Justia Construction Law Opinion Summaries

Articles Posted in Contracts
by
Yates Construction, LLC, and D.W. Caldwell, Inc., entered into a construction subcontract for the roof installation on a residential dormitory at Auburn University in Auburn, Alabama. When Caldwell completed both the repairs and the roof installation, it had yet to receive total payment for the structural repairs. The companies disputed the scope and expense of these repairs and quickly negotiated to an impasse. Thereafter, Caldwell filed a claim against Yates for causing delay and increased costs by failing to pay for work performed, which was in breach of the agreements between the parties. The parties proceeded to arbitration. Although the arbitration record was neither recorded nor transcribed, the parties conceded that the arbitrator considered arguments, reviewed evidence, and heard witness testimony over the course of three days. He then reopened the proceedings for additional documentation, before issuing his thirteen-page award. Within two weeks of the arbitrator’s decision to deny Yates’s motion for reconsideration, Caldwell requested that the circuit court confirm the award under Mississippi Code Section 11-15-125. Yates moved the trial court to alter, amend, or vacate the award under Mississippi Code Section 11-15-25. With the understanding that Yates would provide oral argument on its motion at the award confirmation hearing, Caldwell filed a request to limit the presentation of proof before the circuit court. Ultimately, the trial court reviewed fourteen exhibits and the testimony of one witness in making its decision. Based on this evidence, the court issued its order modifying the arbitrator’s award. Finding that the arbitrator had duplicated the labor costs for shingle installation in its award–once under the original subcontract and once under the oral agreement to repair the structural damage (referred to as the Repair Agreement)–it amended the award, reducing the total by $104,507. After its review, the Mississippi Supreme Court determined: (1) the miscalculations alleged in this matter were not evident from the award itself, nor were they apparent from the agreed-upon record; and (2) the judge erred when he allowed the parties to present witness testimony regarding the extent of any alleged miscalculations, rather than relying on the award and the arbitration record as the relevant law suggested. Finding error, the Court therefore reversed the circuit court’s decision and remanded this case to the circuit court with directions to confirm the arbitration award. Furthermore, because the subcontract between the parties provided that each contractor would be responsible for his own fees and costs, the Court declined to assess costs to one party over the other, and instead, enforced their bargained-for agreement. View "D. W. Caldwell, Inc. v. W.G. Yates & Sons Construction Company" on Justia Law

by
Ewing Construction Co., Inc., appeals from a judgment denying its N.D.R.Civ.P. 60(b) motion to vacate a $951,191.62 default judgment entered in favor of Key Energy Services, LLC. Ewing began serving as the designer of and general contractor for Key's construction of the P3 Service Center project in Williston. Ewing voluntarily canceled its North Dakota contractor license in October 2014. In January 2015, Key sued Ewing and 22 others to invalidate construction liens filed against its property and claiming Ewing failed to pay numerous subcontractors for their work on the project in violation of its contractual obligations. After Ewing failed to answer the complaint, Key moved in June 2016 for a default judgment against Ewing. The district court granted the motion and entered default judgment against Ewing, awarding Key $951,191.62. The default judgment was entered on June 24, 2016, and Key served notice of entry of judgment on June 27, 2016. On May 12, 2017, after attempts were made to enforce the default judgment in Texas, Ewing brought a N.D.R.Civ.P. 60(b) motion to vacate the default judgment "because of insufficient service of process, and excusable neglect." Key responded by filing a corrected return of service which the district court accepted and considered. The corrected return of service was notarized and identified the documents served. On July 28, 2017, the court denied the N.D.R.Civ.P. 60(b) motion, concluding service of process was sufficient, the motion was untimely, and Ewing failed to establish excusable neglect. Because the district court did not err in ruling service of process was proper and did not abuse its discretion in denying the motion to vacate, the North Dakota Supreme Court affirmed. View "Key Energy Services, LLC v. Ewing Construction Co., Inc., et. al." on Justia Law

by
Scott and Anne Davison appealed the grant of summary judgment in favor of DeBest Plumbing (DeBest). In 2012, the Davisons hired Gould Custom Builders, Inc. (Gould) to perform an extensive remodel of their vacation home in Idaho. Gould hired DeBest as the plumbing subcontractor. A bathtub installed by DeBest developed a leak that caused significant damage before it was noticed and repaired. The Davisons sought damages based upon the contract between Gould and DeBest and for negligence. The district court granted DeBest’s motion for summary judgment on the contract claims because the Davisons were not in privity of contract with DeBest. Later, the district court granted summary judgment in favor of DeBest on the negligence claim, finding that the Davisons had failed to comply with the requirements of the Notice and Opportunity to Repair Act (NORA), Idaho Code sections 6-2501–2504. On appeal, the Davisons argued they satisfied the requirements of NORA because DeBest received actual notice of the claim and sent a representative to inspect the damage. Finding that the Davidsons satisfied the requirements of NORA when they gave DeBest actual notice, and DeBest had an opportunity to inspect the defect, the Idaho Supreme Court determined the district court erred in granting DeBest's motion for summary judgment on the Davidsons' negligence claim. The Supreme Court reversed as to negligence, but affirmed the district court in all other respects. View "Davison v. DeBest Plumbing" on Justia Law

by
The Supreme Court reversed the order of the circuit court dismissing Petitioners’ civil action as a sanction for alleged discovery violations, holding that the circuit court abused its discretion by imposing the sanction of dismissal.Petitioners bought this civil action against Respondent alleging unfair and deceptive acts, breach of express and implied warranties, breach of contract, and other causes of action. Respondent eventually filed a second motion to dismiss the civil action as a sanction for alleged discovery violations. The circuit court identified ten instances of alleged wrongful conduct by Petitioners and granted Respondent’s motion to dismiss. The Supreme Court reversed, holding that, even assuming that there was a discovery violation, the circuit court’s imposition of the extreme sanction of dismissal was an abuse of discretion. View "Smith v. Gebhardt" on Justia Law

by
In this billing dispute between a general contractor, Dudley Construction, Ltd., and a pipe supplier, ACT Pipe and Supply, Inc., the Supreme Court affirmed the judgment of the court of appeals in part and reversed it in part, holding (1) in defending a favorable judgment notwithstanding the jury’s verdict, ACT successfully raised a “cross-point” in the court of appeals that preserved an alternative argument proscribing the jury’s original verdict, even though ACT did not formally label its argument a “cross-point”; and (2) attorney’s fees are not recoverable for a claim brought under the Texas Construction Trust Fund Act. The Court remanded this case to the trial court for further proceedings. View "Dudley Construction, Ltd. v. ACT Pipe & Supply, Inc." on Justia Law

by
The terms of the insurance policy at issue in this coverage dispute required a written contract between the named insured and an additional insured if coverage was to be extended to an additional insured, and therefore, Liberty Insurance Underwriters was entitled to summary judgment.Gilbane Building Co. and TDX Construction Corporation (collectively, Gilbane JV) was the construction manager for a new forensic laboratory, and Samson Construction Co. was the general contractor. Samson obtained general liability insurance coverage from Liberty Insurance Underwriters. When disputes arose over the construction, Gilbane JV commerced this lawsuit arguing that it qualified for coverage under the Liberty policy as an additional insured. Gilbane JV had no written contract with Samson denominating it as an additional insured but argued that no such contract was necessary. Supreme Court denied Liberty’s motion for summary judgment, determining that Gilbane JV was an additional insured under the policy. The Appellate Division reversed and granted Liberty’s motion. The Court of Appeals affirmed based on the terms of the policy at issue. View "Gilbane Building Co./TDX Construction Corp. v St. Paul Fire & Marine Insurance Co." on Justia Law

by
The terms of the insurance policy at issue in this coverage dispute required a written contract between the named insured and an additional insured if coverage was to be extended to an additional insured, and therefore, Liberty Insurance Underwriters was entitled to summary judgment.Gilbane Building Co. and TDX Construction Corporation (collectively, Gilbane JV) was the construction manager for a new forensic laboratory, and Samson Construction Co. was the general contractor. Samson obtained general liability insurance coverage from Liberty Insurance Underwriters. When disputes arose over the construction, Gilbane JV commerced this lawsuit arguing that it qualified for coverage under the Liberty policy as an additional insured. Gilbane JV had no written contract with Samson denominating it as an additional insured but argued that no such contract was necessary. Supreme Court denied Liberty’s motion for summary judgment, determining that Gilbane JV was an additional insured under the policy. The Appellate Division reversed and granted Liberty’s motion. The Court of Appeals affirmed based on the terms of the policy at issue. View "Gilbane Building Co./TDX Construction Corp. v St. Paul Fire & Marine Insurance Co." on Justia Law

by
In this construction dispute, Plaintiff was not entitled to relief on its breach of contract claim or under a quantum meruit theory.Plaintiff and Defendant entered into a subcontract agreement that outlined services that Plaintiff was to perform as a subcontractor for the construction of the Bridge Street Bridge. Plaintiff later sued Defendant for breach of contract and quantum meruit in the alternative, asserting that the parties had entered into a separate agreement before the subcontract agreement and that, under that alleged agreement, Defendant was obligated to pay for additional work performed. The circuit court granted Defendant’s motion for judgment for the pleadings, concluding that the subcontract agreement was a complete integration of the dealings between the parties. The court of appeals determined that it was unclear whether the subcontract agreement was a full integration or a partial integration. Thus, the court declared that whether any additional work Plaintiff allegedly performed was covered by the subcontract agreement was an issue of fact for the jury. The Supreme Court reversed, holding (1) by its own terms, the subcontract agreement was a full integration of the parties’ contract for Plaintiff’s subcontracting work on the bridge; and (2) Plaintiff was not entitled to relief under a quantum meruit theory. View "Vanhook Enterprises, Inc. v. Kay & Kay Contracting, LLC" on Justia Law

by
In this construction dispute, Plaintiff was not entitled to relief on its breach of contract claim or under a quantum meruit theory.Plaintiff and Defendant entered into a subcontract agreement that outlined services that Plaintiff was to perform as a subcontractor for the construction of the Bridge Street Bridge. Plaintiff later sued Defendant for breach of contract and quantum meruit in the alternative, asserting that the parties had entered into a separate agreement before the subcontract agreement and that, under that alleged agreement, Defendant was obligated to pay for additional work performed. The circuit court granted Defendant’s motion for judgment for the pleadings, concluding that the subcontract agreement was a complete integration of the dealings between the parties. The court of appeals determined that it was unclear whether the subcontract agreement was a full integration or a partial integration. Thus, the court declared that whether any additional work Plaintiff allegedly performed was covered by the subcontract agreement was an issue of fact for the jury. The Supreme Court reversed, holding (1) by its own terms, the subcontract agreement was a full integration of the parties’ contract for Plaintiff’s subcontracting work on the bridge; and (2) Plaintiff was not entitled to relief under a quantum meruit theory. View "Vanhook Enterprises, Inc. v. Kay & Kay Contracting, LLC" on Justia Law

by
Meridian contracted to construct the Chula Vista Project flood control project, including construction of concrete channels, relocation of a sewer line, and dewatering and water diversion. After commencing work, Meridian encountered problems relating to “a layer of dripping saturated dark clay material under which a clean layer of sand is producing water” with “the potential for serious structural damage.” The government issued contract modifications, including an increase in funds for larger pipe, addition of a reinforced concrete access ramp, investigation of soil properties, remediation of saturated soils, and additional sheet piling. The government directed Meridian to suspend work following structural failures and terminated the project following a final inspection. Meridian sued for breach of contract, breach of the duty of good faith and fair dealing, and violation of the Contract Disputes Act, 41 U.S.C. 601−613. The government conceded liability for certain costs relating to suspension of work, channel fill, and interim protection. With respect to other claims, the Federal Circuit affirmed in part. Meridian’s interpretation of the contract was not reasonable; the existence of subsurface saturated soil conditions was “reasonably foreseeable.” The Trade Court did not impose an improper requirement for investigation of site conditions beyond what a reasonable contractor would undertake. The court remanded for consideration of whether the parties reached a meeting of the minds on flood event claims and held that the Trade Court erred dismissing Meridian’s unpaid contract quantities claim, in light of conflicting information. View "Meridian Engineering Co. v. United States" on Justia Law