Justia Construction Law Opinion Summaries

Articles Posted in Construction Law
by
RGW entered into a contract with Watson for the delivery of 146 sealed expansion joints for use on the Caltrans project for the construction of Highway 99. Watson filed a breach of contract action, contending it was entitled to an adjustment of the price on RGW’s original purchase order because the items ordered were changed. The trial court concluded that RGW’s purchase order was ambiguous and allowed the jury to decide what the contract meant and what price was appropriate. The jury decided in favor of Watson, finding the amount of the subject agreement was $605,990. The jury awarded Watson damages of $383,032. The court concluded that the trial court correctly (1) determined that RGW’s purchase order was ambiguous and (2) allowed the jury to evaluate the conflicting parol evidence before deciding the meaning of the contract. The court also concluded that the price adjustment owed to Watson for the change in the order was sufficiently certain to meet the statutory requirements for an award of prejudgment interest. Accordingly, the court affirmed the judgment, except for its failure to award prejudgment interest to Watson. View "Watson Bowman Acme Corp. v. RGW Construction" on Justia Law

by
This dispute arose from the construction of Cypress Point, a luxury condominium complex in Hoboken. Co-defendants Adria Towers, LLC, Metro Homes, LLC, and Commerce Construction Management, LLC (collectively, the developer) served as the project's developer and general contractor, and subcontractors carried out most of the work. During construction, the developer obtained four CGL policies from Evanston Insurance Company, covering a four-year period, and three from Crum & Forster Specialty Insurance Company, covering a subsequent three-year period (collectively, the policies). In this appeal, issue before the Supreme Court was whether rain water damage caused by a subcontractor's faulty workmanship constituted property damage and an occurrence under the developer's commercial general liability (CGL) insurance policy. In a published decision, the Appellate Division reversed, holding that, under the plain language of the CGL policies, the unintended and unexpected consequential damages caused by the subcontractors faulty workmanship constituted property damage and an occurrence. The Supreme Court agreed and affirmed, finding that the consequential damages caused by the subcontractors faulty workmanship constituted property damage, and the event resulting in that damage water from rain flowing into the interior of the property due to the subcontractors faulty workmanship was an occurrence under the plain language of the CGL policies at issue here. View "CypressPoint Condominium Association, Inc. v. Adria Towers, L.L.C., et al." on Justia Law

by
Meagher & Geer, PLLP (MG) represented Ryan Contracting Company (Ryan) in an action to foreclose on several mechanic’s liens. Later, represented by O’Neill & Murphy, LLP (O’Neill), Ryan brought suit against MG for legal malpractice arising out of MG’s allegedly defective filing and foreclosure of Ryan’s mechanic’s liens. The district court granted MG’s motion to dismiss on the ground that O’Neill failed to timely file expert witness affidavits. Ryan then brought suit against O’Neill for legal malpractice arising out of O’Neill’s representation of Ryan in the MG lawsuit. The district court granted summary judgment for O’Neill, concluding that the mechanic’s liens were not perfected, not because of MG’s conduct, but because of Ryan’s error in not filing the pre-lien notice to the property owner required by Minn. Stat. 514.011. The court of appeals reversed in part, concluding that Ryan was exempt from the pre-lien notice requirement under section 514.011, and there were genuine issues of fact regarding the other issues. The Supreme Court affirmed as modified, holding that the court of appeals did not err in concluding that Ryan was not required to give pre-lien notice to enforce its mechanic’s liens. View "Ryan Contracting Co. v. O’Neill & Murphy, LLP" on Justia Law

by
The Coyote Valley Band of Pomo Indians and Findleton entered into the Construction Agreement for a gaming facility. In 2008 (10 months later), the Tribe suspended construction because the financial meltdown had adversely affected its ability to secure financing. In 2012, Findleton sought to compel ADR under the Agreement The Tribe asserted that it had not waived its sovereign immunity or consented to suit in the state court and that Findleton’s failure to exhaust his tribal administrative remedies deprived the court of jurisdiction. Findleton cited resolutions by the Tribal Council, waiving immunity. The Tribe has a General Council, consisting of all tribal members 18 years or older, and the Tribal Council, an elective body consisting of seven members of the General Council whose powers are more narrowly circumscribed. The Tribe’s constitution does not permit the Tribal Council to waive sovereign immunity without the General Council’s “consent” and “prior approval.” The court of appeal reversed the trial court’s dismissal of the action, finding that the Council was authorized to waive the Tribe’s immunity and did so in resolutions adopted in 2008 and on June 2, 2007, “in order to attract other individuals and entities to do business with the Tribe.” View "Findleton v. Coyote Valley Band of Pomo Indians" on Justia Law

by
At issue in this case was whether plaintiff, Ronnisch Construction Group (RCG), could seek attorney fees under section 118(2), MCL 570.1118(2), of the Construction Lien Act (CLA) from defendant Lofts on the Nine, LLC (LOTN), given that plaintiff received a favorable arbitration award on its related breach of contract claim but did not obtain a judgment on its construction lien claim. After review, the Michigan Supreme Court held that the trial court could award attorney fees to RCG because RCG was a lien claimant who prevailed in an action to enforce a construction lien through foreclosure. Therefore, the Court affirmed the Court of Appeals and remanded this case back to the trial court for further proceedings. View "Ronnisch Construction Group, Inc. v. Lofts on the Nine, LLC" on Justia Law

by
Byrne & Jones Enterprises, Inc. filed an action against Monroe City R-1 School District alleging that it was denied a fair and equal opportunity to compete in the bidding process for a public works contract to build an athletics stadium. The trial court dismissed the petition, concluding that Byrne & Jones, as an unsuccessful bidder, lacked standing to challenge the school district’s award of the contract to another bidder because it did not bring the action in the interest of the public or as a taxpayer. The Supreme Court affirmed, holding (1) Byrne & Jones had standing to challenge the award of the contract to another bidder; but (2) the trial court did not err in dismissing the petition because Byrne & Jones was not entitled to the relief requested in the petition. View "Byrne & Jones Enters., Inc. v. Monroe City R-1 Sch. Dist." on Justia Law

by
The Weitz Company, LLC, a general contractor, submitted a bid on a planned nursing facility. Weitz’s bid incorporated the amount of a bid submitted to Weitz by H&S Plumbing and Heating for the plumbing work and the heating, ventilation, and air conditioning parts of the job. The project owner awarded the project to Weitz, but H&S reneged on its bid. Weitz used other subcontractors to complete the project at greater expense. Weitz later sued H&S, claiming breach of contract and promissory estoppel. The court determined that the parties had not formed a contract but enforced H&S’s bid under promissory estoppel, awarding Weitz damages of $292,492. The Supreme Court affirmed the judgment and the amount of damages, holding that the district court did not err by entering a judgment for Weitz on its promissory estoppel claim and correctly measured Weitz’s damages. View "Weitz Co., LLC v. Hands, Inc." on Justia Law

by
Appellant City of Allentown (City) contracted with appellee A. Scott Enterprises, Inc. (ASE), to construct a new public road. After arsenic-contaminated soil was discovered at the worksite, the City suspended work on the project. Following testing, it was determined construction could resume if precautions were taken. Accordingly, the City instructed ASE to obtain revised permits and proceed with the project. However, the existing contract did not include terms regarding the potential for contaminated soil, despite the fact the City was aware there might be contamination prior to entering into the contract, and ASE declined to proceed, explaining it would incur substantial additional costs due to the contaminated soil. The parties made several attempts to reach an agreement in which ASE would continue the construction, but to no avail. Consequently, ASE sued the City to recover its losses on the project, alleged breach of contract, and sought compensation under theories of quantum meruit and unjust enrichment, as well as interest and a statutory penalty and fee award for violations of the prompt pay provisions of the Procurement Code. After a trial, a jury found the City breached its contract with ASE and also withheld payments in bad faith. In this discretionary appeal, the issue this case presented for the Supreme Court's review was whether an award of a statutory penalty and attorney fees under the prompt payment provisions of the Commonwealth’s Procurement Code was mandatory upon a finding of bad faith, irrespective of the statute’s permissive phrasing. The Court held such an award was not mandatory, and therefore reversed the order of the Commonwealth Court and remanded the case to the trial court for further proceedings. View "A. Scott Enterprises v. City of Allentown" on Justia Law

by
After TEC, a subcontractor, submitted a written bid to Flintco, a general contractor, to perform glazing work on a project, Flintco used TEC's bid price in compiling its own bid to the owner of the project. Flintco was awarded the contract and sent TEC a letter of intent to enter into a subcontract and a standard-form subcontract, both of which documents differed materially from TEC’s bid. TEC refused to enter into a subcontract. Flintco secured another subcontractor for that scope of work and sued TEC on a theory of promissory estoppel seeking the difference between TEC’s bid and the amount Flintco was required to pay the replacement subcontractor. The trial court entered judgment for TEC. The court concluded that Flintco failed to demonstrate that there was no substantial evidence to support the trial court’s finding that Flintco did not reasonably rely on TEC’s bid price without considering the material conditions stated in TEC’s bid, the proposed subcontract Flintco sent TEC constituted a counteroffer because it contained material variations from the conditions in TEC’s bid, and the counteroffer gave TEC the right to withdraw its bid. Accordingly, the court affirmed the judgment. View "Flintco Pacific v. TEC Mgmt. Consultants" on Justia Law

by
In 2011, Horning won the subcontract for roofing work at the Dayton Veterans Affairs Medical Center. The Davis‐Bacon Act, 40 U.S.C. 3141–43, requires contractors who perform construction for the federal government to pay their workers the “prevailing wage.” Department of Labor regulations at that time set the base rate for a Dayton Sheet Metal Worker at $26.41 per hour; the fringe benefit rate was another $16.82 an hour. The workers were properly classified and received the appropriate base rate. All employees who work at Horning for more than 90 days are eligible for insurance; some receive vacation days. After a year, they become eligible for matching contributions to a 401(k) account. Accountants advised Horning about the amount to deposit into its benefits trust to comply with ERISA and Davis‐Bacon. Horning deducted a flat hourly fee from the paycheck of each Medical Center worker, regardless of whether the employee was eligible for any benefits. The amount did not correspond to the actual monetary value of the benefits each individual employee received. The Union filed a qui tam action under the False Claims Act, 31 U.S.C. 3729–3733, rather than filing under Davis-Bacon. The Seventh Circuit affirmed judgment in favor of Horning. Under the False Claims Act, the Union had to show that Horning knowingly made false statements (or misleading omissions) that were material to the government’s payment decision. The Union did not proffer enough evidence to permit a reasonable jury to conclude that Horning acted with such knowledge. View "Sheet Metal Workers Int'l Assoc. v. Horning Invs., LLC" on Justia Law