Justia Construction Law Opinion Summaries

Articles Posted in Contracts
by
In 2011, the Town of Middletown issued an invitation for bids on a drainage improvement project. Two contractors submitted bids, including HK&S Construction Holding Corp., which provided the lowest bid. Woodard & Curran, Inc. recommended against awarding HK&S the project and in favor of negotiating a contract with the second bidder. The town counsel concluded that HK&S’s bid was non-responsive and awarded the contract to the second bidder. Plaintiff filed a complaint against the Town and Woodard & Curran alleging, among other claims, that the Town violated state and local law when it denied the contract award for the project. The superior court granted summary judgment for Defendants. The Supreme Court affirmed, holding (1) there was no error in disposing of HK&S’s claims against the Town in summary judgment where HK&S failed to submit a responsive bid; and (2) HK&S’s claim of negligence against Woodard & Curran also failed. View "HK&S Constr. Holding Corp. v. Dible" on Justia Law

by
A property developer filed suit against several defendants involved in a construction project asserting claims for negligence and breach of contract. Defendants filed motions to compel arbitration, which the trial court denied. The court of appeals affirmed. The Supreme Court held that the developer must arbitrate its claims against the general contractor but not its claims against the other defendants, as (1) the developer agreed to arbitrate its claims against the general contractor, and the general contractor did not waive its right to demand arbitration; (2) the developer’s argument that a contractual deadline barred the general contractor’s demand for arbitration was itself a claim that must be arbitrated; (3) the developer did not agree in the general contract to arbitrate its claims against the other defendants; (4) the developer was not equitably estopped from denying its assent to its purported agreement that the other defendants could enforce the general contract’s arbitration provisions; and (5) the subcontracts did not require the parties to arbitrate these claims. View "G.T. Leach Builders, LLC v. Sapphire V.P., L.P." on Justia Law

by
After Rio School District’s new school was completed, the District and its general contractor (FTR) engaged in a decade-long legal battle, resulting in a judgment for FTR exceeding $9 million. Public Contract Code section 7107 allows a public entity to withhold funds due a contractor when there are liens on the property or a good faith dispute concerning whether the work was properly performed. The trial court assessed penalties against District because it did not timely release the retained funds. The court of appeal affirmed in part. A dispute over the contract price does not entitle a public entity to withhold funds due a contractor; the doctrine of unclean hands does not apply to section 7107; the trial court properly rejected the District's action under the False Claims Act, Government Code section 12650 and properly assessed prejudgment interest, subject to adjustment for any extra work claims found untimely on remand. The trial court erred in its interpretation of a contract provision imposing time limitations to submit the contractor's claims for extra work as requiring a showing of prejudice and erred in awarding fees for work not solely related to FTR's section 7107 cause of action. View "East West Bank v. Rio School Dist." on Justia Law

by
Defendants, Keith McNamara, Shirley Benton, and Jerel Benton, appealed: (1) a jury verdict in favor of the plaintiffs, Richard and Mary Murray, on their claim that the defendants breached the implied warranty of workmanlike quality; (2) a Superior Court order denying their motion to dismiss the plaintiffs' New Hampshire Consumer Protection Act (CPA) claim; and (3) a Superior Court order finding that the defendants violated the CPA when they built the plaintiffs' home with latent structural defects that caused mold growth. Defendants argued that, because plaintiffs' claim was exempt from the CPA, the trial court erred by denying their motion to dismiss. Defendants added that the trial court erred by denying their motion for a judgment notwithstanding the verdict (JNOV) on the plaintiffs breach of implied warranty claim. There is no dispute that the transaction at issue here is the defendants alleged construction of the house with latent structural defects, not any representations that the defendants made to others during or after construction. The New Hampshire Supreme Court affirmed, finding that because the house was completed in 2004 and was purchased by the plaintiffs five years later and the allegedly wrongful transaction occurred more than three years before the plaintiffs "knew or reasonably should have known" of it, the construction of the house was an exempt transaction pursuant to RSA 358-A:3, IV-a and that plaintiffs' CPA claim should have been dismissed. Thus, the Court reversed the trial court's ruling on the CPA claim. However, the Court was not persuaded that defendants were insulated from liability on the breach of the implied warranty of workmanlike quality claim. Because the Court reversed the trial court's judgment on the CPA claim, defendants failed to show that they were prejudiced with respect to the breach of warranty claim. View "Murray v. McNamara" on Justia Law

by
Atwood Health Properties, LLC contracted with Calson Construction Company to construct a medical office building. Calson engaged Gem Plumbing & Heating Co., Inc. (GEM) as a subcontractor to design and install a heating, ventilation, and air conditioning (HVAC) system. Five years after the project was completed, Atwood sold the building to Atwood Medical Properties, LLC (AMP). When AMP experienced compressor failures in the HVAC system, AMP filed suit against Atwood. Atwood paid for a new HVAC system and initiated arbitration proceedings against Calson to recover its costs. Calson, in turn, initiated an arbitration proceeding against GEM for indemnification under the parties’ contract. The two arbitration proceedings were consolidated. The arbitrator concluded that Calson should pay Atwood $358,223 and that GEM should pay Calson that same amount. The superior court confirmed the arbitration award. GEM appealed. The Supreme Court affirmed, holding that the trial justice properly confirmed the arbitration award. View "Atwood Health Props., LLC v. Calson Constr. Co." on Justia Law

by
The Department of Agriculture’s Rural Utilities Service (RUS) made a $267 million loan to Open Range to finance construction of wireless broadband networks in 540 RUS-approved markets. Open Range subcontracted with G4S. The FCC suspended a permit, so that Open Range lost the spectrum rights necessary to operate the planned network. RUS gave notice of its intent to terminate remaining funds on the loan unless Open Range could obtain replacement rights. Open Range began failing to meet its obligations to subcontractors. The Secretary of Agriculture made loan money available, provided a press release, and offered to reassure subcontractors, but Open Range was unable to regain the full spectrum rights necessary to complete the original project. RUS and Open Range executed an amendment to reflect a loan amount reduced to $180 million, and 160 RUS-approved markets, but Open Range remained unable to satisfy its debts and filed for bankruptcy. G4S filed suit. The Claims Court held that G4S was not a third party beneficiary to the agreement. The Federal Circuit affirmed, stating that G4S asked that the government incur liability simply because it talked to the individuals in charge of a failing project in an attempt to fix the problems. View "G4S Tech., LLC v. United States" on Justia Law

by
In 2003, the VA entered into a contract with Reliable for electrical improvements at a VA medical center, requiring installation of three backup generators, “new and of the most suitable grade.” Federal Acquisition Regulation 52.211-5, incorporated by reference, requires that supplies be “new, reconditioned, or remanufactured,” and defines “new” as “composed of previously unused components.” Reliable sub-contracted to Fisk, which contracted with DTE. In 2004, DTE delivered two Cummins Power Generation generators to the construction site. The VA’s senior resident engineer inspected the generators and determined that they were not “new.” He wrote to Reliable, stating: They show a lot of wear and tear including field burns to enlarge mounting holes. Are they new and will you certify them as such? I cannot pay you … without that certification. Fisk and Reliable initially agreed that the generators did not meet the contract specification. After investigation, they concluded that the generators, manufactured in 2000, had been previously purchased by others but never used. Fisk obtained different generators, which were accepted by the VA. In 2007, Reliable submitted a claim, seeking $1,100,000 for additional costs incurred as a result of rejection of the original generators. In 2013, the Board of Contract Appeals denied Reliable’s claim. The Federal Circuit vacated, holding that the Board erred in its interpretation of the contract. View "Reliable Contracting Grp., LLC v. Dep't of Veterans Affairs" on Justia Law

by
Lydig Construction was the general contractor on a large public works project. Martinez Steel was the original steel supply subcontractor on the project. Lydig sued Martinez for additional costs Lydig incurred because Martinez failed to timely supply steel for the project; Lydig, with the public agency's approval, had been required to replace Martinez as the steel supplier. Lydig moved for a right to attach order and a writ of attachment and presented the trial court with its business records and declarations from its employees. Martinez opposed Lydig's motion and presented declarations from one of its employees that set forth its contention Lydig owed it for, among other items, steel Martinez had delivered to the project. Martinez filed a cross-complaint in which it alleged claims that, if successful, would entirely offset Lydig's claims against it. The trial court granted Lydig's motion and issued writs of attachment in the amount of $203,315. The court of appeal affirmed, rejecting Martinez's contentions that its cross-complaint, as a matter of law, prevented the trial court from issuing a writ of attachment against it and that Lydig's application for a writ of attachment was not supported by substantial evidence. View "Lydig Constr., Inc. v. Martinez Steel Corp." on Justia Law

by
Belasco bought a new Manhattan Beach residence in 2004 from the builder (Wells). In 2006, Belasco filed a complaint with the Contractors State License Board, alleging construction defects. Belasco and Wells settled the dispute in 2006, with Wells paying $25,000 and Belasco executing a release and a Civil Code 15241 waiver of all known or unknown claims. In 2012, Belasco sued, based on an alleged roof defect discovered in 2011. The trial court entered summary judgment, finding the action barred by the settlement. The court of appeal affirmed, rejecting arguments that: the 2006 general release and waiver for patent construction defects is not a “reasonable release” of a subsequent claim for latent defects under section 929 and the Right to Repair Act (section 895); a reasonable release can only apply to a “particular violation” and not to a latent defect under section 945.5(f), and the 2006 settlement was too vague to be a valid; section 932 authorizes an action on “[s]ubsequently discovered claims of unmet standards;” public policy prohibits use of a general release and section 1542 waiver to bar a subsequent claim for latent residential construction defects; and a genuine issue of fact existed concerning fraud and negligence claims that would void the settlement under section 1668. View "Belasco v. Wells" on Justia Law

by
In 2004, K-Con entered into a contract with the federal government to construct a Coast Guard building in Port Huron Michigan for $582,641. Once K-Con finished, the government imposed liquidated damages of $109,554 for tardiness of 186 days in completion. KCon sued, seeking remission of the liquidated damages on two grounds—that the contract’s liquidated-damages clause was unenforceable and that KCon was entitled to an extension of the completion date. KCon also requested additional compensation based on work performed in response to government requests that K-Con alleges amounted to contract changes. The Court of Federal Claims held that the contract’s liquidated damages clause was enforceable; that K-Con did not comply with the written-notice precondition for invoking the contract clause governing changes; and that K-Con’s claim for an extension on the completion date must be dismissed for lack of jurisdiction. The Federal Circuit affirmed. K-Con failed to comply with the changes clause, and its after-the-fact speculations about what would have happened had it complied do not create a genuine dispute of material fact regarding whether it should be excused for its failure. View "K-Con Bldg. Sys., Inc. v. United States" on Justia Law