Justia Construction Law Opinion Summaries
Articles Posted in Construction Law
Olshan Foundation Repair Company of Jackson, LLC v. Moore
Phillip Moore, Gloria Moore, and Katelyn Moore sued Olshan Foundation Repair of Jackson, LLC (Olshan), and Wayne Brown. Olshan and Brown sought to compel arbitration pursuant to an arbitration provision within a contract between Phillip Moore and Olshan for the repair of the foundation of the Moores’ home. The circuit court ordered Phillip and Gloria Moore to arbitrate their claims. But because the circuit court declined to order Katelyn Moore to the arbitral forum, Olshan and Brown appealed. Finding that Katelyn Moore was neither a third-party beneficiary to the foundation-repair contract nor was she bound by direct-benefit estoppel, the Mississippi Supreme Court found Katelyn Moore’s claims, including negligence and intentional/negligent infliction of emotional distress, were wholly independent of the terms of the contract to which she was not a party. As such, Olshan was not allowed to enforce an arbitration clause respecting Katelyn Moore’s claims, which were unrelated to the contract. View "Olshan Foundation Repair Company of Jackson, LLC v. Moore" on Justia Law
J.R. v. State
The Supreme Court summarily affirmed the parts of the opinion of the court of appeals that addressed and rejected J.R.’s challenge to a pat-down search and remanded to the juvenile court to vacate the delinquency adjudication for carrying a handgun without a license (CHWOL) and affirmed the delinquency adjudication for dangerous possession of a firearm, as all parties agreed that double jeopardy principles precluded J.R.’s dual adjudications.The juvenile court found sixteen-year-old J.R. delinquent for committing acts that would be dangerous possession of a firearm and CHWOL, had they been committed by an adult. On appeal, J.R. argued that a pat-down search violated his constitutional right to be free from unreasonable searches. The court of appeals concluded that the pat-down search was constitutional but that J.R.’s adjudication for CHWOL should be vacated on double jeopardy grounds. The Supreme Court affirmed. View "J.R. v. State" on Justia Law
Leone v. BMI Refractory Services., Inc.
Leone’s employer used a degasser, a large vat lined with brick, to extract gas impurities from molten steel. The degasser’s components include an alloy chute near the top of the vat. The employer hired BMI to “tearout” the degasser’s deteriorated face brick. Although the contract did not include any work on the alloy chute, a BMI employee testified that his team would dislodge loose material from the chute to ensure that nothing could fall. He did not notice any loose slag on the chute. After BMI finished, his employer assigned Leone to reline the degasser. Leone and his crew frequently climbed ladders near the alloy chute. They never spotted any loose slag on the chute but, 21 days after BMI completed its one-day job, a 40-pound piece of slag fell and struck Leone. Leone sued, claiming that the slag detached from the alloy chute. Because no molten metal could have created new slag, the court concluded that the slag must have existed when BMI finished but that BMI owed Leone no duty of care under Michigan law. The Sixth Circuit reversed. The district court interpreted Michigan law too narrowly. Although a contractor’s creation of a new hazard can trigger a duty to third parties, that is not the only way that such a duty might arise. A contractor can be liable to a third party if “any legal duty independent of the contract existed,” including by voluntary assumption of a duty. View "Leone v. BMI Refractory Services., Inc." on Justia Law
Ex parte Consolidated Pipe & Supply Co., Inc.
Consolidated Pipe filed the underlying action against The Ohio Casualty Insurance Company ("Ohio Casualty"), Bolt Construction & Excavating, LLC ("Bolt Construction"), and Michael Bolt (collectively, defendants). The West Morgan East Lawrence Water and Sewer Authority ("the Water Authority") contracted with Bolt Construction to perform a public work known as "the Vaughn Bridge Road Water Line Relocation Project No. 14018.00" ("the project"). In the course of performing its contract with the Water Authority, Bolt Construction entered into a contract with Consolidated Pipe pursuant to which Consolidated Pipe was to supply materials for use in the project. Bolt executed a guaranty in conjunction with the contract with Consolidated Pipe in which he agreed to unconditionally and personally guarantee full and prompt payment of all sums owed to Consolidated Pipe by Bolt Construction in the event Bolt Construction failed to pay the contracted-for amount. In its complaint, Consolidated Pipe alleged Bolt Construction failed to pay Consolidated Pipe for the materials it furnished to Bolt Construction for the project. At issue in this case was venue: the Alabama Supreme Court determined that based on a forum-selection clause, the only proper venue for this action was Morgan County. Therefore, the circuit court erred by granting the motion to transfer. Accordingly, the Court granted Consolidated Pipe's petition for mandamus relief, and directed the Morgan Circuit Court to vacate its order transferring this case to Jackson County. View "Ex parte Consolidated Pipe & Supply Co., Inc." on Justia Law
City of Rapid City v. Big Sky, LLC
The Supreme Court affirmed the judgment of the trial court entering judgment on the jury’s general verdict in favor of real-estate developers (Developers) and against the City of Rapid City in this suit seeking to recover the prospective cost of repairing roads in a development outside Rapid City.Specifically, the Court held that the circuit court did not err by (1) denying the City’s motion for summary judgment on the issue of liability; (2) excluding evidence of the Developers’ litigation and settlement with their subcontractors; (3) granting one of the developer’s motion for judgment as a matter of law; (4) instructing the jury on estoppel defenses; and (5) not instructing the jury on the City’s public-nuisance claim. View "City of Rapid City v. Big Sky, LLC" on Justia Law
Young Electrical Contractors, Inc. v. Dustin Construction, Inc.
The award of summary judgment in favor of the general contractor against the subcontractor in this case based on a pay-if-paid clause was improper because the pay-if-paid clause did not apply to the issues in this case.Pay-if-paid clauses make the project owner’s payment of the general contractor a condition precedent of the general contractor’s obligation to pay the subcontractor. Thus, the pay-if-paid clause can relieve the general contractor of liability to the subcontractor even where the subcontractor has fully performed its part of the subcontract. Here, Subcontractor sued General Contractor for breach of contract relating to a construction project. The circuit court granted summary judgment to General Contractor, concluding that, under Virginia law, a pay-if-paid provision in the subcontract applied to the damages sought. The Supreme Court reversed and remanded the case, holding (1) the pay-if-paid clause did not necessarily apply to the costs at issue in this case; and (2) the other provision relied upon by the circuit court did not create a condition precedent for payment of subcontractors. View "Young Electrical Contractors, Inc. v. Dustin Construction, Inc." on Justia Law
ProLite Building Supply, LLC v. Ply Gem Windows
Prolite Building Supply bought Ply Gem windows, which it resold to Wisconsin builders. Some homeowners were not satisfied with the windows, which admitted air even when closed. Contractors stopped buying from Prolite, which stopped paying Ply Gem. Prolite and homeowners sued. Ply Gem removed the action to federal court and counter-claimed against Prolite for unpaid bills. Additional parties intervened. The Seventh Circuit affirmed summary judgment in favor of Prolite. The court vacated the judgment on the homeowners’ claims for remand to state court. The service agreement between Prolite and Ply Gem requires Prolite to repair the Ply Gem windows in exchange for a discount and needed parts. There was no breach of that agreement. The homeowners’ claims can be resolved under supplemental jurisdiction only if they “are so related to claims in the action within such original jurisdiction that they form part of the same case or controversy,” 28 U.S.C. 1367(a). The language of the window warranties received by the homeowners and the service agreement did not overlap. Prolite complained that Ply Gem did not do enough to ensure that its customers (the builders) remained willing to purchase Ply Gem windows. The homeowners just wanted to stop drafts and moisture. The nature of the work done differed. View "ProLite Building Supply, LLC v. Ply Gem Windows" on Justia Law
LeGrand Johnson Construction Co. v. Celtic Bank Corp.
The Supreme Court reversed the decision to award prejudgment interest to LeGrand and concluded that Celtic Bank was the prevailing party on the prejudgment interest issues.LeGrand Johnson Construction Company filed an action seeking to enforce its mechanic’s lien on property owned by B2AC, LLC for the unpaid value of construction services, and Celtic Bank, B2AC’s lender, sought to foreclose on the same property after B2AC failed to pay on its loan. The action resulted in a lien for $237,294 and an award of attorney fees and costs. Thereafter, the district court determined that LeGrand’s lien, rather than Celtic Bank’s lien, had priority and awarded LeGrand attorney fees and costs. The court then ruled that LeGrand was entitled to recover eighteen percent in prejudgment and postjudgment interest from Celtic Bank based on LeGrand’s contract with B2AC. The Supreme Court (1) reinforced its holding in Jordan Construction, Inc. v. Federal National Mortgage Ass’n, 408 P.3d 296 (Utah 2017), that prejudgment interest is not available under the 2008 version of the Utah Mechanic’s Lien Act; and (2) vacated the attorney fee award because it was based, in part, on the notion that LeGrand had succeeded in establishing its right to prejudgment interest. View "LeGrand Johnson Construction Co. v. Celtic Bank Corp." on Justia Law
Bruckner v. State
The Supreme Court affirmed Appellant’s conviction of one count of sexual assault in the first degree, holding that Appellant’s trial counsel did not provide ineffective assistance.The jury in this case concluded that Appellant committed sexual intrusion upon a non-consenting victim whom Appellant knew or had reason to believe was physically helpless. On appeal, Appellant argued that his trial counsel provided ineffective assistance by failing to object to inadmissible evidence, failing to adequately advance her theory of the case, and failing to suppress the statements made by Appellant when under investigative detention. The Supreme Court disagreed, holding that trial counsel was not ineffective in her representation of Appellant. View "Bruckner v. State" on Justia Law
Lacy v. State
The Supreme Court affirmed in part and reversed and dismissed in part the order of the circuit court denying Appellant’s petition for postconviction relief filed pursuant to Ark. R. Crim. P. 37.5.The Court reversed and dismissed as to the issue of whether trial counsel’s failure to present the affirmative defense of not guilty by reason of mental disease or defect was ineffective assistance of counsel, holding that the trial court did not have jurisdiction to consider this issue. The Court otherwise affirmed, holding (1) the trial court did not err in finding that counsel did not provide ineffective assistance as to Appellant’s remaining allegations of defective representation; and (2) the cumulative error rule in allegations of ineffective assistance of counsel should not be recognized in Arkansas. View "Lacy v. State" on Justia Law