Justia Construction Law Opinion Summaries
Articles Posted in Construction Law
Sletten Construction of Wyoming, Inc. v. Big Horn Glass, Inc.
Gunwerks sought to expand its business by constructing a new manufacturing facility in Cody, Wyoming, a project involving public funds and coordinated through Forward Cody Wyoming, Inc. Forward Cody retained Plan One Architects and Sletten Construction of Wyoming, Inc. as the project's designer and general contractor, respectively. Sletten hired various subcontractors, including Big Horn Glass, Inc. (BHG), to perform specific tasks. After completion, Gunwerks alleged numerous construction defects in the facility, including issues with concrete, finishes, HVAC, siding, drainage, ceiling heights, door and window flashings, and the shooting tunnel. Gunwerks sued Forward Cody, Plan One, and Sletten for breach of contract and breach of the covenant of good faith and fair dealing.Sletten responded to Gunwerks’s lawsuit by filing a third-party complaint against its subcontractors, including BHG. Sletten claimed that, should it be found liable to Gunwerks, subcontractors responsible for any deficient work should indemnify it for those damages. Sletten did not specifically admit or allege deficiencies in BHG’s work but sought to preserve its right to recovery if any subcontractor was found at fault. Approximately ten months after Sletten’s third-party complaint, BHG moved for summary judgment in the District Court of Park County, arguing that Sletten had not presented evidence showing BHG caused any of the alleged damages. The district court granted summary judgment for BHG, finding that Sletten had not countered BHG’s prima facie showing with disputed facts, relying instead on speculation.On appeal, the Supreme Court of Wyoming reviewed the district court’s summary judgment ruling de novo, applying the same standard as the lower court and viewing the record most favorably to Sletten. The Supreme Court affirmed the district court’s decision, holding that Sletten failed to present admissible, competent evidence creating a genuine issue of material fact regarding BHG’s liability for any alleged defects. The court found Sletten’s evidence speculative and conclusory, insufficient to defeat summary judgment. The disposition was affirmed. View "Sletten Construction of Wyoming, Inc. v. Big Horn Glass, Inc." on Justia Law
Perkins v. RMR Building Group
A Nebraska limited liability company owned by Michael Perkins hired RMR Building Group, LLC, managed and solely owned by Robert M. Ryan II, as a general contractor to redevelop a shopping center. Their contract used a cost-plus billing arrangement, where Perkins paid RMR in advance for specific construction costs, including a substantial sum for HVAC equipment and RMR’s fee. RMR deposited the funds into its general operating account but did not pay for the HVAC equipment; instead, it used the money to cover other business obligations. Perkins terminated the contract after RMR failed to provide proof of payment for the equipment and then sued RMR and Ryan for breach of contract, unjust enrichment, conversion, and fraudulent misrepresentation, also seeking to pierce the corporate veil and hold Ryan personally liable.The District Court for Douglas County found that RMR breached the contract and was liable under theories of money had and received and unjust enrichment, but not for conversion or fraudulent misrepresentation. The court declined to disregard RMR’s corporate entity, finding no sufficient evidence that Ryan diverted funds for personal use or that RMR was a mere facade for Ryan’s dealings. Perkins appealed these findings.The Nebraska Court of Appeals reversed in part, concluding that the corporate veil should be pierced and Ryan held jointly and severally liable for the misappropriated funds, relying on factors from United States Nat. Bank of Omaha v. Rupe. On further review, the Nebraska Supreme Court reversed the Court of Appeals, holding that the evidence did not establish by a preponderance that RMR’s entity should be disregarded, nor did it support fraud or conversion claims against Ryan. The Supreme Court remanded with direction to affirm the district court’s judgment. View "Perkins v. RMR Building Group" on Justia Law
Ward v. Bishop Construction
Joel Ward performed construction work for Bishop Construction, LLC and its sole member, Ren Bishop, in Idaho, Montana, and Wyoming, with an agreed hourly wage and travel compensation. Despite keeping detailed records of his hours, Ward was not paid for work completed between 2017 and 2019, leading him to pursue payment through legal action. The dispute centered on whether Ward should be classified as an employee or an independent contractor and whether he was required to register as a contractor under Idaho law.The case was first heard in the District Court of the Seventh Judicial District of Idaho, Bonneville County. After a bench trial, and based on the parties’ stipulation that Ward was an independent contractor, the court dismissed his wage claims, leaving only breach of contract and unjust enrichment claims. The district court initially awarded Ward full damages for breach of contract. However, after Bishop raised the issue of contractor registration under the Idaho Contractor Registration Act (ICRA) in post-trial motions, the court amended its findings, limited contract damages to out-of-state work, awarded unjust enrichment damages for Idaho work, and granted costs and attorney fees.On appeal, the Supreme Court of the State of Idaho reviewed whether Ward was required to register as a contractor under ICRA and whether the contract was illegal. The Court held that Bishop failed to meet his burden to prove Ward was required to register under ICRA, as the record did not establish Ward’s status as a contractor for those purposes. The Supreme Court vacated the district court’s amended judgment and remanded with instructions to reinstate its original findings and amended judgment, including the previously awarded attorney fees and costs. The Court also awarded Ward attorney fees and costs on appeal as the prevailing party. View "Ward v. Bishop Construction" on Justia Law
Johnson v. Rubylin, Inc.
A plaintiff filed a lawsuit against the owner of a restaurant, alleging violations of accessibility laws and seeking damages as well as attorney fees and costs. The defendant requested an early evaluation conference under the Construction-Related Accessibility Standards Compliance Act, which allows certain defendants to obtain a stay of proceedings and mandates that the plaintiff provide a statement disclosing, among other things, the amount of claimed attorney fees and costs. The plaintiff objected to disclosing this information, arguing that it was protected by attorney-client privilege, and did not include it in the required statement.The Superior Court of Santa Clara County ordered the plaintiff to comply with the statutory disclosure and, after the plaintiff’s continued refusal, imposed sanctions. The court offered the plaintiff a choice between a ruling that would bar recovery of attorney fees or dismissal of the case with prejudice; the plaintiff chose dismissal. On appeal, the plaintiff argued that the requested disclosure was privileged and that the trial court’s process violated due process rights.The California Court of Appeal, Sixth Appellate District, reviewed the case. It held that the statutory requirement to disclose claimed attorney fees and costs for the purposes of an early evaluation conference does not violate the attorney-client privilege. The court found that the statutory scheme does not provide for a privilege exception, and that requiring disclosure does not frustrate the legislative purpose of promoting early settlement. The appellate court also found no due process violation in the trial court’s sanction process, noting that the plaintiff had the opportunity to be heard on the privilege issue. Accordingly, the appellate court affirmed the trial court’s order dismissing the plaintiff’s case with prejudice. View "Johnson v. Rubylin, Inc." on Justia Law
Dibrino v Rockefeller Ctr. N., Inc.
A carpenter employed by a subcontractor was injured after falling from a ladder owned by another subcontractor, DAL Electrical Corporation, while working on a renovation project at an office building. The injured worker was using his own employer’s equipment in the morning but, after lunch, returned to the worksite without his equipment and used an unattended DAL ladder, which was defective and marked with blue tape. He was injured when the ladder wobbled and he fell, impaling himself on a tool in his belt. The worker brought claims under New York Labor Law and for common-law negligence against the project’s general contractor, premises owner, and DAL, asserting the defective ladder caused his injuries. The general contractor and owner sought indemnification from DAL under their subcontract.The Supreme Court of Bronx County granted the worker’s motion for partial summary judgment on one Labor Law claim and denied DAL’s motion to dismiss other claims and cross-claims by the general contractor and owner. The court also granted the general contractor and owner summary judgment on their contractual indemnification claim against DAL. The Appellate Division, First Department, modified this order by denying summary judgment on contractual indemnification and granting summary judgment for DAL on all claims and cross-claims against it. The general contractor and owner appealed to the New York Court of Appeals.The New York Court of Appeals affirmed the Appellate Division’s decision. The Court held that none of the indemnification provisions in the subcontract required DAL to indemnify the general contractor or owner for the worker’s injuries because the injuries did not arise from DAL’s performance of its contractually defined work. The Court also found that DAL did not owe a duty of care in tort to the injured worker, as the facts did not fit within any recognized exception to the general rule against extending contractual duties to non-contracting third parties. The certified question was answered in the affirmative. View "Dibrino v Rockefeller Ctr. N., Inc." on Justia Law
THIRD COAST SERVICES, LLC v. CASTANEDA
Pedro Castaneda died in a traffic accident at an intersection on State Highway 249 that was under construction. At the time, the intersection’s traffic lights were installed but not yet operational, and there was a dispute about whether they were properly covered to indicate their status. Castaneda’s family sued the contractors involved in the project, SpawGlass Civil Construction, Inc. and Third Coast Services, LLC, alleging that negligence in the construction and installation of the traffic signals contributed to the fatal accident. The construction project was governed by an agreement between the Texas Department of Transportation (TxDOT) and Montgomery County, with the County responsible for the project’s design and construction, but with TxDOT retaining authority over the adjacent frontage roads and final approval of plans.The trial court denied the contractors’ motions for summary judgment that sought dismissal under Texas Civil Practice and Remedies Code Section 97.002, which grants immunity to contractors under certain conditions. The contractors appealed. The Fourteenth Court of Appeals affirmed, concluding that Section 97.002 applies only to contractors who are in direct contractual privity with TxDOT, and since neither contractor had a direct contract with TxDOT, they could not invoke the statute’s protection.The Supreme Court of Texas reversed the court of appeals. It held that Section 97.002 does not require direct contractual privity with TxDOT for a contractor to qualify for statutory immunity. The court determined that, based on the summary judgment record, SpawGlass and Third Coast performed work "for" TxDOT within the meaning of the statute, as their activities directly related to frontage roads that TxDOT would own and maintain. The court remanded the case to the court of appeals to determine whether the contractors met the remaining requirements of Section 97.002. View "THIRD COAST SERVICES, LLC v. CASTANEDA" on Justia Law
Ropken v. Yj Construction, Inc.
Russ and Debi Ropken hired a construction company to build a custom home based on an oral agreement. The contractor began work and sent invoices for services and materials, which the Ropkens paid until May 2022, after which they stopped making payments. In July 2022, the Ropkens removed the contractor from the site. The contractor then sent a demand letter for three unpaid invoices totaling $276,169, but the Ropkens refused to pay. The contractor sued to recover the unpaid amount.In the District Court of Park County, the Ropkens admitted owing at least $176,870.21. At the conclusion of a jury trial, the jury found there was a valid contract, the Ropkens had breached it, and awarded the contractor $258,587.70 in damages. The district court entered judgment for that amount and permitted the contractor to request prejudgment interest. The contractor timely filed for prejudgment interest, and the Ropkens objected. The district court found for the contractor, awarding $33,473.25 in prejudgment interest at a statutory rate, and calculated interest from the date of the demand letter. The Ropkens paid the judgment but appealed the prejudgment interest award.The Supreme Court of Wyoming reviewed whether the district court erred in awarding prejudgment interest and whether due process was violated by granting interest without an evidentiary hearing. The court held that a district court may award prejudgment interest even when it is not the trier of fact, as prejudgment interest is a matter of law and not fact. The court found the claim was liquidated and the Ropkens had notice. The court also held that the Ropkens received adequate notice and opportunity to be heard, satisfying due process. The Supreme Court of Wyoming affirmed the award of prejudgment interest. View "Ropken v. Yj Construction, Inc." on Justia Law
Bagelmania Holdings, LLC v. RDH Interests, Inc.
The case centers on a bakery and deli operator, Bagelmania Holdings, LLC, which leased property from Somerset Property, LLC. Together, they renovated the building for Bagelmania’s restaurant, hiring RDH Interests, Inc. as architect, JEM Associates West, Inc. as contractor, and Turpin & Rattan Engineering, Inc. for HVAC mechanical engineering. Following the renovation, Bagelmania and Somerset alleged construction defects and sued these entities for breach of contract, breach of the implied covenant of good faith and fair dealing, and negligence, with both plaintiffs represented by the same attorney.Prior attempts to initiate litigation were dismissed for failing to comply with Nevada’s NRS 11.258 requirements, which mandate an attorney affidavit of merit and supporting expert reports in nonresidential construction defect cases. The plaintiffs then filed a joint complaint supported by one affidavit and a set of expert reports. The defendants argued that each plaintiff was required to file separate affidavits and expert reports, and the Eighth Judicial District Court, Clark County, agreed, dismissing the case with prejudice for failure to comply with NRS 11.258, also awarding attorney fees, costs, and interest to the defendants.On appeal, the Supreme Court of the State of Nevada considered whether a single affidavit and set of expert reports sufficed under NRS 11.258 when coplaintiffs, represented by the same attorney, jointly brought identical claims arising from the same alleged defects. The Supreme Court held that, under such circumstances, separate affidavits and expert reports are not required. The Court found that the plaintiffs complied with the statute’s plain language and purpose and that the affidavit and reports met the statutory requirements. The Supreme Court reversed the district court’s dismissal, vacated the post-judgment award of fees, costs, and interest, and remanded for further proceedings. View "Bagelmania Holdings, LLC v. RDH Interests, Inc." on Justia Law
Design Gaps, Inc. v. Distinctive Design & Construction LLC
A dispute arose from the design and installation of cabinetry in a luxury home in Charleston, South Carolina. Design Gaps, Inc., owned by David and Eva Glover, had a longstanding business relationship with Shelter, LLC, a general contractor operated by Ryan and Jenny Butler. After being dissatisfied with Design Gaps’ performance, the homeowners, Dr. Jason and Kacie Highsmith, and Shelter terminated their contract with Design Gaps and hired Distinctive Design & Construction LLC, owned by Bryan and Wendy Reiss, to complete the work. The Highsmiths and Shelter initiated arbitration against Design Gaps, which led to the arbitrator ruling in favor of the homeowners and Shelter on their claims, and against Design Gaps on its counterclaims, including those for copyright infringement, tortious interference, and unfair trade practices.After the arbitration, Design Gaps sought to vacate the arbitration award in the United States District Court for the District of South Carolina, but the court instead confirmed the award. Concurrently, Design Gaps filed a separate federal lawsuit against several parties, including some who were not part of the arbitration. The defendants moved to dismiss, arguing that res judicata and collateral estoppel barred the new claims, or alternatively, that the claims failed on other grounds such as the statute of limitations and laches. The district court agreed, dismissing most claims based on preclusion or other legal bars, and granted summary judgment on the remaining claims.The United States Court of Appeals for the Fourth Circuit reviewed the district court’s decisions. The court held that res judicata and collateral estoppel applied to bar most of Design Gaps’ claims, even against parties not directly involved in the arbitration but in privity with those who were. For the remaining claims, the court found they were properly dismissed on grounds such as the statute of limitations, waiver, or laches. The Fourth Circuit affirmed the district court’s judgment in full. View "Design Gaps, Inc. v. Distinctive Design & Construction LLC" on Justia Law
Jimenez v. Hayes Apartment Homes
Two young children, ages four and two, were severely injured after falling from a second-floor bedroom window in an apartment building in Lodi, California, where they lived with their mother. The accident occurred shortly after the property owner replaced the apartment’s windows during a renovation that did not include installing fall prevention devices on the upper-floor windows. The children’s guardian ad litem sued the property owner and its manager, alleging negligence based on both general negligence and negligence per se, claiming that the absence of fall prevention devices violated the California Building Standards Code and proximately caused the injuries.The case was heard in the Superior Court of California, County of Alameda. Prior to trial, the defendants sought to defeat the negligence per se claim, arguing the building was exempt from current code requirements because it complied with the code at the time of its original construction in 1980. The trial court denied their motion, allowing both negligence theories to proceed to trial. After plaintiffs presented their case, the court granted a nonsuit for the entire complaint, ruling there was no duty owed under general negligence given lack of foreseeability, and that the window replacement qualified for a code exemption, negating negligence per se.On appeal, the Court of Appeal of the State of California, First Appellate District, Division Four, reviewed the matter de novo. The appellate court affirmed the nonsuit on the general negligence claim, finding the harm was not sufficiently foreseeable to impose a duty. However, it reversed the nonsuit as to negligence per se, holding that replacing the window did not qualify for the “original materials” exemption in the Building Code, and thus the defendants were required to comply with current safety standards. The case was remanded for retrial on the negligence per se claim. View "Jimenez v. Hayes Apartment Homes" on Justia Law