Justia Construction Law Opinion Summaries

Articles Posted in Contracts
by
A black-owned construction company was not invited to bid as general contractor on a major Boston public housing redevelopment project after participating in pre-construction work. Years earlier, the developer had called the company’s president to discuss possible involvement, but the parties disputed what promises, if any, were made during that conversation. The construction company performed pre-construction work and was later selected as general contractor for the first phase (Camden), but after performance and communication issues arose during that project, the developer chose a different, white-owned company for the second phase (Lenox). The construction company did not protest at the time but later sued, alleging breach of contract, quasi-contract, violation of Massachusetts consumer protection law, and racial discrimination under 42 U.S.C. § 1981.The matter was first brought in Massachusetts state court, then removed to the United States District Court for the District of Massachusetts based on federal question jurisdiction. After discovery, the developer moved for summary judgment. The District Court granted summary judgment for the developer, finding no enforceable contract or promise had been made regarding the Lenox phase, that the quasi-contract and Chapter 93A claims failed as derivative, and that there was insufficient evidence of racial discrimination.The United States Court of Appeals for the First Circuit affirmed the District Court’s decision. The First Circuit held that the summary judgment record did not contain evidence from which a reasonable jury could find an enforceable implied-in-fact contract or a promise sufficient for promissory estoppel. It further held that the plaintiff failed to create a triable issue of fact regarding pretext or discriminatory intent under § 1981, given the legitimate business reasons cited for the company’s exclusion. Thus, summary judgment on all claims was proper. View "John B. Cruz Construction Co. v. Beacon Communities Corp." on Justia Law

by
A steel subcontractor was hired to perform work for a university construction project and entered into a subcontract with the general contractor. The general contractor began defaulting on payments, prompting the subcontractor to notify the surety insurance company, which had issued a payment bond guaranteeing payment for labor, materials, and equipment. The surety made partial payment but disputed the remaining amount. The subcontractor then demanded arbitration against the contractor, with the surety notified and invited to participate. The contractor filed for bankruptcy and did not defend in arbitration, nor did the surety participate. The arbitrator awarded the subcontractor damages, including attorneys’ fees and interest, and the award was confirmed in court. The subcontractor sought to enforce the arbitration award against the surety, including attorneys’ fees and prejudgment interest, and also brought a bad faith claim under Pennsylvania’s insurance statute.The Centre County Court of Common Pleas initially excluded evidence of the arbitration award against the surety at trial and ruled the surety was not liable for attorneys’ fees or bad faith damages. A jury found for the subcontractor on the underlying debt, and the court awarded prejudgment interest at the statutory rate. Both parties appealed. The Superior Court held the arbitration award was binding and conclusive against the surety, who had notice and opportunity to participate, and affirmed liability for attorneys’ fees related to pursuing the contractor in arbitration. The court rejected the bad faith claim, holding the statute did not apply to surety bonds, and confirmed the statutory interest rate.On appeal, the Supreme Court of Pennsylvania affirmed in all respects. It held that Pennsylvania’s insurance bad faith statute does not apply to surety bonds, based on statutory language. The court also held that the surety is bound by the arbitration award against its principal, and is liable for attorneys’ fees incurred in arbitration and prejudgment interest at the statutory rate. View "Eastern Steel v. Int Fidelity Ins. Co." on Justia Law

by
A Wyoming firearms manufacturer sought to expand its operations by constructing a new facility. The company, unable to directly access specific state economic development funds, partnered with a city and a local non-profit to obtain funding, resulting in a written agreement outlining each party’s roles. The non-profit was charged with managing the project, including hiring architects and contractors. During and after construction, the manufacturer identified substantial design and construction defects, including climate control problems, leaks, and structural issues. The manufacturer sued the non-profit for breach of contract and also sued the architect and contractor, asserting it was a third-party beneficiary of their contracts with the non-profit.In the District Court of Park County, the court dismissed the manufacturer’s claims against the architect and contractor, finding it was not an intended third-party beneficiary under their contracts, and granted summary judgment to the non-profit on all but one claim, determining that the non-profit’s contractual obligations were limited to financial administration of the project. The remaining claim was later dismissed by stipulation.The Supreme Court of Wyoming reviewed the case de novo. The court held that the district court erred in dismissing the manufacturer’s claims against the architect and contractor because, accepting the complaint’s factual allegations as true and considering the relevant contracts, the manufacturer had sufficiently alleged facts that could support third-party beneficiary status and breach of contract. The court also found the district court erred in granting summary judgment to the non-profit, concluding that the contract’s language and context imposed broader duties on the non-profit, including project administration and construction oversight, not merely financial management. The Supreme Court of Wyoming reversed the lower court’s orders of dismissal and summary judgment, allowing the manufacturer’s claims to proceed. View "Gunwerks, LLC v. Forward Cody Wyoming, Inc." on Justia Law

by
The dispute arose from a failed attempt to construct an osteopathic medical school in Gaylord, Minnesota. Philip Keithahn formed Minnesota Medical University, LLC (MMU) and retained Heritage Construction Companies, LLC as the general contractor. MMU planned to finance the project through bond proceeds, with a portion immediately available and the remainder contingent on achieving pre-accreditation. Representatives from Heritage sought confirmation of available funds prior to construction, and Keithahn assured them that the project would be funded and that millions would be available after closing. However, after initial payments, MMU ran out of funds when pre-accreditation was denied, leading Heritage to halt construction and terminate its contract.The United States District Court for the District of Minnesota oversaw the case after Heritage and its affiliates faced indemnification claims and filed a third-party complaint against Keithahn and MMU. The defendants’ motion for summary judgment was denied, and the case proceeded to trial on claims including breach of contract, indemnification, negligent misrepresentation, fraudulent misrepresentation, and fraud by omission. MMU admitted liability for breach of contract and damages. The jury found the defendants liable on all claims except fraudulent misrepresentation. Post-verdict, the district court denied defendants’ motions for judgment as a matter of law or for a new trial, addressing issues of jury instructions, violations of in limine orders, improper statements, and impeachment.The United States Court of Appeals for the Eighth Circuit reviewed the appeal. It held that Keithahn’s representations regarding available financing were actionable as negligent misrepresentations, as they concerned present facts susceptible of knowledge rather than mere future assurances. The court found no error in the jury instructions, no prejudicial violation of evidentiary rulings, and no cumulative error warranting a new trial. The Eighth Circuit affirmed the district court’s judgment. View "Heritage Const. Companies, LLC v. Keithahn" on Justia Law

by
Gunwerks sought to expand its business by constructing a new manufacturing facility in Cody, Wyoming, a project involving public funds and coordinated through Forward Cody Wyoming, Inc. Forward Cody retained Plan One Architects and Sletten Construction of Wyoming, Inc. as the project's designer and general contractor, respectively. Sletten hired various subcontractors, including Big Horn Glass, Inc. (BHG), to perform specific tasks. After completion, Gunwerks alleged numerous construction defects in the facility, including issues with concrete, finishes, HVAC, siding, drainage, ceiling heights, door and window flashings, and the shooting tunnel. Gunwerks sued Forward Cody, Plan One, and Sletten for breach of contract and breach of the covenant of good faith and fair dealing.Sletten responded to Gunwerks’s lawsuit by filing a third-party complaint against its subcontractors, including BHG. Sletten claimed that, should it be found liable to Gunwerks, subcontractors responsible for any deficient work should indemnify it for those damages. Sletten did not specifically admit or allege deficiencies in BHG’s work but sought to preserve its right to recovery if any subcontractor was found at fault. Approximately ten months after Sletten’s third-party complaint, BHG moved for summary judgment in the District Court of Park County, arguing that Sletten had not presented evidence showing BHG caused any of the alleged damages. The district court granted summary judgment for BHG, finding that Sletten had not countered BHG’s prima facie showing with disputed facts, relying instead on speculation.On appeal, the Supreme Court of Wyoming reviewed the district court’s summary judgment ruling de novo, applying the same standard as the lower court and viewing the record most favorably to Sletten. The Supreme Court affirmed the district court’s decision, holding that Sletten failed to present admissible, competent evidence creating a genuine issue of material fact regarding BHG’s liability for any alleged defects. The court found Sletten’s evidence speculative and conclusory, insufficient to defeat summary judgment. The disposition was affirmed. View "Sletten Construction of Wyoming, Inc. v. Big Horn Glass, Inc." on Justia Law

by
A Nebraska limited liability company owned by Michael Perkins hired RMR Building Group, LLC, managed and solely owned by Robert M. Ryan II, as a general contractor to redevelop a shopping center. Their contract used a cost-plus billing arrangement, where Perkins paid RMR in advance for specific construction costs, including a substantial sum for HVAC equipment and RMR’s fee. RMR deposited the funds into its general operating account but did not pay for the HVAC equipment; instead, it used the money to cover other business obligations. Perkins terminated the contract after RMR failed to provide proof of payment for the equipment and then sued RMR and Ryan for breach of contract, unjust enrichment, conversion, and fraudulent misrepresentation, also seeking to pierce the corporate veil and hold Ryan personally liable.The District Court for Douglas County found that RMR breached the contract and was liable under theories of money had and received and unjust enrichment, but not for conversion or fraudulent misrepresentation. The court declined to disregard RMR’s corporate entity, finding no sufficient evidence that Ryan diverted funds for personal use or that RMR was a mere facade for Ryan’s dealings. Perkins appealed these findings.The Nebraska Court of Appeals reversed in part, concluding that the corporate veil should be pierced and Ryan held jointly and severally liable for the misappropriated funds, relying on factors from United States Nat. Bank of Omaha v. Rupe. On further review, the Nebraska Supreme Court reversed the Court of Appeals, holding that the evidence did not establish by a preponderance that RMR’s entity should be disregarded, nor did it support fraud or conversion claims against Ryan. The Supreme Court remanded with direction to affirm the district court’s judgment. View "Perkins v. RMR Building Group" on Justia Law

by
Joel Ward performed construction work for Bishop Construction, LLC and its sole member, Ren Bishop, in Idaho, Montana, and Wyoming, with an agreed hourly wage and travel compensation. Despite keeping detailed records of his hours, Ward was not paid for work completed between 2017 and 2019, leading him to pursue payment through legal action. The dispute centered on whether Ward should be classified as an employee or an independent contractor and whether he was required to register as a contractor under Idaho law.The case was first heard in the District Court of the Seventh Judicial District of Idaho, Bonneville County. After a bench trial, and based on the parties’ stipulation that Ward was an independent contractor, the court dismissed his wage claims, leaving only breach of contract and unjust enrichment claims. The district court initially awarded Ward full damages for breach of contract. However, after Bishop raised the issue of contractor registration under the Idaho Contractor Registration Act (ICRA) in post-trial motions, the court amended its findings, limited contract damages to out-of-state work, awarded unjust enrichment damages for Idaho work, and granted costs and attorney fees.On appeal, the Supreme Court of the State of Idaho reviewed whether Ward was required to register as a contractor under ICRA and whether the contract was illegal. The Court held that Bishop failed to meet his burden to prove Ward was required to register under ICRA, as the record did not establish Ward’s status as a contractor for those purposes. The Supreme Court vacated the district court’s amended judgment and remanded with instructions to reinstate its original findings and amended judgment, including the previously awarded attorney fees and costs. The Court also awarded Ward attorney fees and costs on appeal as the prevailing party. View "Ward v. Bishop Construction" on Justia Law

by
A carpenter employed by a subcontractor was injured after falling from a ladder owned by another subcontractor, DAL Electrical Corporation, while working on a renovation project at an office building. The injured worker was using his own employer’s equipment in the morning but, after lunch, returned to the worksite without his equipment and used an unattended DAL ladder, which was defective and marked with blue tape. He was injured when the ladder wobbled and he fell, impaling himself on a tool in his belt. The worker brought claims under New York Labor Law and for common-law negligence against the project’s general contractor, premises owner, and DAL, asserting the defective ladder caused his injuries. The general contractor and owner sought indemnification from DAL under their subcontract.The Supreme Court of Bronx County granted the worker’s motion for partial summary judgment on one Labor Law claim and denied DAL’s motion to dismiss other claims and cross-claims by the general contractor and owner. The court also granted the general contractor and owner summary judgment on their contractual indemnification claim against DAL. The Appellate Division, First Department, modified this order by denying summary judgment on contractual indemnification and granting summary judgment for DAL on all claims and cross-claims against it. The general contractor and owner appealed to the New York Court of Appeals.The New York Court of Appeals affirmed the Appellate Division’s decision. The Court held that none of the indemnification provisions in the subcontract required DAL to indemnify the general contractor or owner for the worker’s injuries because the injuries did not arise from DAL’s performance of its contractually defined work. The Court also found that DAL did not owe a duty of care in tort to the injured worker, as the facts did not fit within any recognized exception to the general rule against extending contractual duties to non-contracting third parties. The certified question was answered in the affirmative. View "Dibrino v Rockefeller Ctr. N., Inc." on Justia Law

by
Russ and Debi Ropken hired a construction company to build a custom home based on an oral agreement. The contractor began work and sent invoices for services and materials, which the Ropkens paid until May 2022, after which they stopped making payments. In July 2022, the Ropkens removed the contractor from the site. The contractor then sent a demand letter for three unpaid invoices totaling $276,169, but the Ropkens refused to pay. The contractor sued to recover the unpaid amount.In the District Court of Park County, the Ropkens admitted owing at least $176,870.21. At the conclusion of a jury trial, the jury found there was a valid contract, the Ropkens had breached it, and awarded the contractor $258,587.70 in damages. The district court entered judgment for that amount and permitted the contractor to request prejudgment interest. The contractor timely filed for prejudgment interest, and the Ropkens objected. The district court found for the contractor, awarding $33,473.25 in prejudgment interest at a statutory rate, and calculated interest from the date of the demand letter. The Ropkens paid the judgment but appealed the prejudgment interest award.The Supreme Court of Wyoming reviewed whether the district court erred in awarding prejudgment interest and whether due process was violated by granting interest without an evidentiary hearing. The court held that a district court may award prejudgment interest even when it is not the trier of fact, as prejudgment interest is a matter of law and not fact. The court found the claim was liquidated and the Ropkens had notice. The court also held that the Ropkens received adequate notice and opportunity to be heard, satisfying due process. The Supreme Court of Wyoming affirmed the award of prejudgment interest. View "Ropken v. Yj Construction, Inc." on Justia Law

by
The case centers on a bakery and deli operator, Bagelmania Holdings, LLC, which leased property from Somerset Property, LLC. Together, they renovated the building for Bagelmania’s restaurant, hiring RDH Interests, Inc. as architect, JEM Associates West, Inc. as contractor, and Turpin & Rattan Engineering, Inc. for HVAC mechanical engineering. Following the renovation, Bagelmania and Somerset alleged construction defects and sued these entities for breach of contract, breach of the implied covenant of good faith and fair dealing, and negligence, with both plaintiffs represented by the same attorney.Prior attempts to initiate litigation were dismissed for failing to comply with Nevada’s NRS 11.258 requirements, which mandate an attorney affidavit of merit and supporting expert reports in nonresidential construction defect cases. The plaintiffs then filed a joint complaint supported by one affidavit and a set of expert reports. The defendants argued that each plaintiff was required to file separate affidavits and expert reports, and the Eighth Judicial District Court, Clark County, agreed, dismissing the case with prejudice for failure to comply with NRS 11.258, also awarding attorney fees, costs, and interest to the defendants.On appeal, the Supreme Court of the State of Nevada considered whether a single affidavit and set of expert reports sufficed under NRS 11.258 when coplaintiffs, represented by the same attorney, jointly brought identical claims arising from the same alleged defects. The Supreme Court held that, under such circumstances, separate affidavits and expert reports are not required. The Court found that the plaintiffs complied with the statute’s plain language and purpose and that the affidavit and reports met the statutory requirements. The Supreme Court reversed the district court’s dismissal, vacated the post-judgment award of fees, costs, and interest, and remanded for further proceedings. View "Bagelmania Holdings, LLC v. RDH Interests, Inc." on Justia Law