Justia Construction Law Opinion Summaries
Articles Posted in Contracts
A. Scott Enterprises v. City of Allentown
Appellant City of Allentown (City) contracted with appellee A. Scott Enterprises, Inc. (ASE), to construct a new public road. After arsenic-contaminated soil was discovered at the worksite, the City suspended work on the project. Following testing, it was determined construction could resume if precautions were taken. Accordingly, the City instructed ASE to obtain revised permits and proceed with the project. However, the existing contract did not include terms regarding the potential for contaminated soil, despite the fact the City was aware there might be contamination prior to entering into the contract, and ASE declined to proceed, explaining it would incur substantial additional costs due to the contaminated soil. The parties made several attempts to reach an agreement in which ASE would continue the construction, but to no avail. Consequently, ASE sued the City to recover its losses on the project, alleged breach of contract, and sought compensation under theories of quantum meruit and unjust enrichment, as well as interest and a statutory penalty and fee award for violations of the prompt pay provisions of the Procurement Code. After a trial, a jury found the City breached its contract with ASE and also withheld payments in bad faith. In this discretionary appeal, the issue this case presented for the Supreme Court's review was whether an award of a statutory penalty and attorney fees under the prompt payment provisions of the Commonwealth’s Procurement Code was mandatory upon a finding of bad faith, irrespective of the statute’s permissive phrasing. The Court held such an award was not mandatory, and therefore reversed the order of the Commonwealth Court and remanded the case to the trial court for further proceedings. View "A. Scott Enterprises v. City of Allentown" on Justia Law
Flintco Pacific v. TEC Mgmt. Consultants
After TEC, a subcontractor, submitted a written bid to Flintco, a general contractor, to perform glazing work on a project, Flintco used TEC's bid price in compiling its own bid to the owner of the project. Flintco was awarded the contract and sent TEC a letter of intent to enter into a subcontract and a standard-form subcontract, both of which documents differed materially from TEC’s bid. TEC refused to enter into a subcontract. Flintco secured another subcontractor for that scope of work and sued TEC on a theory of promissory estoppel seeking the difference between TEC’s bid and the amount Flintco was required to pay the replacement subcontractor. The trial court entered judgment for TEC. The court concluded that Flintco failed to demonstrate that there was no substantial evidence to support the trial court’s finding that Flintco did not reasonably rely on TEC’s bid price without considering the material conditions stated in TEC’s bid, the proposed subcontract Flintco sent TEC constituted a counteroffer because it contained material variations from the conditions in TEC’s bid, and the counteroffer gave TEC the right to withdraw its bid. Accordingly, the court affirmed the judgment. View "Flintco Pacific v. TEC Mgmt. Consultants" on Justia Law
Smith v. D.R. Horton, Inc
In August 2005, D.R. Horton, Inc. completed construction of the Smiths' home, and the Smiths closed on the property and received the deed. Thereafter, the Smiths experienced a myriad of problems with the home that resulted in severe water damage to the property. D.R. Horton attempted to repair the alleged construction defects on "numerous occasions" during the next five years, but was ultimately unsuccessful. In 2010, the Smiths filed a construction defect case against D.R. Horton and seven subcontractors. In response, D.R. Horton filed a motion to compel arbitration. The Smiths opposed the motion, arguing, inter alia, that the arbitration agreement was unconscionable and therefore unenforceable. The circuit court denied D.R. Horton's motion to compel arbitration, finding that the arbitration agreement was unconscionable. D.R. Horton appealed, but finding no error in the circuit court's decision, the South Carolina Supreme Court affirmed. View "Smith v. D.R. Horton, Inc" on Justia Law
Arthur v. State, Dep’t of Hawaiian Home Lands
Plaintiffs brought a wrongful death action against Kamehameha Investment Corporation (KIC), the developer of a hillside area, and Sato and Associates, Inc. and Daniel Miyasato (collectively, Sato), the civil engineer. KIC tendered defense against Plaintiffs’ claims to Sato pursuant to a hold harmless clause in a project consultant agreement between Sato and KIC. KIC filed a cross-claim against Sato, alleging that Sato had agreed to defend and indemnify KIC against Plaintiffs’ claims. The trial court granted KIC’s motion for partial summary judgment against Sato. Relying on Pancakes of Hawaii, Inc. v. Pomare Properties Corp., the Intermediate Court of Appeals (ICA) affirmed, concluding that Sato had a contractual duty to defend KIC in the wrongful death action. The Supreme Court vacated the ICA’s judgment, holding (1) Haw. Rev. Stat. 431:10-222 renders invalid any provision in a construction contract requiring the promisor to defend “the promisee against liability for bodily injury to persons or damage to property caused by or resulting from the sole negligence of willful misconduct of the promisee, the promisee’s agent or employees, or indemnitee”; (2) Pancakes does not apply to defense provisions in construction contracts; and (3) the scope of a promisor’s duty to defend imposed by a construction contract is determined at the end of litigation. Remanded. View "Arthur v. State, Dep’t of Hawaiian Home Lands" on Justia Law
Pizano v. Lacey & Assoc., LLC
In 2012, Lacey & Associates, LLC, contracted with Everest Homes, LLC, to purchase a commercial building. In addition, Lacey and Everest executed an escrow agreement for the release of additional funds to Everest if the roof was replaced after title had transferred to Lacey. After title passed to Lacey, Everest entered into a contract with the Williams Group, a contractor, to replace the roof. The Williams Group then hired Andrea Pizano to remove the old roof and HVAC units, which service she performed. In early 2013, Pizano sued alleging the Williams Group did not pay the contractual amount of $11,085, as agreed by the two parties. She filed a mechanic's lien on Lacey's building one day before she filed her petition. The lawsuit sought judgment against the Williams Group in the amount of $11,085, plus interest. The Williams Group never filed an answer. The trial court thereafter entered a default judgment against the Williams Group, awarding Pizano $11,085, an attorney's fee of $2,500.00 and court costs of $461.81. Pizano then sought to foreclose her lien against Lacey and be awarded court costs and attorney fees. She requested that the property be sold to satisfy the judgment. Lacey answered and included a "Cross-motion for Summary Judgment," contending that the new roof leaked so badly that large barrels had to be placed inside the building to catch the water. Therefore, no party was entitled to be paid for the roof. Lacey also asserted that Pizano's motion should be denied because Lacey had no contract with Pizano, and also that the plaintiff failed to file the required pre-lien notice. The trial court granted Pizano's summary judgment motion in part, and denied Lacey's counter-motion for summary judgment. Lacey appealed and Pizano counter-appealed. The Court of Civil Appeals held that Pizano successfully preserved her subcontractor's lien, but found that genuine disputes of fact remained as to the amount owed to Pizano and the enforceability of the lien. The Supreme Court found that the Legislature intended amounts less than $10,000 to be exempt from pre-lien notice. Having provided such an exception, the wording of the applicable statute persuaded the Court that "if a claimant filed a claim of $10,085 without a pre-claim notice, the claim would be enforceable up to $9,999. We do not believe that the claim would be completely unenforceable if it exceeded that legislatively-approved amount by a mere $86." The trial court's order entitling Pizano to a reduced judgment amount of $9,999.00 and an award of attorneys' fees and costs was affirmed. This case was remanded to the trial court to issue a judgment consistent with the law as expressed in the Supreme Court's opinion. View "Pizano v. Lacey & Assoc., LLC" on Justia Law
C.G. Schmidt Inc. v. Permasteelisa N. Am.
Using a form provided by CGS, the general contractor for construction of an 18-story Milwaukee office building, PNA submitted a $12,675,421 bid to provide a glass curtainwall--a nonstructural outer covering for weatherproofing and aesthetics. The contract manual provided by CGS stated that “[t]he bidder must accept all terms of the [standard CGS] subcontract as a condition for submitting a bid.” After CGS chose PNA’s bid, PNA repeatedly expressed a need to review the finalized prime contract before it would execute a formal subcontract. CGS and PNA engaged in a “value engineering process” during which they refined the price and other terms of the subcontract. PNA regularly updated the proposed price and communicated the updates to CGS. Several times, PNA raised concerns about subcontract terms. CGS never indicated to PNA that, in CGS’s view, there was already an agreement in place. The parties never entered into a formal subcontract. CGS had to use a different subcontractor at a higher price. CGS filed suit. The district court granted PNA summary judgment, finding that the parties did not intend to be bound until the execution of a formal subcontract. The Seventh Circuit affirmed, agreeing that the parties never entered into a binding contract and that CGS’s promissory estoppel claim fails as a matter of law. View "C.G. Schmidt Inc. v. Permasteelisa N. Am." on Justia Law
Schumacher Homes of Circleville v. Spencer
Plaintiff signed a contract with Defendant for the construction of a house. The contract contained an arbitration clause. Plaintiff later brought suit against Defendant, claiming that there were defects in the house. Defendant filed a motion to dismiss and compel arbitration. The circuit court denied the motion, finding that the arbitration clause was unconscionable. Defendant appealed, arguing that the circuit court erred by ruling on questions of arbitrability despite the existence of a delegation provision in the arbitration agreement that vested the arbitrator with authority to determine issues of arbitrability relating to the dispute. The Supreme Court determined that the circuit court was within its rights not to enforce the delegation language because the language did not reflect the parties’ clear and unmistakable intention to delegate issues about the validity, revocability, or enforceability of the arbitration agreement to an arbitrator. The United States Supreme Court granted Defendant’s requested writ of certiorari, vacated the Supreme Court’s opinion, and remanded for further consideration in light of their decision in DIRECTV, Inc. v. Imburgia. The Supreme Court reversed the circuit court’s order, holding that because Plaintiffs never specifically challenged the delegation language before the circuit court or Supreme Court, Plaintiffs waived any right to challenge the delegation language. Remanded for arbitration. View "Schumacher Homes of Circleville v. Spencer" on Justia Law
Cashman Equip. Corp., Inc. v. Cardi Corp., Inc.
Cashman sued, alleging Cardi provided defective cofferdams for construction of the Sakonnet River Bridge. Cofferdams are temporary watertight enclosures that are pumped dry to expose the bottom of a body of water so that construction can occur. During discovery, Cashman sought, and Cardi refused to produce, computer models and draft reports that had been “considered by” its testifying engineering expert to determine “certain stress and loads that are going to be placed on certain points on this cofferdam,” including models “that [the expert] created which [he] may not have relied on but certainly would’ve considered” and draft reports. Cardi argued that Rule 26(b)(4)(A) of the Superior Court Rules of Civil Procedure does not allow discovery of materials “considered by” an expert in forming an expert opinion. The hearing justice concluded that he did not have the authority to compel production of the material. The Rhode Island Supreme Court affirmed, after considering interpretations of the corresponding Federal Rule. The state rule is “clear and unambiguous” and is confined to discovery through interrogatories or deposition. It does not provide for the disclosure of documents. View "Cashman Equip. Corp., Inc. v. Cardi Corp., Inc." on Justia Law
Travelers Prop. Cas. Co. v. Stresscon Co.
Travelers Property Casualty Company of America (Travelers) petitioned for review of a court of appeals judgment affirming the district court’s denial of its motion for directed verdict in a lawsuit brought by its insured, Stresscon Corporation. Stresscon, a subcontracting concrete company, filed suit against Travelers, alleging, among other things, that Travelers acted in bad faith, unreasonably delaying or denying its claim for covered insurance benefits; and Stresscon sought awards of two times the covered benefits along with fees and costs, as prescribed by statute. Stresscon’s claims for relief arose from a serious construction accident in July 2007, which was caused by a crane operator employed by a company that was itself a subcontractor of Stresscon. Stresscon’s general contractor, Mortenson, sought damages from Stresscon, asserting Stresson’s contractual liability for the resulting construction delays, and Stresscon in turn sought indemnification from Travelers. Although there was much dispute over the factual and legal import of Travelers’ reservation of rights and other of its communications with both Stresscon and Mortenson concerning Mortenson’s claim, there was no dispute that by December 31, 2008, Travelers had not paid the damages asserted by Mortenson. The appellate court rejected Travelers’ contention that the no-voluntary-payments clause of their insurance contract relieved it of any obligation to indemnify Stresscon for payments Stresscon had made without its consent. Instead, the court of appeals found that the Colorato Supreme Court's opinion in "Friedland v. Travelers Indemnity Co.," (105 P.3d 639 (2005)) had effectively overruled prior “no voluntary payments” jurisprudence to the contrary and given Stresscon a similar opportunity. The Supreme Court found that its adoption of a notice-prejudice rule in "Friedland" did not overrule any existing “no voluntary payments” jurisprudence in Colorado, and because the Court declined to extend notice-prejudice reasoning in Friedland to Stresscon’s voluntary payments, made in the face of the no-voluntary-payments clause of its insurance contract with Travelers, the judgment of the court of appeals was reversed. View "Travelers Prop. Cas. Co. v. Stresscon Co." on Justia Law
Fattah v. Bim
In 2005, Masterklad built a house in Glenview, including a brick patio that extended off the rear of the house. Because the ground underneath the patio sloped down, dirt and gravel were placed underneath it to support the bricks and make them level with the house's rear entrance. A retaining wall was built to contain the fill. In 2007, the house was sold by Masterklad to a Lubeck for $1,710,000. In the contract Lubeck “knowingly, voluntarily, fully and forever,” waived the implied warranty of habitability in exchange for an express warranty provided by Masterklad, with a one-year term. In 2010, Lubeck sold the house to Fattah, for $1,050,000, with a document stating that the house was being sold “as is” and that the seller made no representations or warranty regarding its condition. In 2011, parts of the retaining wall around the rear patio gave way and part of the patio collapsed. The owner sued. The circuit court found that the patio wall had given way due to latent defects in its construction, but that plaintiff could not recover because Masterklad had executed a valid, enforceable waiver of the implied warranty of habitability with Lubeck. The appellate court reversed. The Illinois Supreme Court reversed. The implied warranty of habitability may not be extended to a second purchaser of a house when a valid, bargained-for waiver of the warranty has been executed between the builder-vendor and the first purchaser. View "Fattah v. Bim" on Justia Law