Justia Construction Law Opinion Summaries
Articles Posted in Civil Procedure
Clearfield County v. Transystems Corp.
A county entered into a contract in the late 1970s with various firms for the construction of a new jail, which was completed in 1981. Decades later, during a renovation in 2021, a construction defect was discovered: the original roof was not properly attached to the masonry walls. The county paid for repairs and, in 2023, sued the original architect, the general contractor, and the masonry subcontractor for negligence, fraudulent misrepresentation or nondisclosure, and breach of contract. Each defendant raised the statute of repose in 42 Pa.C.S. § 5536 as a defense, arguing the claims were filed more than 12 years after completion of the jail.The Court of Common Pleas of Clearfield County sustained the defendants’ preliminary objections, finding the statute of repose applied because the jail was completed in 1981, and the defendants had performed the qualifying construction services. The court further held that the doctrine of nullum tempus occurrit regi, which sometimes allows government entities to avoid statutes of limitations, did not apply to the statute of repose. The county appealed.The Commonwealth Court affirmed, assuming for argument's sake that nullum tempus could apply to statutes of repose, but concluding the county failed to meet the requirements for invoking the doctrine because constructing the jail was not enforcing an obligation imposed by law.Upon further appeal, the Supreme Court of Pennsylvania held that nullum tempus cannot preclude the application of the Section 5536 statute of repose. The court concluded the statute of repose is a legislative judgment eliminating liability for construction professionals after 12 years, and its purpose cannot be undermined by the common law doctrine of nullum tempus. The Supreme Court affirmed the Commonwealth Court’s order upholding dismissal of the complaint. View "Clearfield County v. Transystems Corp." on Justia Law
Cuevas Machine v. Calgon Carbon
Cuevas Machine Company entered into a subcontract with O’Neal Constructors for fabrication and machining work at a filtration plant owned by Calgon Carbon Corporation in Mississippi. Under the subcontract, Cuevas was to be paid after Calgon paid O’Neal. Despite nonpayment from O’Neal, Cuevas continued its work. In October 2023, Cuevas recorded two construction liens totaling over $1.2 million against Calgon’s property, but the lien documents did not explicitly state the last date labor, services, or materials were supplied—a statutory requirement. Instead, Cuevas attached invoices to the liens, which included dates, but it was unclear whether these dates satisfied the statutory requirement.After Cuevas filed suit to foreclose on the liens in Mississippi state court, Calgon removed the case to the United States District Court for the Southern District of Mississippi and moved to dismiss. The district court granted Calgon’s motion, dismissing Cuevas’s complaint with prejudice under Rule 12(b)(6). The district court concluded, making an Erie guess, that the liens were unenforceable because they did not clearly specify the required “last date” in the manner demanded by Mississippi law, and found that the attached invoices did not sufficiently cure this defect.On appeal, the United States Court of Appeals for the Fifth Circuit reviewed the district court’s decision de novo. Finding Mississippi law ambiguous on whether attachments that do not plainly state the “last date” can satisfy the statutory requirement, the Fifth Circuit certified the following question to the Mississippi Supreme Court: whether attaching invoices that do not explicitly state the “last date labor, services or materials were supplied” satisfies the requirement under Miss. Code Ann. § 85-7-405(1)(b) that a lien “specify the date the claim was due.” The Fifth Circuit did not decide the merits, instead certifying the question for authoritative resolution. View "Cuevas Machine v. Calgon Carbon" on Justia Law
Atkinson v. Livingston
Christopher and Jennifer Atkinson purchased a lot in the Ridgeview Trails Major Subdivision in Livingston, Montana, in 2012. The City of Livingston had approved the subdivision in 2005 and 2006, and a geotechnical report identifying problematic soils was created for the subdivision developers but was not provided to the Atkinsons when they purchased the lot. The Atkinsons received a building permit from the City to construct a residence, which was substantially completed in June 2013. In 2021, the Atkinsons began to observe cracking and structural problems in their home. After later discovering the existence of the geotechnical report, they sued the City in April 2024, alleging negligence and negligent misrepresentation for the City’s failure to disclose known soil issues during the permitting process.The case was heard in the Montana Sixth Judicial District Court, Park County. By agreement, the parties proceeded directly to cross-motions for summary judgment to address threshold legal issues before discovery. The District Court granted summary judgment for the City, holding that the claims were barred by Montana’s statute of repose for construction-related claims, found in § 27-2-208, MCA. The District Court also found that the City owed no duty to the Atkinsons, that the public duty doctrine barred the claims, that the Atkinsons had disclaimed claims relating to permits and inspections, and that the geotechnical report was for the developer’s exclusive use.On appeal, the Supreme Court of the State of Montana affirmed the District Court’s judgment. The Supreme Court held that the Atkinsons’ claims were barred by the ten-year statute of repose in § 27-2-208, MCA, because their claims arose from the City’s planning and inspection activities and were filed more than ten years after substantial completion of the home. The Court also held that the statute applies to municipalities and that no statutory exception applied. View "Atkinson v. Livingston" on Justia Law
Ropken v. Yj Construction, Inc.
Russ and Debi Ropken hired a construction company to build a custom home based on an oral agreement. The contractor began work and sent invoices for services and materials, which the Ropkens paid until May 2022, after which they stopped making payments. In July 2022, the Ropkens removed the contractor from the site. The contractor then sent a demand letter for three unpaid invoices totaling $276,169, but the Ropkens refused to pay. The contractor sued to recover the unpaid amount.In the District Court of Park County, the Ropkens admitted owing at least $176,870.21. At the conclusion of a jury trial, the jury found there was a valid contract, the Ropkens had breached it, and awarded the contractor $258,587.70 in damages. The district court entered judgment for that amount and permitted the contractor to request prejudgment interest. The contractor timely filed for prejudgment interest, and the Ropkens objected. The district court found for the contractor, awarding $33,473.25 in prejudgment interest at a statutory rate, and calculated interest from the date of the demand letter. The Ropkens paid the judgment but appealed the prejudgment interest award.The Supreme Court of Wyoming reviewed whether the district court erred in awarding prejudgment interest and whether due process was violated by granting interest without an evidentiary hearing. The court held that a district court may award prejudgment interest even when it is not the trier of fact, as prejudgment interest is a matter of law and not fact. The court found the claim was liquidated and the Ropkens had notice. The court also held that the Ropkens received adequate notice and opportunity to be heard, satisfying due process. The Supreme Court of Wyoming affirmed the award of prejudgment interest. View "Ropken v. Yj Construction, Inc." on Justia Law
Design Gaps, Inc. v. Distinctive Design & Construction LLC
A dispute arose from the design and installation of cabinetry in a luxury home in Charleston, South Carolina. Design Gaps, Inc., owned by David and Eva Glover, had a longstanding business relationship with Shelter, LLC, a general contractor operated by Ryan and Jenny Butler. After being dissatisfied with Design Gaps’ performance, the homeowners, Dr. Jason and Kacie Highsmith, and Shelter terminated their contract with Design Gaps and hired Distinctive Design & Construction LLC, owned by Bryan and Wendy Reiss, to complete the work. The Highsmiths and Shelter initiated arbitration against Design Gaps, which led to the arbitrator ruling in favor of the homeowners and Shelter on their claims, and against Design Gaps on its counterclaims, including those for copyright infringement, tortious interference, and unfair trade practices.After the arbitration, Design Gaps sought to vacate the arbitration award in the United States District Court for the District of South Carolina, but the court instead confirmed the award. Concurrently, Design Gaps filed a separate federal lawsuit against several parties, including some who were not part of the arbitration. The defendants moved to dismiss, arguing that res judicata and collateral estoppel barred the new claims, or alternatively, that the claims failed on other grounds such as the statute of limitations and laches. The district court agreed, dismissing most claims based on preclusion or other legal bars, and granted summary judgment on the remaining claims.The United States Court of Appeals for the Fourth Circuit reviewed the district court’s decisions. The court held that res judicata and collateral estoppel applied to bar most of Design Gaps’ claims, even against parties not directly involved in the arbitration but in privity with those who were. For the remaining claims, the court found they were properly dismissed on grounds such as the statute of limitations, waiver, or laches. The Fourth Circuit affirmed the district court’s judgment in full. View "Design Gaps, Inc. v. Distinctive Design & Construction LLC" on Justia Law
RTI, LLC v. Pro Engineering
RTI, LLC and RTI Holdings, LLC sought to construct a specialized clinical research facility in Brookings, South Dakota, designed for animal health research trials with stringent air filtration and ventilation requirements. Acting as the general contractor, RTI hired designArc Group, Inc. as architect and several contractors, including Pro Engineering, Inc., Ekern Home Equipment Company, FM Acoustical Tile, Inc., and Trane U.S. Inc., to design and build the facility. After completion in April 2016, RTI experienced significant issues with air pressure, ventilation, and ceiling integrity, leading to contamination problems that disrupted research and resulted in financial losses.The Circuit Court of the Third Judicial Circuit, Brookings County, reviewed RTI’s claims for breach of contract and breach of implied warranties against the architect and contractors. All defendants moved for summary judgment, arguing that RTI’s claims were based on professional negligence and required expert testimony, which RTI failed to provide. The circuit court agreed, finding RTI’s CEO unqualified as an expert, and granted summary judgment to all defendants. The court also denied RTI’s motion to amend its complaint to add negligence claims, deeming the amendment untimely and futile due to the lack of expert testimony.The Supreme Court of the State of South Dakota affirmed the summary judgment for designArc, Pro Engineering, and FM Acoustical, holding that expert testimony was required for claims involving specialized design and construction issues, and that RTI’s CEO was not qualified to provide such testimony. However, the court reversed the summary judgment for Trane and Ekern, finding genuine issues of material fact regarding Trane’s alleged faulty installation and Ekern’s potential vicarious liability. The court also reversed the denial of RTI’s motion to amend the complaint, concluding the proposed amendments were not futile and would not prejudice Trane or Ekern. The case was remanded for further proceedings. View "RTI, LLC v. Pro Engineering" on Justia Law
Yoder v. McCarthy Const.
An employee of a roofing subcontractor was severely injured after falling through an uncovered hole while working on a library roof replacement project. The general contractor had contracted with the property owner to perform the roof work and then subcontracted the roofing portion to the injured worker’s employer. The injured worker received workers’ compensation benefits from his direct employer and subsequently filed a negligence lawsuit against the general contractor, seeking damages for his injuries.In the Philadelphia County Court of Common Pleas, the general contractor asserted statutory employer immunity under Pennsylvania’s Workers’ Compensation Act, arguing it was immune from tort liability as a statutory employer. The trial court struck the general contractor’s answer and new matter as untimely and granted the injured worker’s motion to preclude the statutory employer defense at trial. The case proceeded to a jury, which found the general contractor negligent and awarded $5 million to the plaintiff. The trial court denied the general contractor’s post-trial motion for judgment notwithstanding the verdict.On appeal, the Pennsylvania Superior Court vacated the trial court’s judgment and remanded for entry of judgment in favor of the general contractor. The Superior Court held that the general contractor was the injured worker’s statutory employer and thus immune from tort liability, finding all elements of the statutory employer test satisfied and that the defense was not waivable.The Supreme Court of Pennsylvania reviewed whether to overrule prior precedent (Fonner and LeFlar) regarding statutory employer immunity and waiver, and whether the Superior Court properly applied the statutory employer test. The Supreme Court reaffirmed its prior holdings that a general contractor’s statutory employer immunity does not depend on actual payment of workers’ compensation benefits and that the defense is jurisdictional and not waivable. However, it found the Superior Court erred by exceeding its scope of review and remanded the case to the trial court to determine, after appropriate proceedings, whether the general contractor satisfied the disputed elements of the statutory employer test. View "Yoder v. McCarthy Const." on Justia Law
Nordic PCL Construction, Inc. v. LPIHGC, LLC
A dispute arose between two companies, one a contractor and the other a developer, over a construction project in Maui. The disagreement was submitted to binding arbitration, resulting in an award in favor of the developer. The developer sought to confirm the award in the Circuit Court of the First Circuit, but the contractor challenged the award, alleging the arbitrator was evidently partial due to undisclosed relationships. The circuit court initially confirmed the award, but on appeal, the Supreme Court of Hawai‘i remanded the case for an evidentiary hearing on the partiality claim. After the hearing, the circuit court found evident partiality, denied confirmation, vacated the award, and ordered a rehearing before a new arbitrator.Following this, the contractor moved for taxation of costs incurred on appeal, which the circuit court granted. The developer sought to appeal the costs order, but the circuit court denied an interlocutory appeal. A new arbitration was held, again resulting in an award for the developer, which was confirmed in a new special proceeding with a final judgment entered. The developer then appealed the earlier costs order from the first special proceeding.The Intermediate Court of Appeals (ICA) dismissed the appeal as untimely, reasoning that the circuit court’s order vacating the first arbitration award and ordering a rehearing was an appealable final order under Hawai‘i Revised Statutes (HRS) § 658A-28(a)(3), making the subsequent costs order also immediately appealable.The Supreme Court of Hawai‘i reviewed the case and held that an order vacating an arbitration award and directing a rehearing is not an appealable order under HRS § 658A-28(a). The court clarified that such orders lack finality, regardless of whether the rehearing is full or partial, and reaffirmed the majority rule previously adopted in State of Hawaii Organization of Police Officers (SHOPO) v. County of Kauai. The Supreme Court vacated the ICA’s dismissal and remanded the case for entry of a final judgment, so the merits of the appeal could be addressed. View "Nordic PCL Construction, Inc. v. LPIHGC, LLC" on Justia Law
PeakCM, LLC v. Mountainview Metal Systems, LLC
A general contractor was hired to oversee the construction of a hotel in Vermont and subcontracted with a firm to install metal siding panels manufactured by a third party. The subcontractor relied on installation instructions available on the manufacturer’s website, which did not specify the use of a splice plate to connect the panels. The panels were installed without splice plates, and after construction, the panels began to detach from the building, causing some to fall and damage nearby property. The contractor later discovered that the manufacturer had created an instruction sheet in 2006 recommending splice plates, but this information was not publicly available at the time of installation.The contractor initially sued the installer for breach of contract, warranty, and negligence in the Vermont Superior Court, Chittenden Unit, Civil Division. The complaint was later amended to add a product liability claim against the manufacturer. After further discovery, the contractor sought to amend the complaint a third time to add new claims against the manufacturer, arguing that new evidence justified the amendment. The trial court denied this motion, citing undue delay and prejudice to the manufacturer, and granted summary judgment to the manufacturer on the product liability claim and on a crossclaim for implied indemnity brought by the installer, finding both barred by the economic-loss rule.On appeal, the Vermont Supreme Court affirmed the trial court’s decisions. The Court held that the trial court did not abuse its discretion in denying the third motion to amend due to undue delay and prejudice. It also held that the economic-loss rule barred the contractor’s product liability claim, as neither the “other-property” nor “special-relationship” exceptions applied. Finally, the Court found the contractor lacked standing to appeal the summary judgment on the installer’s implied indemnity claim. View "PeakCM, LLC v. Mountainview Metal Systems, LLC" on Justia Law
Johnson v. Albin Carlson & Co.
A contractor hired a subcontractor to work on a remote bridge construction project. The scope of the work changed, and neither party kept detailed records of the changes and associated costs. Years after the project was completed, the subcontractor sued for damages, claiming unpaid work. The superior court found that the subcontract did not govern the extra work, awarded some damages to the subcontractor, and precluded some claims due to discovery violations. The court also found the contractor to be the prevailing party and awarded attorney’s fees. Both parties appealed.The superior court denied summary judgment motions from both parties, finding factual disputes. It precluded the subcontractor from pursuing certain damages claims due to insufficient documentation but allowed evidence for contingent findings. After a bench trial, the court awarded the subcontractor $191,443.42, later reduced to $146,693.42 upon reconsideration. The court found the contractor to be the prevailing party under Rule 68 and awarded attorney’s fees.The Supreme Court of Alaska reviewed the case. It concluded that the superior court abused its discretion by precluding the subcontractor’s claims for snowmachine use and labor without considering less severe sanctions. The court affirmed the superior court’s findings on other damages but reversed the awards for Morris Johnson’s labor and boat use, remanding for recalculation. The prevailing party determination and attorney’s fee award were vacated and remanded for reconsideration. The court otherwise affirmed the superior court’s judgment. View "Johnson v. Albin Carlson & Co." on Justia Law