Justia Construction Law Opinion Summaries

Articles Posted in Construction Law
by
North Edwards Water District (the District) selected Clark Bros., Inc. (Clark) as its general or direct contractor on a public works project to build an arsenic removal water treatment plant. Clark hired subcontractor Crosno Construction (Crosno) to build and coat two steel reservoir tanks. The subcontract contained a "pay-when-paid" provision that stated Clark would pay Crosno within a reasonable time of receiving payments from the District, but that this reasonable time "in no event shall be less than the time Contractor and Subcontractor require to pursue to conclusion their legal remedies against Owner or other responsible party to obtain payment . . . ." After Crosno completed most of its work, a dispute arose between the District and Clark halting the project. As Clark sued the District, Crosno sought to recover payments owed under the public works payment bond that Clark had obtained for the project. The issue this case presented for the Court of Appeal's review involved Crosno's claim against the bond surety, Travelers Casualty and Surety Company of America (Travelers). At issue was whether the pay-when-paid provision in Crosno's subcontract precluded Crosno from recovering under the payment bond while Clark's lawsuit against the District was pending. Relying on Wm. R. Clarke Corp. v. Safeco Ins. Co., 15 Cal.4th 882 (1997), the trial court found the pay-when-paid provision here unenforceable because it affected or impaired Crosno's payment bond rights in violation of Civil Code section 8122. With the facts largely undisputed, the court granted Crosno's motion for summary judgment and entered judgment in its favor for principal due plus prejudgment interest. Travelers argued the trial court misconstrued Wm. R. Clarke and erred in failing to enforce the pay-when-paid provision against the bond claim. After carefully considering the parties' arguments, the Court of Appeal agreed with the trial court's analysis and affirmed. View "Crosno Construction, Inc. v. Travelers Casualty etc." on Justia Law

by
The Supreme Court reversed the judgment of the court of appeals dismissing Appellant's appeal of the trial court's grant of summary judgment for Plaintiff and against Defendants for want of jurisdiction, holding that, contrary to the decision of the court of appeals, the trial court's judgment was final and appealable.Plaintiff sued Defendants for declaratory judgment and monetary damages arising from a commercial construction project. The trial court awarded summary judgment in favor of Plaintiff. Despite the trial court's confirmation of its intent to render a final judgment, the court of appeals concluded that no final judgment had been rendered. The Supreme Court reversed, holding that the court of appeals erred by analyzing the record for evidence of finality after the trial court provided a clear and unequivocal statement that it had intended the appealed-from order to be a final judgment. View "Bella Palma, LLC v. Young" on Justia Law

by
Michael Montgomery, an employee of Taylor Construction working as a truck dispatcher, called Superior Mat Company to rent mats for Taylor Construction’s use. From June 9, 2017, to June 27, 2017, Taylor employees drove to Superior’s location in Covington County and picked up more than seven hundred mats. When Taylor returned the mats, Superior alleged that many were in varying degrees of dirtiness, or in some cases, damaged beyond repair. Taylor paid Superior for the mats until Superior additionally billed Taylor for the mats Taylor did not return. Taylor later stopped payment on all invoices from Superior. Superior filed suit against Taylor in Covington County Circuit Court, alleging breach of contract, open account, quantum meruit, and bad-faith breach of contract. Taylor filed its answer along with a motion to transfer venue under Rule 82(d). After hearing arguments, the circuit court denied Taylor's motion. Taylor appealed. The Mississippi Supreme Court affirmed, finding the record demonstrated credible evidence that substantial events or acts occurred in Covington County. View "Taylor Construction Company, Inc. v. Superior Mat Company, Inc." on Justia Law

by
Restore was asked to mitigate and repair significant fire damage at Proviso East High School, having provided similar service to the District in the past. The District’s customary practice when contracting for repair and payment of losses covered by insurance was to proceed without a recorded vote of its Board. The fire loss was covered by insurance. The District’s superintendent executed contracts with Restore.The District was subject to the School District Financial Oversight Panel (FOP) and Emergency Financial Assistance Law (105 ILCS 5/1B-1) and the Financial Oversight Panel Law (105 ILCS 5/1H-1). The FOP’s chief fiscal officer attended construction meetings and approved numerous subcontracts, quotations, bids, sales orders, change orders, and invoices. Although there was no recorded vote, “a majority of the Proviso Board knew and informally approved" the work. Restore was paid by the insurers for all but $1,428,000. Restore sued, seeking recovery from the District based on quantum meruit. The District argued that it had no obligation to pay because the contracts had not been let out for bid and approved by a majority vote as required by the School Code (105 ILCS 5/1-1).The Illinois Supreme Court affirmed the reinstatement of the case following dismissal. The failure of a governmental unit to comply with required contracting methods is not fatal to a plaintiff’s right to recover based on quasi-contract or implied contract principles. The Board was subject to the FOP; the FOP was fully apprised of and approved the work. Any misconduct was on the part of the Board; allowing Restore to recover presents no “risk of a raid on the public treasury.” View "Restore Construction Co., Inc. v. Board of Education of Proviso Township High Schools District 209" on Justia Law

by
Western Surety filed suit against US Engineering, seeking declaratory and injunctive relief regarding its potential liability under a construction performance bond. Western Surety claimed that its obligations under the bond were discharged because U.S. Engineering failed to comply with a condition precedent, thereby relieving Western Surety of any liability.The DC Circuit affirmed the district court's grant of summary judgment for Western Surety. Because the bond expressly provides the surety with the opportunity to participate in curing the subcontractor's default, the court held that it is a condition precedent to the surety's obligations under the bond that the owner must provide timely notice to the surety of any default and termination before it elects to remedy that default on its own terms. In this case, US Engineering failed to provide such timely notice, and thus Western Surety was not obligated to perform under the bond. The court also held that the bond is clear that Western Surety is not required to demonstrate actual prejudice to avoid liability under these circumstances. View "Western Surety Co. v. U.S. Engineering Construction, LLC" on Justia Law

by
A construction contractor’s employees were injured on the job and received workers’ compensation benefits from their employer. The workers later brought a negligence suit against three other corporations: the one that had entered into the construction contract with their employer, that corporation’s parent corporation, and an affiliated corporation that operated the facility under construction. The three corporations moved for summary judgment, arguing that all three were “project owners” potentially liable for the payment of workers’ compensation benefits and therefore were protected from liability under the exclusive liability provision of the Alaska Workers’ Compensation Act. The superior court granted the motion, rejecting the workers’ argument that status as a “project owner” was limited to a corporation that had a contractual relationship with their employer. After review, the Alaska Supreme Court concluded a project owner, for purposes of the Act, "must be someone who actually contracts with a person to perform specific work and enjoys the beneficial use of that work." Furthermore, the Court found the workers raised issues of material fact about which of the three corporate defendants satisfied this definition. Judgment was therefore reversed and the matter remanded for further proceedings. View "Lovely, et al. v Baker Hughes, Inc., et al." on Justia Law

by
In this construction law case, the Supreme Court reversed the order of the circuit court granting summary judgment in favor of Appellee, holding that Appellee was not entitled to claim preclusion or issue preclusion even though the federal court found in Appellee favor in a parallel federal case.The dispute in this case arose out of a contract between two subcontractors in a construction project. In the federal case, subcontracting parties litigated questions related to the fabrication of the salt conveyor system. The federal district court ruled in favor of Appellee. Appellant filed a second lawsuit in state court against subcontractors involved in the federal case. Appellee filed a motion for summary judgment, arguing that the judgment in the federal litigation compelled judgment in its favor in the state court litigation. The district court granted summary judgment for Appellee on both claim preclusion and issue preclusion. The Supreme Court reversed, holding (1) under Noel v. Noel, 334 N.W.2d 146 (Iowa 1983), and Pagel v. Notbohm, 186 N.W.2d 638 (Iowa 1971), Appellee waived its claim preclusion argument; and (2) that the state district court ruling took too broad an approach to what the "issue" was in the federal lawsuit. View "Lemartec Engineering & Construction v. Advance Conveying Technologies, LLC" on Justia Law

by
The Supreme Court conditionally granted Mobile Mini, Inc.'s petition for writ of mandamus and directed the trial court to vacate its order denying Mobile Mini's motion to designate a responsible third party in a construction worker's personal injury suit, holding that the trial court was obligated to grant Mobile Mini's motion to designate a responsible third party under the circumstances of this case.Mobile Mini, the owner of a construction trailer, was sued for injuries Luis Covarrubias received when a wind gust blew the door of the trailer closed on his hand. Mobile Mini filed a motion to designate Nolana Self Storage, LLC, the owner of the construction site, as a responsible third party so a jury could determine whether Nolana caused or contributed to Covarrubias's injury. The trial court denied Mobile Mini's request. The court of appeals denied Mobile Mini's mandamus petition. The Supreme Court conditionally granted the petition and directed the trial court to vacate its order denying Mobile Mini's motion to designate Nolana as a responsible third party, holding that Mobile Mini's discovery response disclosing Nolana as a potentially responsible third party was timely even though it was served after the statute of limitations had expired on Covarrubias's tort claims. View "In re Mobile Mini, Inc." on Justia Law

by
At stake in this appeal before the Mississippi Supreme Court was the ability of Hobbs Construction, LLC, to continue doing business in the state as a commercial general contractor. The Mississippi State Board of Contractors revoked the certificate of responsibility (COR) held by Hobbs. The chancery court granted Hobbs’s motion for a preliminary injunction and enjoined the Board’s revocation decision during the pendency of the appeal. Later the chancery court entered an order reversing the Board’s decision and reinstating Hobbs’s COR. The Board appealed, arguing that the chancery court erred because the Board’s revocation decision was supported by substantial evidence, was not arbitrary and capricious, was within the Board’s power to make, and did not violate Hobbs’s statutory or constitutional rights. The Board argued also that the chancery court erred by granting a preliminary injunction. The Supreme Court determined the Board violated Hobbs’s constitutional right to due process of law by not providing sufficient notice of the charges that were considered at the revocation hearing and were a basis for the revocation decision, therefore it affirmed the chancery court's. Furthermore, the Supreme Court found the chancery court did not err by granting a preliminary injunction. View "Mississippi State Board of Contractors v. Hobbs Construction, LLC" on Justia Law

by
The Supreme Court reversed the decision of the district court granting summary judgment in favor of Plaintiffs in this action seeking to recover delinquent contributions to various trust funds for construction on a state construction project, holding that the right of action under a payment bond statute extends to any amount due an employee, meaning any amount that is traceable specifically to an employee.One of the subcontractors hired to work on the project failed to make contributions to various trust funds for its employees' work on the project, as required by trust agreements and a collective bargaining agreement. The trusts (Plaintiffs) sought to recover the delinquent contributions from the public payment bond associated with the project by suing Defendant, the surety for the payment bond. The district court granted summary judgment for Plaintiffs. On appeal, the parties disputed whether Utah Code 63G-6-505(4) limits the right of action on a payment bond to amounts due to an employee or encompasses claims for any amounts due for an employee or on the employee's behalf. The Supreme Court reversed, holding that the right of action under the public payment bond statute contemplates recovery of any specific benefit that is due a person in the sense of being traceable to that person. View "McDonald v. Fidelity & Deposit Co. of Maryland" on Justia Law