Justia Construction Law Opinion Summaries

Articles Posted in Construction Law
by
A charter city in California entered into an agreement with a private developer to revitalize a nearly vacant mall into a multipurpose development. The city contributed approximately $51.36 million in local funds for public improvements, while the developer invested $143 million of its own funds and obtained additional loans. The developer selected the contractors and paid workers less than the prevailing wage, relying on a city ordinance exempting the project from the Prevailing Wage Law (PWL).The Department of Industrial Relations (DIR) determined that the project was subject to the PWL, as it involved public funds. The developer challenged this determination, but the Superior Court of Riverside County affirmed the DIR's decision, concluding that the project was not a municipal affair exempt from the PWL.The Court of Appeal, Fourth Appellate District, reviewed the case and affirmed the lower court's judgment. The court held that the project was not a municipal affair under the home rule provision of the California Constitution. The court distinguished this case from others where charter cities directly managed and funded public works projects. Here, the developer controlled the construction, selected contractors, and bore the majority of the financial burden. The court concluded that the primary purpose of the project was to benefit the developer, not the city, and thus, the PWL applied. The judgment was affirmed, and the DIR was awarded costs on appeal. View "Palm Springs Promenade, LLC v. Dept. of Industrial Relations" on Justia Law

by
A contractor hired a subcontractor to work on a remote bridge construction project. The scope of the work changed, and neither party kept detailed records of the changes and associated costs. Years after the project was completed, the subcontractor sued for damages, claiming unpaid work. The superior court found that the subcontract did not govern the extra work, awarded some damages to the subcontractor, and precluded some claims due to discovery violations. The court also found the contractor to be the prevailing party and awarded attorney’s fees. Both parties appealed.The superior court denied summary judgment motions from both parties, finding factual disputes. It precluded the subcontractor from pursuing certain damages claims due to insufficient documentation but allowed evidence for contingent findings. After a bench trial, the court awarded the subcontractor $191,443.42, later reduced to $146,693.42 upon reconsideration. The court found the contractor to be the prevailing party under Rule 68 and awarded attorney’s fees.The Supreme Court of Alaska reviewed the case. It concluded that the superior court abused its discretion by precluding the subcontractor’s claims for snowmachine use and labor without considering less severe sanctions. The court affirmed the superior court’s findings on other damages but reversed the awards for Morris Johnson’s labor and boat use, remanding for recalculation. The prevailing party determination and attorney’s fee award were vacated and remanded for reconsideration. The court otherwise affirmed the superior court’s judgment. View "Johnson v. Albin Carlson & Co." on Justia Law

by
Tom Smith Masonry (Smith Masonry) and WIPI Group USA, Inc. (WIPI) entered into a contract for Smith Masonry to construct a fence on WIPI’s property. After completing most of the work, Smith Masonry requested final payment, which WIPI withheld due to a dispute over the installation of a gate operator. Smith Masonry filed a mechanic’s lien and subsequently a lawsuit to foreclose on the lien, seeking the unpaid balance. WIPI counterclaimed for breach of contract and other issues, seeking damages for alleged faulty workmanship.The Circuit Court of the Second Judicial Circuit, Lincoln County, South Dakota, denied relief to both parties, finding that Smith Masonry’s work was defective and that WIPI’s damages were not established with exactitude. Smith Masonry appealed, and the South Dakota Supreme Court reversed and remanded, directing the lower court to enter a judgment of foreclosure in favor of Smith Masonry for the full amount of the lien and to reconsider Smith Masonry’s request for attorney fees.On remand, the circuit court entered a judgment in favor of Smith Masonry on the lien but denied the request for attorney fees. Smith Masonry appealed again. The South Dakota Supreme Court found that the circuit court violated the law of the case doctrine by revisiting issues already settled in the first appeal and by speculating on what might have occurred had the trial resumed. The Supreme Court also held that the circuit court abused its discretion by denying attorney fees based on irrelevant factors and an overly narrow interpretation of the statute governing attorney fees in mechanic’s lien cases.The South Dakota Supreme Court reversed the circuit court’s denial of attorney fees and remanded for a determination of an appropriate award of attorney fees consistent with its opinion. The court also awarded Smith Masonry $30,000 for appellate attorney fees. View "Smith Masonry v. Wipi Group Inc." on Justia Law

by
EdgeRock Development, LLC developed a planned unit development in Westfield, Indiana, comprising retail and residential projects. EdgeRock contracted with C.H. Garmong & Son, Inc. and Fox Contractors Corp. to develop the lots. When EdgeRock fell behind on payments, Garmong and Fox recorded construction liens on all five lots, including those sold to ZPS Westfield, LLC and a nonparty. The contractors sued EdgeRock for breach of contract and sought to foreclose the liens.The Hamilton Superior Court awarded the contractors most of the relief they sought, including foreclosure of the construction liens. The Indiana Court of Appeals reversed the foreclosure, concluding the liens were overstated as they were not limited to debts for improvements directly benefiting the properties to which the liens attached.The Indiana Supreme Court reviewed the case to address the validity and scope of the construction liens and the priority between the construction liens and First Bank Richmond’s mortgage lien. The court held that a construction lien secures only the debt for improvements directly benefiting the property to which the lien attaches. Therefore, the contractors can foreclose the liens on each property to recover only those amounts. The court also concluded that First Bank’s mortgage lien is senior to the construction liens for the amount loaned to satisfy Garmong’s prior construction lien but junior for the remaining amounts.The court affirmed the trial court’s judgment in part, reversed in part, and remanded for the trial court to amend the judgment consistent with its opinion. The court also noted that its holdings do not disturb the in personam judgments against EdgeRock on Garmong’s and Fox’s breach-of-contract claims. View "Edgerock Development, LLC v. C.H. Garmong & Son Inc" on Justia Law

by
Cashman Equipment Corporation, Inc. (Cashman) was contracted by Cardi Corporation, Inc. (Cardi) to construct marine cofferdams for the Sakonnet River Bridge project. Cashman then subcontracted Specialty Diving Services, Inc. (SDS) to perform underwater aspects of the cofferdam installation. Cardi identified deficiencies in the cofferdams and sought to hold Cashman responsible. Cashman believed it had fulfilled its contractual obligations and sued Cardi for breach of contract, unjust enrichment, and quantum meruit. Cardi counterclaimed, alleging deficiencies in Cashman's construction. Cashman later added SDS as a defendant, claiming breach of contract and seeking indemnity and contribution.The Superior Court denied SDS's motion for summary judgment, finding genuine disputes of material fact. The case proceeded to a jury-waived trial, after which SDS moved for judgment as a matter of law. The trial justice granted SDS's motion, finding Cashman failed to establish that SDS breached any obligations. SDS then moved for attorneys' fees, which the trial justice granted, finding Cashman's claims were unsupported by evidence and lacked justiciable issues of fact or law. The trial justice ordered mediation over attorneys' fees, resulting in a stipulated amount of $224,671.14, excluding prejudgment interest.The Rhode Island Supreme Court reviewed the case and affirmed the Superior Court's amended judgment. The Supreme Court held that the trial justice did not err in granting judgment as a matter of law, as Cashman failed to provide specific evidence of justiciable issues of fact. The Court also upheld the award of attorneys' fees, finding no abuse of discretion. Additionally, the Court determined that the attorneys' fees were not barred by the Bankruptcy Code, as they arose post-confirmation and were not contingent claims. View "Cashman Equipment Corporation, Inc. v. Cardi Corporation, Inc." on Justia Law

by
A contractor, Flintco, LLC, entered into a subcontract with Total Installation Management Specialists, Inc. (Total) for flooring work on a construction project at Oklahoma State University. Total was required to secure a performance bond from Oklahoma Surety Company (OSC). Flintco later supplemented Total's workforce due to delays and performance issues but did not notify OSC until five weeks after taking over the work.The Tulsa County District Court ruled in favor of Flintco, awarding damages against Total and OSC. OSC appealed, arguing that Flintco failed to meet the performance bond's conditions requiring a declaration of default and reasonable notice before assuming control of the work. The Court of Civil Appeals reversed the district court's judgment, finding that the notice requirement was a mandatory condition precedent, and Flintco's failure to provide timely notice relieved OSC of liability.The Supreme Court of the State of Oklahoma reviewed the case and agreed with the Court of Civil Appeals. The court held that the performance bond's notice requirement constituted a mandatory condition precedent. Flintco's failure to provide timely notice to OSC so it could exercise its performance options under the bond relieved OSC from liability. The court vacated the Court of Civil Appeals' opinion, reversed the district court's judgment, and remanded the case with instructions to enter judgment consistent with this decision. The trial court's judgments against Total were not affected by this decision. View "Flintco, LLC v Total Installation Management Specialists, Inc." on Justia Law

by
New Star General Contractors, Inc. (New Star) filed a lawsuit to enforce its construction lien on twelve condo units in a large development in Grand County after the developer, Sage Creek at Moab, LLC (Sage Creek), failed to pay for New Star’s construction work. The units’ owners, Dumar, LLC, and Duane Shaw (collectively, Dumar), challenged the lien on multiple grounds. The district court ruled in favor of New Star, allowing it to enforce its lien. Dumar appealed the decision.The Seventh District Court, Grand County, initially heard the case and ruled that New Star could enforce its lien. The court found that New Star’s preliminary notices were sufficient and that the lien was valid despite New Star’s failure to allocate expenses between the units and the common areas. The court also concluded that Dumar was responsible for the full amount of the lien, which included the costs of constructing Building C and its common areas. Dumar’s excessive lien claim was dismissed, and the court awarded attorney fees to New Star.The Supreme Court of the State of Utah reviewed the case. The court held that New Star’s second preliminary notices, which were specific to Building C, substantially complied with the Construction Lien Statute despite not listing the correct parcel numbers. The court declined to analyze the first preliminary notices. The court also held that New Star’s failure to allocate expenses between the units and the common areas did not invalidate the lien. However, the court found that the district court erred in calculating the amount owed under the lien by treating Dumar as owning all the common areas of Building C, rather than only its ownership share in the development. The court remanded the case for the district court to determine the correct amount Dumar owes based on its ownership share.Additionally, the Supreme Court vacated the district court’s order dismissing Dumar’s excessive lien claim and the attorney fee award for New Star. The court directed the district court to reconsider both issues on remand. View "New Star General Contractors, Inc. v. Dumar" on Justia Law

by
Saul Arellano, a roofer, was injured while working on a construction project for Sunrise Homes, Inc. He fell from a roof without fall protection equipment and sustained multiple injuries. Arellano received worker’s compensation benefits through Sunrise Homes after it was discovered that his direct employer did not carry worker’s compensation insurance. Subsequently, Arellano filed negligence and negligence per se claims against Sunrise Homes, arguing that his injuries fell under the “unprovoked physical aggression” exception to Idaho’s worker’s compensation exclusive remedy rule.The District Court of the Seventh Judicial District, Madison County, granted summary judgment in favor of Sunrise Homes. The court concluded that Arellano failed to provide clear and convincing evidence that his claims fell within the statutory exception to the exclusive remedy rule. Specifically, the court found no genuine issues of material fact that Sunrise Homes knew injury or death was substantially likely to occur due to the lack of fall protection equipment.The Supreme Court of the State of Idaho reviewed the case and affirmed the district court’s decision. The Supreme Court held that the district court erred in applying the “clear and convincing” evidentiary standard at the summary judgment stage. However, upon de novo review, the Supreme Court found that Arellano did not raise a genuine issue of material fact regarding Sunrise Homes’ knowledge that injury was substantially likely to occur. The court also rejected Arellano’s arguments that the 2020 amendments to Idaho Code section 72-209(3) codified a more lenient standard or reduced the burden of proof for plaintiffs. Consequently, the Supreme Court affirmed the district court’s order granting summary judgment to Sunrise Homes and awarded costs on appeal to Sunrise Homes. View "Arellano v. Sunrise Homes, Inc." on Justia Law

by
Neely, acting as his own general contractor, hired Grosvold to perform excavation work on his property under an oral contract. Grosvold worked from April to October 2021, but their relationship deteriorated, and Neely refused to pay for an invoice amounting to $55,858. Neely sent Grosvold a notice of alleged defects in the work, which Grosvold disputed. Grosvold then filed a complaint for breach of contract and prejudgment interest, while Neely counterclaimed for breach of contract, negligence, and construction defect.The District Court of the Third Judicial District in Anaconda-Deer Lodge County tried the case before a jury. The court refused to instruct the jury on Neely’s construction defect and negligence claims, reasoning that the evidence did not substantiate the work was done to a residence and that the case was strictly a breach of contract matter. The jury found Neely had breached the contract and awarded Grosvold $60,512.60 in damages. The court denied Grosvold’s request for prejudgment interest, finding the damages were not certain until the jury’s determination.The Supreme Court of the State of Montana reviewed the case. It affirmed the District Court’s decision not to instruct the jury on the construction defect claim, holding that the residential construction defect statute did not create an independent cause of action beyond breach of contract or tort. The court also affirmed the refusal to instruct the jury on negligence, finding that Neely’s substantial rights were not affected as the breach of contract instructions adequately covered the disputed subject matter. Finally, the court upheld the denial of prejudgment interest, concluding the amount of recovery was not capable of being made certain until the jury’s verdict. View "Grosvold v. Neely" on Justia Law

by
The case involves a dispute arising from alleged breaches of a partnership agreement between PNC Bank, N.A., Columbia Housing SLP Corporation (collectively, the "PNC Parties"), and Rene O. Campos, along with 2013 Travis Creek GP, LLC, as general partner. The partnership was formed to acquire, construct, develop, and operate an affordable housing apartment complex in Austin, Texas, with anticipated federal tax credits. A mechanic’s lien was placed on the property, leading to a default on the construction loan. The PNC Parties sought to remove the general partner and replace it with Columbia, resulting in a lawsuit.The PNC Parties filed the lawsuit in the United States District Court for the Western District of Texas, invoking diversity jurisdiction. The district court retained supplemental jurisdiction over the enforcement of the settlement agreement that resolved the 2017 lawsuit. In 2021, the Eureka Parties moved to re-open the case to enforce the settlement agreement, leading to competing motions to enforce. The district court severed the motions from the original lawsuit, creating a new case, and granted each motion in part, offsetting the balance owed. The Eureka Parties and the Partnership appealed.The United States Court of Appeals for the Fifth Circuit reviewed the case and found that the parties failed to establish an independent jurisdictional basis for the severed motions. The court noted that severed claims must have an independent jurisdictional basis and that the record lacked sufficient evidence to establish diversity of citizenship. Consequently, the court remanded the case to the district court for the limited purpose of determining whether such jurisdiction exists. The panel retained jurisdiction over the limited remand. View "PNC Bank v. 2013 Travis Oak Creek" on Justia Law