GSS Group Ltd. v. Republic of Liberia
GSS appealed the district court’s dismissal of its second attempt to confirm a $44 million arbitral award entered against the Port Authority for breach of a construction contract. GSS first tried to confirm the award, but the district court found that it had no personal jurisdiction over the Port Authority. Then GSS filed its second petition, also naming the Republic of Liberia, which owns the Port Authority, as respondents. The district court again dismissed GSS’s petition, finding that issue preclusion barred relitigating its personal jurisdiction over the Port Authority and that GSS failed to demonstrate that Liberia was liable for the Port Authority’s alleged breach. The court affirmed the district court's dismissal of the claims against Liberia for lack of subject matter jurisdiction under the Foreign Sovereign Immunities Act (FSIA), 28 U.S.C. 1330 et seq.; affirmed the district court's dismissal of GSS's petition against the Port Authority on sovereign immunities grounds; and concluded that the district court did not abuse its discretion by dismissing GSS's petition before allowing jurisdictional discovery. View "GSS Group Ltd. v. Republic of Liberia" on Justia Law
Wyandotte Electric Supply Co. v. Electrical Technology Systems, Inc.
In 2009 and 2010, the south wing of the Detroit Public Library was renovated. Defendant KEO & Associates, Inc. (KEO) was the principal contractor for this project. Defendant Westfield Insurance Company supplied KEO with a payment bond worth $1.3 million, as required by the public works bond act (PWBA). KEO was identified as the principal contractor and Westfield as the surety on the bond. KEO subcontracted with defendant Electrical Technology Systems, Inc. (ETS) to provide labor and materials for electrical work. The agreement between KEO and ETS included a pay-if-paid clause, obliging KEO to pay ETS only after KEO had been paid for the relevant portion of work performed. ETS in turn subcontracted with Wyandotte Electric Supply Company for materials and supplies, making Wyandotte a sub-subcontractor from KEO’s perspective. ETS and Wyandotte first formed a relationship in 2003, when they entered into an “open account” agreement that governed ETS’s purchases from Wyandotte. Over the course of the project, ETS paid Wyandotte only sporadically and the unpaid balance grew. Initially, Wyandotte supplied materials on credit and credited ETS’s payments to the oldest outstanding balance, but eventually Wyandotte began to ship materials only for cash on delivery. Wyandotte sent certified letters to KEO and Westfield asking for a copy of the payment bond related to the library renovation project. The letter, on Wyandotte’s letterhead, referred to the “Detroit Public Library South Wing with [ETS.]” According to Wyandotte, KEO provided a copy of the payment bond the next day. Wyandotte also sent KEO a 30-day “Notice of Furnishing” in accordance with MCL 129.207, explaining that it was one of ETS’s suppliers. Wyandotte also sent copies of the letter to Westfield, the library, and ETS. The issue this case presented for the Supreme Court's revie centered on whether actual notice was required for a sub-subcontractor to recover on a payment bond when that sub-subcontractor complied with the notice requirements set forth in MCL 129.207. Furthermore, this case raised the question of whether a PWBA claimant could recover a time-price differential and attorney fees that were provided for by the claimant’s contract with a subcontractor, but were unknown to the principal contractor holding the payment bond as well as the principal’s surety. The Supreme Court concluded that the PWBA contained no actual notice requirement for claimants that comply with the statute, that the trial court properly awarded a time-price differential and attorney fees on past-due invoices to Wyandotte, and that the trial court erred in awarding postjudgment interest under MCL 600.6013(7). Accordingly, the Court affirmed the Court of Appeals with regard to the first two issues and reversed with regard to the third. View "Wyandotte Electric Supply Co. v. Electrical Technology Systems, Inc." on Justia Law
Lamar Contractors, Inc. v. Kacco, Inc.
Lamar Contractors, Inc. was general contractor on a construction project, and entered into a subcontract with Kacco, Inc. to provide metal framing and drywall work on the project. The subcontract included a “pay-if-paid” payment provision, which afforded Lamar ten days to remit payment to its subcontractors after receipt of payment from the owner. Kacco began work on the project but experienced recurring problems with providing manpower and paying for supplies. Kacco submitted an invoice for work that reflected that forty-five percent of the work had been performed. Lamar paid the invoice prior to receiving payment from the owner. Lamar sent Kacco an email noting its concerns with whether Kacco would be able to perform under the subcontract. Kacco notified Lamar that Kacco was waiting on another payment so that it could order and pay for supplies to finish the project. Lamar had received payment from the owner on January 26; however, pursuant to the subcontract, Lamar was not required to make payment to Kacco until February 9, ten business days later. Lamar officially terminated Kacco’s subcontract in a letter dated February 5. After termination of the subcontract with Kacco, Lamar hired another contractor to complete the work. Lamar then sued Kacco for breach of the subcontract. Kacco countersued Lamar for allegedly failing to pay for work performed under the contract, and that failure to pay caused it to breach. After a bench trial, the district court entered judgment on the main demand for Lamar for $24,116.67 with interest, $7,681.75 for attorney’s fees, and $3,105.81 in costs. Additionally, the district court entered a judgment in the amount of $60,020.00 plus interest in favor of Kacco on its countersuit. Lamar appealed but the court of appeal affirmed. Under the circumstances of this case, it was clear to the Supreme Court that Lamar did not violate any obligation owed under the contract to make payment to Kacco and could not have negligently contributed to Lamar’s breach of its obligations under the contract. Accordingly, the district court erred in reducing Lamar’s award of damages. The case was remanded for further proceedings. View "Lamar Contractors, Inc. v. Kacco, Inc." on Justia Law
Pierce Foundations, Inc. v. JaRoy Construction, Inc.
This matter stemmed from a public works project for the construction of a gymnasium in Terrytown. JaRoy Construction Inc. served as the general contractor, and pursuant to statute, furnished a surety bond to Jefferson Parish. Ohio Casualty Insurance Company was the surety. JaRoy entered into a written subcontract with Pierce Foundations, Inc. to provide and install pilings for the project. Once finished, Pierce alleged JaRoy failed to pay certain funds due under the subcontract. Pierce sued both JaRoy and Ohio Casualty Insurance, alleging they were jointly and severally liable to Pierce. JaRoy filed for bankruptcy, leaving only Ohio Casualty Insurance as party to the suit. When the project was substantially completed, the Jefferson Parish government filed a notice of acceptance of work with the Jefferson Parish mortgage records office. This occurred over a year after Pierce amended its lawsuit to add Ohio Casualty as a defendant. Pierce never filed a sworn statement of claim in the mortgage records. Ohio Casualty filed a motion for summary judgment, contending that Pierce was required to comply with statutory notice and recordation, and because it failed to do so within 45 days of Jefferson Parish’s acceptance of the project, Pierce could not recover from Ohio Casualty. Pierce argued that the statute did not affect its right to proceed in contract. After a bench trial, the trial court rendered judgment in favor of Pierce for sums owed under the contract plus judicial interest from the date of the original judgment. Ohio Casualty appealed, arguing that the trial court erred in not dismissing Pierce's claims. The court of appeal reversed and ruled in Ohio Casualty's favor. The Supreme Court, however, disagreed and affirmed the trial court judgment. View "Pierce Foundations, Inc. v. JaRoy Construction, Inc." on Justia Law
Travelers Prop. Cas. Co. v. Stresscon Co.
Stresscon Corporation, a subcontracting concrete company, filed suit against Travelers Property Casualty Company of America, alleging, among other things, that Travelers acted in bad faith, unreasonably delaying or denying its claim for covered insurance benefits; and Stresscon sought awards of two times the covered benefits along with fees and costs, as prescribed by statute. Stresscon’s claims for relief arose from a 2007 serious construction accident which was caused by a crane operator employed by a company that was itself a subcontractor of Stresscon. Stresscon’s general contractor, Mortenson, sought damages from Stresscon, asserting Stresson’s contractual liability for the resulting construction delays, and Stresscon in turn sought indemnification from Travelers. Travelers petitioned for review of the court of appeals’ judgment affirming the district court’s denial of its motion for directed verdict in a lawsuit brought by its insured, Stresscon. Much as the district court had done, the appellate court rejected Travelers’ contention that the no-voluntary-payments clause of their insurance contract relieved it of any obligation to indemnify Stresscon for payments Stresscon had made without its consent. Instead, the court of appeals found that the Colorado Supreme Court's opinion in "Friedland v. Travelers Indemnity Co.," (105 P.3d 639 (2005)) had effectively overruled the Court's prior “no voluntary payments” jurisprudence to the contrary and given Stresscon a similar opportunity. The Supreme Court reversed, finding that its adoption of a notice-prejudice rule in "Friedland" did not overrule any existing “no voluntary payments” jurisprudence. The Court declined to extend a notice-prejudice reasoning to Stresscon’s voluntary payments, made in the face of the no-voluntary-payments clause of its insurance contract with Travelers. View "Travelers Prop. Cas. Co. v. Stresscon Co." on Justia Law
J.D. Donovan, Inc. v. Minn. Dep’t of Transp.
At issue in this case was whether truck drivers hauling asphalt cement from a commercial oil refinery to a contractor’s facility are performing “work under a contract” under Minn. Stat. 177.44(1) and, therefore, must be paid prevailing wages. The Minnesota Department of Transportation (MDOT) determined that the construction companies that were awarded contracts to work on state highway projects violated the project contracts by failing to ensure that drivers that assisted in the acquisition and transport of asphalt cement for the projects were paid prevailing wages. Appellants argued that the hauling activities of these drivers did not constitute “work under a contract” under Minn. Stat. 177.44(1) and, alternatively, that the hauling activities were exempt from the prevailing wage requirements under the “commercial establishment exception” in the Prevailing Wage Act. The district courts granted summary judgment to MDOT. The court of appeals affirmed. The Supreme Court reversed, holding that hauling activities must be to, from, or on the site of a public works project to qualify as “work under a contract,” and therefore, the hauling activities in this case did not constitute “work under the contract” subject to the prevailing wage requirements. View "J.D. Donovan, Inc. v. Minn. Dep’t of Transp." on Justia Law
LTL Acres Limited Partnership v. Butler Manufacturing Co.
This litigation arose from the construction of a "Johnny Janosik" furniture store in Laurel. The Plaintiff-appellant LTL Acres Limited Partnership (LTL) was the owner of the Janosik Building. Defendant-appellee Butler Manufacturing Company (Butler) provided pre-engineered components which were used to build the roof and exterior walls. Defendant-appellee Dryvit Systems, Inc. (Dryvit) supplied a product used on the exterior finish of the walls, to protect and seal them. Dryvit warranted its product for ten years from the "date of substantial completion of the project." The building was completed in 2006. Unfortunately, the building had issues with water infiltration from the beginning. By February 2012, cladding began to crack and buckle. The water infiltration and delamination persisted through 2013 despite attempts to fix the issues. LTL brought this action in 2013, alleging breach of warranty, breach of contract, and negligence claims against Butler; and breach of warranty and breach of contract claims against Dryvit. The Superior Court granted summary judgment to both Butler and Dryvit on the grounds that the actions against both were barred by the applicable statute of limitations. It held that the action against Butler was barred by 10 Del. C. sec. 8127,which is a six year statute of limitations relating to alleged defective construction of an improvement to real property. After review, the Supreme Court concluded that summary judgment in favor of Butler was proper. The Superior Court ruled that LTL’s action against Dryvit was barred by a four year statute of limitations set forth in 6 Del. C. sec. 2-725. Dryvit gave LTL a ten year express warranty. The Superior Court described the warranty as a “repair and replacement warranty” and reasoned that such a warranty cannot be one that extended to future performance. It therefore concluded that the statute of limitations for an action on the warranty expired not later than four years after the Dryvit product was tendered and applied to the building; that is, not later than four years after 2006. The Supreme Court concluded that grant of summary judgment in favor of Dryvit was inappropriate, and had to be reversed. The case was remanded for further proceedings. View "LTL Acres Limited Partnership v. Butler Manufacturing Co." on Justia Law
Blois Construction v. FCI/Fluor/Parsons
Pursuant to Public Contract Code section 7107, when a project owner pays a direct contractor the amount it had previously withheld as retentions, the direct contractor must pay its subcontractors their share of the retention within seven days or face penalties. The court concluded that, in this case, the decision by the owner to stop withholding future retentions and pay full progress payments to the contractor was not equivalent to a payment by the owner of past retentions under section 7107. Accordingly, the court concluded that the subcontractor is not entitled to late payment penalties under section 7107. The court affirmed the trial court's judgment. View "Blois Construction v. FCI/Fluor/Parsons" on Justia Law
Welch Construction & Excavating, LLC v. Duong
Linh Duc Duong, doing business as Classy Nails, appealed after a bench trial awarded Welch Construction & Excavating, LLC, $30,825, plus interest, for the balance due on a construction contract. Welch Construction sued Duong, alleging the parties contracted for Welch Construction to remodel a vacant retail space in Kirkwood Mall into a Classy Nails salon for $92,225. Welch Construction alleged it completed the work and Duong failed to pay the balance of $30,825 due under the contract. Duong answered and counterclaimed, denying he owed an outstanding balance under the contract and alleging Welch Construction breached the contract by failing to remodel the retail space in a timely and workmanlike manner according to his specifications. Duong claimed he was entitled to a setoff against any balance owed under the contract for his damages caused by Welch Construction's failure to complete the work before Thanksgiving 2013 and failure to construct the salon according to his specifications. Duong sought lost profits and damages for repairing the work according to his specifications. After review, the Supreme Court concluded the district court did not clearly err in finding: (1) the parties did not orally contract for a specific completion date for the construction project; (2) Welch Construction did not unreasonably delay completion of the project; and (3) Duong failed to establish his damages for costs to repair and lost profits for Welch Construction's claimed failure to complete the project according to his specifications. View "Welch Construction & Excavating, LLC v. Duong" on Justia Law
Tom v. Innovative Home Sys.
Respondent, a contractor, and Appellant, a homeowner, entered into a contract under which Respondent agreed to install automation, sound, surveillance, and landscaping systems in Appellant’s residence. Respondent did not have an electrical contractor’s license when it bid the contract and began the work but did receive a license before it completed the work. When the parties disagreed on the performance of the contract, Appellant refused to tender further payment to Respondent, and Respondent filed a notice of lien against Appellant’s residence. Respondent filed a complaint alleging breach of contract, breach of the covenant of good faith and fair dealing, foreclosure of notice of lien, and declaratory relief, alleging that an electrical license was not required for the work performed on Appellant’s residence and that its lien was proper and perfected. The district court granted summary judgment in favor of Respondent. The Supreme Court reversed, holding that genuine issues of material fact existed regarding whether Respondent’s work on Appellant’s residence required a license and whether Respondent completed the contract in a workmanlike manner, thereby possibly negating Appellant’s obligation to make final payment under the contract. Remanded. View "Tom v. Innovative Home Sys." on Justia Law