Homeowners obtained loans from Bank for the construction of a new home and entered into an agreement with Contractor to complete the new home construction. When Homeowners defaulted on payments owed to Contractor and on both loans, the house was sold at foreclosure, and Homeowners filed for bankruptcy. Contractor filed a fourth amended complaint against Homeowners, who were later dismissed as parties, and Bank. Following a trial the court granted summary judgment for Bank on Contractor’s claims of fraud and civil conspiracy. The Supreme Court reversed. After remand, Contractor filed a fifth amended complaint, which differed from the fourth amended complaint in several respects. The district court determined that the election of remedies doctrine and judicial estoppel required a dismissal of Contractor’s claims. The Supreme Court reversed, holding (1) Contractor’s claims were consistently premised on the existence of a contract, and therefore, no election was required; and (2) Contractor’s claims were based on different facts and obligations, and therefore, both could be pursued. View "deNourie & Yost Homes, LLC v. Frost" on Justia Law

by
The Riverwalk at Arrowhead Country Club and Magnolia North Horizontal Property Regime developments were constructed between 1997 and 2000. After construction was complete and the units were sold, the purchasers became aware of significant construction problems, including building code violations, structural deficiencies, and significant water-intrusion problems. In 2003, the purchasers filed suit to recover damages for necessary repairs to their homes. Lawsuits were filed by the respective property owners' associations (POAs), which sought actual and punitive damages for the extensive construction defects under theories of negligent construction, breach of fiduciary duty, and breach of warranty. As to the Riverwalk development, individual homeowners also filed a class action to recover damages for the loss of use of their property during the repair period. The defendants in the underlying suits were the related corporate entities that developed and constructed the condominium complexes: Heritage Communities, Inc. (the parent development company), Heritage Magnolia North, Inc. and Heritage Riverwalk, Inc. (the project-specific subsidiary companies for each separate development), and Buildstar Corporation (the general contracting subsidiary that oversaw construction of all Heritage development projects), referred to collectively as "Heritage." The issues presented to the Supreme Court by these cases came from cross-appeals of declaratory judgment actions to determine coverage under Commercial General Liability (CGL) insurance policies issued by Harleysville Group Insurance. The cases arose from separate actions, but were addressed in a single opinion because they involved virtually identical issues regarding insurance coverage for damages. The Special Referee found coverage under the policies was triggered and calculated Harleysville's pro rata portion of the progressive damages based on its time on the risk. After review of the arguments on appeal, the Supreme Court affirmed the findings of the Special Referee in the Magnolia North matter, and affirmed as modified in the Riverwalk matter. View "Harleysville Group Ins. v. Heritage Communities, Inc." on Justia Law

by
This appeal stemmed from a dispute over the construction of a backyard patio at Defendant’s property. Defendants, the property owners, hired a general contractor, who contracted with Plaintiff for masonry work. Plaintiff filed suit, asserting that Defendants owed it money beyond that paid to it by the general contractor. At issue during the bench trial was whether Plaintiff was paid to construct Defendants’ backyard patio. The trial justice ultimately entered judgment for Defendants. Plaintiff appealed, arguing that the trial justice erred in his factual determinations and credibility assessments. The Supreme Court affirmed, holding that the trial justice neither overlooked nor misconceived material evidence. View "A. Salvati Masonry Inc. v. Andreozzi" on Justia Law

by
Twalker Development, LLC appealed a judgment granting KLE Construction LLC's claim for unjust enrichment and ordering Twalker to pay $87,958.74 in damages. KLE and Twalker engaged in negotiations for KLE to provide construction services to Twalker in exchange for four lots located in Twalker's development. KLE and Twalker never executed a written contract finalizing the terms of an agreement. KLE began performing construction services on the property, including preliminary dirt work related to clearing and scraping the property. KLE also hired an engineering firm to create plans to subdivide the property for future sales. KLE and Twalker disagreed about certain aspects of the project, and Twalker terminated KLE's services. Twalker continued to develop the property and did not compensate KLE for the services it provided. KLE sued Twalker for breach of contract, unjust enrichment, and forbearance. After a bench trial, the district court dismissed KLE's breach of contract claim, finding KLE failed to establish the existence of a contract. The court dismissed KLE's forbearance claim, stating forbearance was not a separate and distinct claim. The court granted KLE's unjust enrichment claim and found KLE was entitled to $90,857 in damages. The court ordered each party pay the other party's costs and disbursements. A judgment was entered in favor of KLE for $87,958.74. After review, the Supreme Court concluded the district court did not err in granting KLE's unjust enrichment claim and awarding damages. View "KLE Construction, LLC v. Twalker Development, LLC" on Justia Law

by
Arundel Valley, LLC, the developer of a facility for a butter manufacturer, filed a complaint against Branch River Plastics, Inc., a manufacturer and distributor of insulated roofing panels, alleging, inter alia, defects in roofing panels that Branch River had manufactured and supplied to Arundel Valley for a construction project. A jury found in Arundel Valley’s favor on its claims that Branch River breached implied warranties by supplying defective roofing panels. Branch River filed a motion for a new trial, which the court denied. The Supreme Judicial Court reversed, holding that the trial court erred in declining to adjudicate whether Branch River had disclaimed implied warranties. Remanded. View "Arundel Valley, LLC v. Branch River Plastics, Inc." on Justia Law

by
Defendant Veterans Parkway Developers, LLC (“VPD”) appealed a Superior Court order granting injunctive relief and requiring an accounting in this suit by RMW Development Fund, II, LLC (“RMW”) stemming from VPD’s management of Veterans Parkway Apartments, LLC (the “Company”). The order at issue granted RMW an interlocutory injunction: (1) enjoining VPD from using funds in its possession or control to construct a second entrance to an apartment complex in Columbus (the “Property”), constructed and managed by the Company; (2) prohibiting VPD from using funds for any purpose other than the normal day-to-day expenses of the Property; and (3) requiring VPD to submit a monthly report of its expenses to the superior court, with copies to counsel for the parties. RMW filed suit against VPD alleging VPD’s breach of contract by its entering into an unauthorized management agreement and thereby paying an unauthorized management fee, and a claim for “promissory estoppel,” stemming from VPD’s alleged failure to use some of the Company’s funds for partial repayment of a development loan; RMW asked for VPD’s removal as manager of the Company and for the costs of litigation. Prior to the filing on the complaint, the Company had purchased a 60-foot strip of land for the purpose of creating a second entrance to the Property. At a hearing on the injunction, RMW argued that it could not undo any construction of the second entrance to the Property. VPD countered that RMW was, in reality, concerned about money being spent on the construction of the second entrance instead of being used to repay the loans made by RMW, and that any appropriate redress was monetary damages. Ultimately the injunction was granted and VPD appealed. The Supreme Court found after review of this matter that the trial court's injunction was not supported by the record, and that court abused its discretion in granting the injunction. The Supreme Court reversed the trial court and remanded this matter for further proceedings. View "Veterans Parkway Developers, LLC v. RMW Development Fund II, LLC" on Justia Law

by
The issue in this appeal centered on whether a force majeure clause in a written contract between the county and a developer did not apply to the developer’s failure to obtain zoning approval in order to construct the cement plant required in the agreement. After review of the contract and the clause at issue here, the Supreme Court held that the clause was broad enough to apply. Accordingly, the Court vacated the district court's judgment and remanded this case for further proceedings. View "Burns Concrete, Inc v. Teton County" on Justia Law

by
Kiva Lodge Condominium Owners' Association, Inc. ("Kiva Lodge") was an Alabama nonprofit corporation formed for the purpose of administering and maintaining the Kiva Dunes Clubhouse and Condominium ("Kiva Dunes") located in Gulf Shores. In 2009, Kiva Lodge contracted with Hudak & Dawson Construction Co., Inc. ("Hudak") to be the general contractor for the remediation of deficiencies in Kiva Dunes buildings that were allowing water to enter the buildings. Hudak subcontracted the stucco and/or sealant portion of the work to Don Colvin d/b/a Colvin Plastering ("Colvin"). The Hanover Insurance Company ("Hanover"), as surety for Hudak, issued to Kiva Lodge a performance bond ensuring and/or securing the full performance of Hudak's contractual obligations. In September 2012, Kiva Lodge informed Hudak and Colvin of leaks and bubbling in the stucco exterior of the buildings at Kiva Dunes caused by water intrusion. Kiva Lodge alleged that Hudak and Colvin failed to determine and/or disclose the course of the problems and the proper scope of repairs necessary. It also alleged that Hanover breached the terms of its performance bond by failing to promptly remedy the default, complete the work within the scope of the contract in accordance with the terms and conditions, or arrange for payment of an alternative contractor to complete the work. Hanover filed a motion to dismiss Kiva Lodge's claims against Hanover on the ground that, under its performance bond, its claims were time-barred, falling outside of a two-year statute of limitations. In 2015, the circuit court heard arguments concerning Kiva Lodge's motion to compel arbitration, eventually granting the stay and ordering the parties to arbitration. The court also denied Hanover's motion to dismiss. Hudak, Colvin, and Hanover timely appealed the circuit court's order. After review, the Supreme Court found no reversible error in the trial court's order and affirmed. View "Hanover Insurance Co. v. Kiva Lodge Condominium Owners' Association, Inc." on Justia Law

by
In 2014, Lend Lease, the construction manager of the Chicago River Point Tower Project, hired Cives as a subcontractor. Cives hired Midwest Steel. Midwest had, years before, hired AES to supply Midwest with additional workers, who were co‐employed by Midwest and AES. Lend Lease entered into a “contractor-controlled insurance program” with Starr Liability with a $500,000 deductible. All subcontractors were to join in the policy. AES had, several years earlier, obtained workers’ compensation for its workers from TIC, so that injured AES‐Midwest workers could obtain workers’ compensation from either Starr (or Lend Lease under the deductible) or TIC. Four ironworkers, jointly employed by Midwest and AES and performing work for Midwest were injured on the job and sought workers’ compensation. The claims exceeded $500,000, so Lend Lease had to pay its full deductible. Starr paid the remaining claims. Lend Lease filed suit against TIC, AES’s insurer, and AES, seeking reimbursement of the $500,000. The district court dismissed. The Seventh Circuit affirmed. Lend Lease made a deal with Starr and is bound by it. The court rejected an argument that AES has been unjustly enriched; AES was not obligated to purchase an insurance policy that would cover Lend Lease's deductible. View "Lend Lease (US) Construction, Inc. v. Administrative Employer Services, Inc." on Justia Law

by
In this appeal, the issue presented for the Supreme Court's review was whether a contractor could maintain an action under the Contractor and Subcontractor Payment Act (CASPA) against a property owner’s agents. Beginning in 2005, Appellant Scungio Borst & Associates (SBA) entered into a series of written and oral construction contracts with Appellee 410 Shurs Lane Developers, LLC (410 SLD), which 410 SLD’s part-owner and president, Appellee Robert DeBolt, executed on 410 SLD’s behalf. Therein, SBA agreed to improve real property owned by 410 SLD in connection with the development of a condominium complex, and did so until November 2006, when SBA’s contracts were terminated with approximately $1.5 million in outstanding payments due. SBA requested payment, but 410 SLD, again through DeBolt, refused. Accordingly, SBA sued 410 SLD; its alleged successor corporation, Appellee Kenworth II, LLC; and DeBolt in his personal capacity. SBA asserted, among other claims, violations of CASPA. After careful review, the Supreme Court held that a contractor could not maintain an action under CASPA, and, accordingly, affirmed the order of the Superior Court. View "Scungio Borst & Assoc. v. 410 Shurs Lane Developers, LLC" on Justia Law