Justia Construction Law Opinion Summaries
Articles Posted in Construction Law
Lamar Contractors, Inc. v. Kacco, Inc.
Lamar Contractors, Inc. was general contractor on a construction project, and entered into a subcontract with Kacco, Inc. to provide metal framing and drywall work on the project. The subcontract included a “pay-if-paid” payment provision, which afforded Lamar ten days to remit payment to its subcontractors after receipt of payment from the owner. Kacco began work on the project but experienced recurring problems with providing manpower and paying for supplies. Kacco submitted an invoice for work that reflected that forty-five percent of the work had been performed. Lamar paid the invoice prior to receiving payment from the owner. Lamar sent Kacco an email noting its concerns with whether Kacco would be able to perform under the subcontract. Kacco notified Lamar that Kacco was waiting on another payment so that it could order and pay for supplies to finish the project. Lamar had received payment from the owner on January 26; however, pursuant to the subcontract, Lamar was not required to make payment to Kacco until February 9, ten business days later. Lamar officially terminated Kacco’s subcontract in a letter dated February 5. After termination of the subcontract with Kacco, Lamar hired another contractor to complete the work. Lamar then sued Kacco for breach of the subcontract. Kacco countersued Lamar for allegedly failing to pay for work performed under the contract, and that failure to pay caused it to breach. After a bench trial, the district court entered judgment on the main demand for Lamar for $24,116.67 with interest, $7,681.75 for attorney’s fees, and $3,105.81 in costs. Additionally, the district court entered a judgment in the amount of $60,020.00 plus interest in favor of Kacco on its countersuit. Lamar appealed but the court of appeal affirmed. Under the circumstances of this case, it was clear to the Supreme Court that Lamar did not violate any obligation owed under the contract to make payment to Kacco and could not have negligently contributed to Lamar’s breach of its obligations under the contract. Accordingly, the district court erred in reducing Lamar’s award of damages. The case was remanded for further proceedings. View "Lamar Contractors, Inc. v. Kacco, Inc." on Justia Law
Pierce Foundations, Inc. v. JaRoy Construction, Inc.
This matter stemmed from a public works project for the construction of a gymnasium in Terrytown. JaRoy Construction Inc. served as the general contractor, and pursuant to statute, furnished a surety bond to Jefferson Parish. Ohio Casualty Insurance Company was the surety. JaRoy entered into a written subcontract with Pierce Foundations, Inc. to provide and install pilings for the project. Once finished, Pierce alleged JaRoy failed to pay certain funds due under the subcontract. Pierce sued both JaRoy and Ohio Casualty Insurance, alleging they were jointly and severally liable to Pierce. JaRoy filed for bankruptcy, leaving only Ohio Casualty Insurance as party to the suit. When the project was substantially completed, the Jefferson Parish government filed a notice of acceptance of work with the Jefferson Parish mortgage records office. This occurred over a year after Pierce amended its lawsuit to add Ohio Casualty as a defendant. Pierce never filed a sworn statement of claim in the mortgage records. Ohio Casualty filed a motion for summary judgment, contending that Pierce was required to comply with statutory notice and recordation, and because it failed to do so within 45 days of Jefferson Parish’s acceptance of the project, Pierce could not recover from Ohio Casualty. Pierce argued that the statute did not affect its right to proceed in contract. After a bench trial, the trial court rendered judgment in favor of Pierce for sums owed under the contract plus judicial interest from the date of the original judgment. Ohio Casualty appealed, arguing that the trial court erred in not dismissing Pierce's claims. The court of appeal reversed and ruled in Ohio Casualty's favor. The Supreme Court, however, disagreed and affirmed the trial court judgment. View "Pierce Foundations, Inc. v. JaRoy Construction, Inc." on Justia Law
Hearn Pac. Corp. v. Second Generation Roofing, Inc.
In 2007, the Sonoma County project’s owner sued Hearn, the general contractor, Second Generation, the roofer, and other subcontractors for design and construction defects. Hearn cross-complained against Second Generation and others. In 2009, Hearn assigned its interests under its subcontracts to two insurers, North American and RSUI. Hearn then settled with the owner and all but two subcontractors, one of which was Second Generation. Hearn filed an amended cross-complaint, purportedly in the name of the insurers, against those subcontractors, adding breach of a contractual obligation to obtain insurance and seeking equitable contribution for Hearn’s defense costs premised on a breach of that duty. In 2013, the court dismissed the cross-complaint against Second Generation on procedural grounds, awarded $30,256.79 in costs and granted prevailing party attorney fees of $179,119. Second Generation moved to amend the orders to name North American as a judgment debtor owing the amounts awarded against Hearn. The trial court denied the motion, stating: Hearn remains the only proper party and that the subcontractor’s exclusive remedy was to pursue a separate action against Hearn’s insurers. The court of appeal reversed, finding that, after the assignment, Hearn was “out of this case.” View "Hearn Pac. Corp. v. Second Generation Roofing, Inc." on Justia Law
Travelers Prop. Cas. Co. v. Stresscon Co.
Stresscon Corporation, a subcontracting concrete company, filed suit against Travelers Property Casualty Company of America, alleging, among other things, that Travelers acted in bad faith, unreasonably delaying or denying its claim for covered insurance benefits; and Stresscon sought awards of two times the covered benefits along with fees and costs, as prescribed by statute. Stresscon’s claims for relief arose from a 2007 serious construction accident which was caused by a crane operator employed by a company that was itself a subcontractor of Stresscon. Stresscon’s general contractor, Mortenson, sought damages from Stresscon, asserting Stresson’s contractual liability for the resulting construction delays, and Stresscon in turn sought indemnification from Travelers. Travelers petitioned for review of the court of appeals’ judgment affirming the district court’s denial of its motion for directed verdict in a lawsuit brought by its insured, Stresscon. Much as the district court had done, the appellate court rejected Travelers’ contention that the no-voluntary-payments clause of their insurance contract relieved it of any obligation to indemnify Stresscon for payments Stresscon had made without its consent. Instead, the court of appeals found that the Colorado Supreme Court's opinion in "Friedland v. Travelers Indemnity Co.," (105 P.3d 639 (2005)) had effectively overruled the Court's prior “no voluntary payments” jurisprudence to the contrary and given Stresscon a similar opportunity. The Supreme Court reversed, finding that its adoption of a notice-prejudice rule in "Friedland" did not overrule any existing “no voluntary payments” jurisprudence. The Court declined to extend a notice-prejudice reasoning to Stresscon’s voluntary payments, made in the face of the no-voluntary-payments clause of its insurance contract with Travelers. View "Travelers Prop. Cas. Co. v. Stresscon Co." on Justia Law
Baker Concrete Constr., Inc. v. Reinforced Concrete Contractors Ass’n
Baker, an Ohio concrete construction business, subcontracts its work to smaller firms. In 2000, Baker signed a multi-employer collective bargaining agreement (CBA) between the Reinforced Concrete Contractors Association and the Union, covering current employees and employees not yet hired. A prehire CBA is allowed only in the construction industry, 29 U.S.C. 158(f). The CBA renewed automatically. On January 25, 2013, Baker sent the Union a letter, asserting: “Baker’s notice of its intent to terminate the Agreement, including any subsequent successor agreements.” The Union responded: "notice of withdrawal should be made not more than 60 days prior to the termination of the Agreement. The Agreement is in effect … until May 31, 2015, therefore your request was untimely." Baker reiterated that none of its employees perform work covered by the Agreement and that none had performed bargaining unit work covered by the Agreement for at least seven years. The Union filed a grievance. Baker stated that it did not recognize the arbitrator’s authority, but would appear to preserve its position. The arbitrator found Baker in violation of the CBA. The district court vacated the award. The Sixth Circuit affirmed, adopting the single-employee-unit rule; an employer may repudiate statutory and contractual obligations when the employer does not employ anyone within the relevant bargaining unit. View "Baker Concrete Constr., Inc. v. Reinforced Concrete Contractors Ass'n" on Justia Law
J.D. Donovan, Inc. v. Minn. Dep’t of Transp.
At issue in this case was whether truck drivers hauling asphalt cement from a commercial oil refinery to a contractor’s facility are performing “work under a contract” under Minn. Stat. 177.44(1) and, therefore, must be paid prevailing wages. The Minnesota Department of Transportation (MDOT) determined that the construction companies that were awarded contracts to work on state highway projects violated the project contracts by failing to ensure that drivers that assisted in the acquisition and transport of asphalt cement for the projects were paid prevailing wages. Appellants argued that the hauling activities of these drivers did not constitute “work under a contract” under Minn. Stat. 177.44(1) and, alternatively, that the hauling activities were exempt from the prevailing wage requirements under the “commercial establishment exception” in the Prevailing Wage Act. The district courts granted summary judgment to MDOT. The court of appeals affirmed. The Supreme Court reversed, holding that hauling activities must be to, from, or on the site of a public works project to qualify as “work under a contract,” and therefore, the hauling activities in this case did not constitute “work under the contract” subject to the prevailing wage requirements. View "J.D. Donovan, Inc. v. Minn. Dep’t of Transp." on Justia Law
Employers Mut. Cas. Co. v. Slack
Jerry and Karen Slack hired Jeffrey Fisher and his construction company, Fisher Builders, to build a remodeled home. During the project, the deck collapsed, and the Slacks’ construction permit was revoked. The Slacks filed a negligence action against Fisher and his company. Fisher had a commercial general liability insurance policy with Employers Mutual Casualty Company (EMC). EMC filed a declaratory action alleging that there was no coverage and that it had no duty to defend or indemnify any party in the negligence action. Fisher and Fisher Builders ultimately settled with the Slacks and assigned their rights under the EMC insurance policy to the Slacks. The district court granted summary judgment in favor of EMC, ruling that Fisher’s conduct was clearly intentional and did not fit within the meaning of “occurrence” under the policy, regardless of whether Fisher intended the consequences. The Supreme Court reversed, holding that the district court (1) erred by concluding that, in the context of general liability insurance, the term “occurrence,” defined by the policy as “an accident,” categorically precludes coverage for any intentional conduct on the part of the insured with unintended results; and (2) erred when it granted summary judgment in favor of EMC, as issues of material fact precluded summary judgment. Remanded. View "Employers Mut. Cas. Co. v. Slack" on Justia Law
Stolz v. J & B Steel Erectors, Inc.
Daniel Stolz worked for a subcontractor on a construction project when he was injured in an accident on the job site. Prior to the accident, Messer had obtained authority from the Ohio Bureau of Workers’ Compensation to act as the self-insuring employer on the project, which gave Messer responsibility for providing workers’ compensation coverage for its own employees as well as the employees of enrolled subcontractors on the project. Stolz brought negligence claims against Messer Construction, the general contractor, and several subcontractors. A federal district court granted summary judgment to Messer as the self-insuring employer but denied summary judgment to the subcontractors, concluding that an enrolled subcontractor on a self-insured construction project is immune from claims made by its own employees but not from those made by employees of other enrolled subcontractors. The federal court then certified a question of state law to the Supreme Court. The Supreme Court answered that subcontractors enrolled in a self-insured construction project plan are immune from tort claims for workplace injuries from employees of other enrolled subcontractors on the same project. View "Stolz v. J & B Steel Erectors, Inc." on Justia Law
City of Tupelo v. McMillin
In 2006, Dr. Terry McMillin and his wife Leslie purchased a new home in Tupelo. Unhappy with contractor Jamie Ewing’s failure to respond to their repair requests, plus their discovery of a document (a blue card, noting a failed home inspection) listing the name of a different contractor as the contractor responsible for their home’s construction, the McMillins began the process of unraveling just who was responsible for building their new home. Ultimately, this case stemmed from an error by the City of Tupelo’s Permit Manager Marilyn Vail in handling the withdrawal of one licensed contractor and mistakenly substituting the name of another licensed contractor, when in actuality, a licensed contractor was not working on the home. The circuit court held a bench trial and awarded $9,319.23 in damages to repair the home and $105,894.39 in legal fees related to another case involving the construction but denied the McMillins’ request for attorneys’ fees in this case. The City appealed, and the McMillins cross-appealed. After review, the Supreme Court concluded that the circuit court erred in finding that the City was not immune from liability. The Court therefore reversed the circuit court’s judgment and render judgment in favor of the City. View "City of Tupelo v. McMillin" on Justia Law
Hammerhead Contracting & Dev. v. Ladd
Dale Ladd hired Hammerhead Contracting & Development, LLC to build a house. After a dispute arose regarding the amount owed for the construction of Ladd’s home, Brandon Holmes filed a Laborer’s, Mechanic’s, or Materialman’s Lien on behalf of the LLC for the amount of $101,676, the additional amount Hammerhead asserted that Ladd owed. Ladd filed suit against Holmes to remove the lien. Hammerhead then filed an amended complaint against Ladd seeking judgment for the $101,676. The cases were consolidated. The circuit court (1) granted Ladd’s motion to dismiss Hammerhead’s complaint because of its failure to give the notice required by Ark. Code Ann. 18-44-115; (2) granted summary judgment in favor of Ladd on Ladd’s complaint and ordered the lien canceled; and (3) found that Ark. Code Ann. 18-44-115(a)(4), which bars suit by a contractor who fails to provide statutory notice, is constitutional. The Supreme Court reversed, holding that the circuit court erred in finding that the direct-sales exception in Ark. Code Ann. 18-44-115(a)(8) to the residential preconstruction-notice requirement can never apply to a contractor. View "Hammerhead Contracting & Dev. v. Ladd" on Justia Law
Posted in:
Arkansas Supreme Court, Construction Law