 to 6,200+ persons. Instead of requesting bids for the new work, KBR kept ABC as the subcontractor due to the urgency of the request. ABC submitted a new proposal with a total monthly cost about triple the monthly cost initially quoted. ABC attributed the increased costs to additional labor and equipment to serve a larger population and to a drastic increase in the cost of labor and a severe shortage of staff willing to work in Iraq. Due to a calculation error, it was determined that ABC’s proposal was reasonable. KBR’s management reviewed and approved a change order, embodying ABC’s proposal. In 2005 the subcontract ended and title to the dining facility passed to the Army. In 2007, the Defense Contract Auditing Agency suspended payment of certain costs paid by KBR to ABC pursuant to the change order. KBR prepared a new price justification for the concrete dining facility and ultimately filed suit, seeking recovery of the $12,529,504 in costs disapproved for reimbursement. The Claims Court awarded $6,779,762. The Federal Circuit affirmed.View "Kellogg Brown & Root Servs. v. United States" on Justia Law
JEM Contracting, Inc. v. Morrison-Maierle, Inc.
Morrison-Maierle, Inc. (MMI) was hired by two counties to provide engineering services and supervision on a road improvement contract. The counties retained JEM Contracting, Inc. (JEM) to provide the construction services on the project. JEM filed suit against MMI alleging detrimental reliance and fraudulent inducement for promises MMI allegedly made during the job that JEM would be paid for unanticipated costs incurred during pulverization of the old road. The district court granted summary judgment for MMI, concluding that JEM could not prove it had been harmed by MMI’s alleged representations. The Supreme Court affirmed, holding that the district court did not err by (1) concluding that JEM was required to continue performance pending approval of a change order under a certain contract provision, as the provision was not void as against public policy; and (2) granting summary judgment to MMI on the ground that JEM failed to show it was harmed by the representations made by MMI.
View "JEM Contracting, Inc. v. Morrison-Maierle, Inc." on Justia Law