Justia Construction Law Opinion Summaries

Articles Posted in Contracts
by
In March 2013, Woodsboro Farmers Cooperative contracted with E.F. Erwin, Inc. to construct two grain silos. Erwin subcontracted AJ Constructors, Inc. (AJC) for the assembly. AJC completed its work by July 2013, and Erwin finished the project in November 2013. However, Woodsboro noticed defects causing leaks and signed an addendum with Erwin for repairs. Erwin's attempts to fix the silos failed, leading Woodsboro to hire Pitcock Supply, Inc. for repairs. Pitcock found numerous faults attributed to AJC's poor workmanship, necessitating complete deconstruction and reconstruction of the silos, costing Woodsboro $805,642.74.Woodsboro sued Erwin in Texas state court for breach of contract, and the case went to arbitration in 2017. The arbitration panel found AJC's construction was negligent, resulting in defective silos, and awarded Woodsboro $988,073.25 in damages. The Texas state court confirmed the award in September 2022. In December 2018, TIG Insurance Company, Erwin's insurer, sought declaratory relief in the United States District Court for the Southern District of Texas, questioning its duty to defend and indemnify Erwin. The district court granted TIG's motion for summary judgment on the duty to defend, finding no "property damage" under the policy, and later ruled there was no duty to indemnify, as the damage was due to defective construction.The United States Court of Appeals for the Fifth Circuit reviewed the case. The court found that there were factual questions regarding whether the damage constituted "property damage" under the insurance policy, as the silos' metal parts were damaged by wind and weather due to AJC's poor workmanship. The court determined that the district court erred in granting summary judgment for TIG and concluded that additional factual development was needed. The Fifth Circuit reversed the district court's decision and remanded the case for further proceedings. View "TIG Insurance Company v. Woodsboro Farmers Coop" on Justia Law

by
Cheryl Lynch, the owner of a residential property in San Clemente, California, engaged a general contractor for home improvement and repairs. The contractor hired Peter & Associates, Engineers, Geologists, Surveyors, Inc. (the Peter firm) to perform a geotechnical inspection of a footing trench. The Peter firm conducted a visual inspection and used a steel probe but did not perform subsurface exploration or laboratory testing. The footing later collapsed, causing significant damage to Lynch's home.Lynch filed a lawsuit in February 2021 against multiple parties, including the Peter firm, for breach of contract, nuisance, and negligence. The Peter firm moved for summary judgment, arguing it owed no duty of care to Lynch due to the lack of a direct contract. The Superior Court of Orange County granted the motion, heavily relying on the precedent set by Weseloh Family Ltd. Partnership v. K.L. Wessel Construction Co., Inc., which found no duty of care in the absence of privity.The Court of Appeal of the State of California, Fourth Appellate District, Division Three, reviewed the case. The court found that the Peter firm failed to meet its burden in the summary judgment motion. The court held that the firm owed a duty of care to Lynch, applying the Biakanja factors, which consider the extent to which the transaction was intended to affect the plaintiff, the foreseeability of harm, and other factors. The court also found that the trial court erred in dismissing Lynch's nuisance claim and in sustaining the Peter firm's evidentiary objections without proper basis.The Court of Appeal reversed the summary judgment and remanded the case to the trial court with instructions to deny the Peter firm's motion in its entirety. View "Lynch v. Peter & Associates" on Justia Law

by
American Building Innovation LP (ABI) was hired by Balfour Beatty Construction, LLC (Balfour Beatty) as a subcontractor for a school construction project. ABI had a workers’ compensation insurance policy when it began work, but the policy was canceled due to ABI’s refusal to pay outstanding premiums from a previous policy. This cancellation led to the automatic suspension of ABI’s contractor’s license. Despite knowing it was unlicensed and uninsured, ABI continued working on the project.The Superior Court of Orange County found that ABI was not duly licensed at all times during the performance of its work, as required by California law. ABI’s license was suspended because it failed to maintain workers’ compensation insurance. ABI later settled its premium dispute and had the policy retroactively reinstated, but the court found this retroactive reinstatement meaningless because it occurred long after the statute of limitations for any workers’ compensation claims had expired. The court ruled that ABI could not maintain its action to recover compensation for its work due to its lack of proper licensure.The California Court of Appeal, Fourth Appellate District, Division Three, affirmed the lower court’s judgment. The court held that ABI was not entitled to retroactive reinstatement of its license because the failure to maintain workers’ compensation insurance was not due to circumstances beyond ABI’s control. ABI’s decision not to pay the premiums and its false representations to the Contractors’ State License Board were within its control. Consequently, ABI was barred from bringing or maintaining the action under section 7031 of the Business and Professions Code. The court also affirmed the award of attorney fees to Balfour Beatty under the subcontract’s prevailing party attorney fee provision. View "American Building Innovations v. Balfour Beatty Construction" on Justia Law

by
American Environmental, Inc. (plaintiff) challenged the Burlington School District (defendant) over a contract awarded for the demolition and remediation of Burlington High School, which was closed due to toxic substances. The District sent a Request for Qualifications to fifteen contractors, including the plaintiff and the winning bidder, EnviroVantage. The plaintiff argued that EnviroVantage did not meet the prequalification criteria and that the contract should have been awarded to them.The Superior Court, Chittenden Unit, Civil Division, denied the plaintiff's request for a preliminary injunction, citing potential financial harm to the District and public interest. The court later granted summary judgment to the District, finding the case moot because the project was substantially complete. The court applied factors from Citineighbors Coalition of Historic Carnegie Hill ex rel. Kazickas v. New York City Landmarks Preservation Commission, determining that no effective relief could be granted due to the project's advanced stage.The Vermont Supreme Court took judicial notice of the project's completion, including demolition and soil remediation, based on public records and visual evidence. The court dismissed the appeal as moot, stating that no effective relief could be provided under Rule 75, which does not allow for damages. The court also rejected the plaintiff's argument that the case met the exception for issues capable of repetition yet evading review, noting the plaintiff's delay in seeking expedited relief and the lack of demonstrated probability of encountering the same situation again. View "American Environmental, Inc. v. Burlington School District" on Justia Law

by
Covenant Construction Services, LLC was the prime contractor on a federal construction project for a U.S. Department of Veterans Affairs facility in Iowa City, Iowa. Covenant subcontracted with Calacci Construction Company, Inc. to supply carpentry labor and materials. Calacci had a collective bargaining agreement (CBA) with two regional unions, requiring it to pay fringe-benefit contributions to the Five Rivers Carpenters Health and Welfare Fund and Education Trust Fund (the Funds). Despite multiple demands, Calacci failed to remit the required contributions.The Funds filed a lawsuit under the Miller Act to collect the unpaid contributions, liquidated damages, interest, costs, and attorneys' fees from Covenant and its surety, North American Specialty Insurance Company. The United States District Court for the Southern District of Iowa granted summary judgment in favor of the Funds, concluding that the Funds had standing to sue and that the Miller Act notice was properly served and timely.The United States Court of Appeals for the Eighth Circuit reviewed the case de novo. The court affirmed the district court's decision, holding that the Funds sufficiently complied with the Miller Act's notice requirements by sending the notice to Covenant's attorney, who confirmed receipt. The court also held that the notice was timely as it was filed within 90 days of the last day of labor on the project. Additionally, the court upheld the award of liquidated damages and attorneys' fees, finding that the CBA obligated Calacci to pay these amounts and that Covenant, as the prime contractor, was liable for the amounts due under the payment bond.The Eighth Circuit concluded that the Funds were entitled to recover the unpaid contributions, liquidated damages, and attorneys' fees from Covenant and its surety, affirming the district court's judgment. View "Five Rivers Carpenters v. Covenant Construction Services" on Justia Law

by
A sub-subcontractor, Diamond Services Corporation, entered into a contract with Harbor Dredging, a subcontractor, to perform dredging work in the Houston Ship Channel. The prime contract for the project was awarded to RLB Contracting by the U.S. Army Corps of Engineers, and RLB obtained a surety bond from Travelers Casualty and Surety Company of America. During the project, unexpected site conditions, including the presence of tires, caused delays and increased costs. Diamond continued working based on an alleged agreement that it would be compensated through a measured-mile calculation in a request for equitable adjustment (REA) submitted by RLB to the Corps. However, RLB later settled the REA for $6,000,000 without directly involving Diamond in the negotiations and issued a joint check to Harbor and Diamond for $950,000.The United States District Court for the Southern District of Texas dismissed some of Diamond's claims, including those for unjust enrichment and express contractual claims against RLB, but allowed Diamond's quantum meruit claim to proceed. The court also denied Travelers' motion to dismiss Diamond's Miller Act claims but required Diamond to amend its complaint to include proper Miller Act notice, which Diamond failed to do timely. Subsequently, the district court granted summary judgment in favor of RLB and Harbor, dismissing Diamond's remaining claims and striking Diamond's untimely second amended complaint.The United States Court of Appeals for the Fifth Circuit reviewed the case. The court affirmed the district court's summary judgment against Diamond's quantum meruit claims, holding that the express sub-subcontract covered the damages Diamond sought and that Diamond failed to provide evidence of the reasonable value of the work performed. The court also affirmed the dismissal of Diamond's Miller Act claim, as the damages sought were not recoverable under the Act. The court dismissed Diamond's appeal regarding the tug-expenses claim due to untimeliness. View "Diamond Services v. RLB Contracting" on Justia Law

by
Keiland Construction, L.L.C. entered into a construction subcontract with Weeks Marine, Inc. for a project in Louisiana. Weeks terminated the contract for convenience, leading to a dispute over compensation. Keiland submitted pay applications and demobilization costs, which Weeks partially paid. The disagreement centered on whether the contract required lump-sum payments for work completed before termination or if it converted to a cost-plus basis upon termination.The United States District Court for the Western District of Louisiana held a bench trial and found the contract ambiguous. It construed the ambiguity against Keiland, the drafter, and ruled in favor of Weeks. The court awarded Keiland damages based on Weeks’s interpretation of the contract but denied Keiland’s claims for direct employee and demobilization costs. The court also awarded Weeks attorneys’ fees and costs, though less than requested, and denied Weeks’s motion for post-offer-of-judgment fees and costs.The United States Court of Appeals for the Fifth Circuit reviewed the case. It affirmed the district court’s findings, agreeing that the contract was ambiguous and that the ambiguity should be construed against Keiland. The appellate court upheld the district court’s rulings on damages, attorneys’ fees, and costs, including the denial of post-offer-of-judgment fees and costs. The court also affirmed the award of prejudgment interest to Keiland, finding no abuse of discretion.In summary, the Fifth Circuit affirmed the district court’s judgment in all respects, including the interpretation of the contract, the award of damages, attorneys’ fees, costs, and prejudgment interest. View "Keiland Construction v. Weeks Marine" on Justia Law

by
A commercial tenant and landlord entered into a contract for the construction and lease of a warehouse, with the landlord also acting as the general contractor. The contract included a waiver of subrogation, where both parties waived subrogation against each other for certain losses, including those caused by their subcontractors. After the warehouse sustained weather damage, the tenant’s insurer sought to recoup insurance payments by suing the subcontractors.The Circuit Court for Baltimore City granted summary judgment in favor of the subcontractors, concluding that they were intended beneficiaries of the waiver of subrogation in the contract between the tenant and landlord. The court did not consider any extrinsic evidence regarding the parties' intent. The Appellate Court of Maryland reversed this decision, finding that the waiver of subrogation in the contract did not unambiguously benefit the subcontractors and that the subcontractors were not intended third-party beneficiaries.The Supreme Court of Maryland reviewed the case and held that the waiver of subrogation in the contract between the tenant and landlord did not extend to the subcontractors. The court found that the language of the waiver was unambiguous and did not show an intent to benefit the subcontractors. However, the court found that the waiver of subrogation included in the subcontracts was ambiguous regarding whether it applied to the tenant’s insurer’s claims against the subcontractors. Therefore, the court held that extrinsic evidence was needed to determine the parties' intent regarding the scope of the subrogation waiver in the subcontracts.The Supreme Court of Maryland affirmed the Appellate Court's decision, reversing the Circuit Court's summary judgment in favor of the subcontractors, and remanded the case for further proceedings to consider extrinsic evidence. View "Lithko Contracting v. XL Insurance America, Inc." on Justia Law

by
Summit Construction filed a lawsuit against Jay Koontz and Jennie L. Kennette for breach of contract and unjust enrichment, alleging nonpayment for work performed on Mr. Koontz’s home based on an oral agreement. The work included an addition to the home and extensive renovations to the existing structure. The District Court rejected both claims, determining that there was no enforceable oral contract between the parties and that Summit did not sufficiently prove its damages for the unjust enrichment claim.The District Court found that the parties had not mutually agreed to sufficiently definite terms for an oral contract. The court noted that the project progressed without a clear understanding of the scope of work, how it would be paid for, and who would be responsible for payment. The court also found that Summit's invoices did not clearly define the terms of the contract. Furthermore, the court concluded that Summit had failed to prove the amount by which Mr. Koontz was unjustly enriched, i.e., its damages.Upon appeal, the Supreme Court of Wyoming affirmed the District Court's decision. The Supreme Court agreed that Summit had failed to show the existence of an enforceable oral contract with either Mr. Koontz or Ms. Kennette. The court also agreed with the lower court's finding that Summit had failed to establish its damages to a reasonable degree of certainty, which is necessary for an unjust enrichment claim. View "Summit Construction v. Koontz" on Justia Law

by
A general contractor, Graycor Construction Company Inc., was involved in a dispute with a subcontractor, Business Interiors Floor Covering Business Trust, over unpaid invoices for flooring work performed on a movie theater project. Business Interiors submitted three separate applications for periodic payments, which Graycor neither approved nor rejected within the time limit set by the Prompt Pay Act. As a result, the applications were deemed approved under the Act. Business Interiors sued Graycor for breach of contract and other claims in the Superior Court. The Superior Court granted Business Interiors's motion for summary judgment on its breach of contract claim and entered separate and final judgment. Graycor appealed.Graycor argued that the original contract was not a "contract for construction" within the meaning of the Act, and that it had a valid impossibility defense due to its failure to pay. The Supreme Judicial Court held that the Act defines its scope broadly, and the subcontract at issue was a "contract for construction" under the Act. The Court also held that common-law defenses are not precluded by the Act, but a contractor that does not approve or reject an application for payment in compliance with the Act must pay the amount due prior to, or contemporaneous with, the invocation of any common-law defenses in any subsequent proceeding regarding enforcement of the invoices. As Graycor sought to exercise its defenses without ever paying the invoices, it could not pursue the defenses. The Court also vacated and remanded the rule 54 (b) certification to the motion judge for reconsideration. View "Business Interiors Floor Covering Business Trust v. Graycor Construction Company Inc." on Justia Law