Bldg. Materials Corp. of Am. v. Bd. of Educ.
For some years, the Board of Education of Baltimore County belonged to a governmental group purchasing consortium, which competitively bid a roofing services contract on behalf of its members. The Board relied on that contact to fulfill its needs for roofing repair services. Appellant Building Materials Corporation of America, a nationwide manufacturer of roofing materials, questioned the Board's authority for that practice under the pertinent statutes. The circuit court granted summary judgment in favor of the Board. The Court of Appeals affirmed, holding that when viewed in the context of the entire education law and regulations promulgated under that law, the competitive bidding statute did not bar the Board from using its membership in an intergovernmental purchasing consortium for the procurement of roofing repair services. View "Bldg. Materials Corp. of Am. v. Bd. of Educ." on Justia Law
State In the Interest of V.A.
The issue before the Supreme Court centered on a decision by a county prosecutor to seek waiver of three juveniles, aged sixteen at the time of their offenses, to adult court for acts of delinquency that, as charged, were equivalent to aggravated assault, robbery, and second-degree conspiracy. A Family Part judge found probable cause that the juveniles committed the offenses but denied the waiver motion. The Appellate Division reversed, concluding that the Family Part overstepped its bounds. The case called into question the standard of review to be exercised by a court reviewing such motions for waiver. "An abuse of discretion review does not allow the court to substitute its judgment for that of the prosecutor. Rather, a review for abuse of discretion involves a limited but nonetheless substantive review to ensure that the prosecutor’s individualized decision about the juvenile before the court, as set forth in the statement of reasons, is not arbitrary or abusive of the considerable discretion allowed to the prosecutor by statute. Cursory or conclusory statements as justification for waiver will not suffice to allow the court to perform its review under the abuse of discretion standard because such statements provide no meaningful explanation of the prosecutor’s reasoning." Applying that standard, the Court held that in this case the prosecutor’s explanation in the Statements of Reasons lacked detail. The Court reversed and remanded this case for a more full explanation by the prosecutor according to the new standard outlined in the Court's opinion.
View "State In the Interest of V.A." on Justia Law
Patrick Eng’g v. City of Naperville
Patrick Engineering signed a 2007 contract with the City of Naperville for work on a stormwater management system. Some work was done and some payments were made, but the parties fell into a dispute over “additional services.” Patrick terminated the agreement and sued Naperville, seeking $436,392. The agreement provided that if Naperville made a verbal request for additional services, the engineers were required to confirm that request in writing and were not obligated to perform the changes until authorized in writing. This procedure was not followed; equitable estoppel became the crux of the case. The trial court dismissed. The appellate court reversed. The city did not appeal with respect to claims of quantum meruit and under the Illinois Local Government Prompt Payment Act, which remain pending in the trial court. The supreme court reversed with respect to other claims and reinstated the dismissals. While equitable estoppel may apply against municipalities in extraordinary and compelling circumstances, Illinois courts have never held that apparent authority may be applied against municipalities. To recover in equitable estoppel, plaintiff must allege specific facts showing that municipal officials possessed actual, rather than apparent, authority on which plaintiff reasonably relied.View "Patrick Eng'g v. City of Naperville" on Justia Law
Hip Heightened Indep. & Progress, Inc. v. Port Auth. of NY & NJ
The Port Authority’s subsidiary, PATH, operates the Grove Street Station in Jersey City. The Station was built in 1910. In 2000 PATH planned to expand the Station to accommodate larger trains and persons with disabilities, a project that would have involved construction of a new entrance and two elevators. After September 11, 2001, and the resulting closure of two stations, ridership increased at the Station. Concerned about congestion and safety, PATH scrapped its renovation plans and undertook a “fast track” project. Construction began in 2002 and concluded in 2005. Plaintiffs alleged that the renovations triggered an obligation under the Americans with Disabilities Act, 42 U.S.C. 12101–12213, to make the Station accessible to handicapped persons. They also alleged violations under New Jersey’s Law Against Discrimination and certain state construction code provisions. The district court dismissed, state-law claims on the basis that allowing such claims to proceed would violate the interstate compact between New York and New Jersey that created the Authority, but ordered the Authority to make the east entrance accessible. The Third Circuit affirmed dismissal of the state law claims, but remanded the ADA issue for trial on the issue of feasibility. View "Hip Heightened Indep. & Progress, Inc. v. Port Auth. of NY & NJ" on Justia Law
United States v. Stoerr
Stoerr pled guilty to bid rigging, 15 U.S.C. 1; conspiracy to provide kickbacks and to defraud the United States, 18 U.S.C. 371; and assisting in the preparation of false tax returns, 26 U.S.C. § 7206(2). The convictions stemmed from kickback payments that Stoerr solicited and accepted from sub-contractors in connection with environmental remediation projects managed by Sevenson, his employer from 1980 to October 2003. In total, the district court determined that the scheme resulted in losses of $134,098.96 to the EPA and $257,129.22 to Tierra. After Sevenson learned of the kickbacks scheme, it paid Tierra approximately $241,000 to compensate for its losses. It then commenced a civil action against Stoerr in state court to recover its losses, and sought restitution in connection with Stoerr’s sentencing, under the Mandatory Victims Restitution Act, 18 U.S.C. 3663A, for reimbursement of the amount that it paid to Tierra. The district court denied Sevenson‟s request for restitution, instead ordering that Stoerr pay restitution to Tierra. The Third Circuit dismissed; as a non-party, Sevenson lacks standing to appeal.
View "United States v. Stoerr" on Justia Law
Remodeling Dimensions, Inc., v. Integrity Mut. Ins. Co.
A home remodeling contractor (Contractor) received a demand for arbitration regarding allegedly defective work it performed on a remodeling project. Contractor's insurer (Insurer) accepted defense of the claim under a reservation of rights. The arbitrator issued an arbitration award in favor of the homeowners. When Insurer refused to pay the award, Contractor paid the homeowners and sued Insurer for indemnification under the policy. The district court granted Contractor's motion for summary judgment, concluding that a vague arbitration award made it impossible to determine whether the insurance policy covered any of the homeonwers' successful claims and was directly attributable to the inaction of the attorney appointed by Insurer to represent Contractor. The court of appeals reversed. The Supreme Court reversed, holding (1) a portion of the homeowners' claim may be covered under the policy; (2) Insurer was not vicariously liable of the absence of an explanation of the arbitration award; and (3) Insurer was directly liable to Contractor for the failure of the attorney to request an explanation of the arbitration award to determine what portion of the award, if any, was for the covered claim. Remanded. View "Remodeling Dimensions, Inc., v. Integrity Mut. Ins. Co." on Justia Law
State v. Alarcon-Chavez
Defendant was convicted of first degree murder, use of a deadly weapon to commit a felony, and tampering with a witness. In this direct appeal, Defendant contended (1) the district court erred in overruling his motion to suppress evidence; (2) the district court erred in giving jury instructions that incorrectly stated the law; and (3) the prosecutor's closing remarks were so inflammatory that reversal under the plain error standard was warranted. The Supreme Court affirmed, holding (1) the district court did not err in overruling Defendant's motion to suppress; (2) Defendant was not prejudiced and his substantial rights were not affected by the jury instructions; and (3) the prosecutor's comments did not prejudice Defendant. View "State v. Alarcon-Chavez" on Justia Law
Lexington Insurance Co. v. Southern Energy Homes, Inc.
Lexington Insurance Company and Chartis, Inc. appealed a circuit court order that appointed a third arbitrator to the arbitration panel established to settle a dispute between Lexington and Southern Energy Homes, Inc. ("SEH"). From January 1, 2002, through October 31, 2004, SEH purchased from Lexington three commercial general-liability ("CGL") policies. An endorsement to a CGL policy insuring SEH from January 1, 2002, through December 31, 2002, provided that SEH is responsible for a $100,000 self-insurance retention ("SIR") "per occurrence." Endorsements to two successive CGL policies that together provided coverage to SEH through October 31, 2004, provide that SEH is responsible for a $250,000 SIR per occurrence. The SIR applied both to costs of defense incurred by SEH and to amounts SEH pays in settlement or pursuant to a judgment. From January 1, 2002, through October 31, 2004, SEH was named as a defendant in 46 lawsuits alleging property damage and personal injury resulting from SEH's using a vinyl-on-gypsum product in the homes it manufactured. SEH gave notice of these lawsuits to Lexington, and that it had exhausted its SIR amounts in the litigation and was entitled to reimbursement from Lexington. More than 120 days passed without SEH receiving a decision from Lexington as to whether it agreed with SEH's claim for this amount. SEH made an arbitration demand pursuant to the arbitration clauses of the CGL policies, including the SIR endorsement to the 2002 policy. Upon review of the policies in question, the Supreme Court concluded that the circuit court erred in appointing the third arbitrator. The order was reversed and the case was remanded for further proceedings. View "Lexington Insurance Co. v. Southern Energy Homes, Inc. " on Justia Law
Scottsdale Ins. Co. v. Nat’l Sur. Corp.
Swanson hired ISF for steel fabrication work on an Indiana construction project. ISF hired Central to perform steel erection work. ISF and Central signed a subcontract in which Central agreed to procure insurance and to “defend, indemnify and hold harmless.” Central purchased insurance from Scottsdale: a $1 million commercial general liability policy and a $2 million umbrella insurance policy. ISF also carried $1 million in commercial general liability coverage from Amerisure and $7 million in umbrella coverage from National. Colip, a Central employee, was injured at work when he fell 30 feet through a hole in a building roof. Colip settled with ISF for $2.9 million, and the insurers paid according to an agreement that provided that Scottsdale would pay $1 million out of the CGL policy and $950,000 out of the Umbrella policy, while Amerisure would pay the remaining $950,000. Initially, National had no obligation to contribute. The agreement reserved the rights of the parties to seek reimbursement or contribution from each other. Amerisure sued Scottsdale and Central; Scottsdale filed counter- and cross-claims against Amerisure and National. The district court dismissed Central from the litigation and awarded Scottsdale $50,000 from Amerisure and the remaining $900,000 from National. The Seventh Circuit affirmed. View "Scottsdale Ins. Co. v. Nat'l Sur. Corp." on Justia Law
Pinnacle Museum Tower Ass’n v. Pinnacle Market Dev.
An owners association for a construction defect action against a condominium developer, seeking recovery for damage to its property and damage to the separate interests of the condominium owners who composed its membership. In response, the developer filed a motion to compel arbitration based on a clause in the recorded declaration of covenants, conditions, and restrictions providing that the association and the individual owners agreed to resolve any construction dispute with the developer through binding arbitration. The trial court determined that the clause embodied an agreement to arbitrate between the developer and the association but invalidated the agreement upon finding it marked by slight substantive unconscionability and a high degree of procedural unconscionability. The court of appeal affirmed. The Supreme Court reversed, holding that the arbitration clause bound the association and was not unconscionable. View "Pinnacle Museum Tower Ass'n v. Pinnacle Market Dev." on Justia Law