Justia Construction Law Opinion Summaries

Articles Posted in Business Law
by
This dispute arose from the construction of a commercial building. Before the property was purchased, Respondent Bryan Causey hired GS2 Engineering and Environmental Consulting, Inc. (GS2) to perform an engineering analysis of the soils on the property to determine whether the land was suitable for construction. Causey formed Causey Consulting, LLC (of which he was the sole member), and Causey Consulting purchased the property to construct the commercial building. Appellant Crouch Construction Company was retained as the general contractor. The parties' dispute began over the amount of unsuitable soils excavated from the building site: during construction, it became apparent that more unsuitable soil needed to be removed than was initially anticipated, and the removal of additional soil increased the cost of the project. The construction project was substantially completed then occupied by Respondent Celebrations of Columbia, LLC, of which Causey is also a member. When Appellant did not receive final payment for the work, it filed a mechanic's lien and a suit to foreclose the lien. The circuit court ordered arbitration pursuant to an arbitration clause in the construction contract. The arbitrator determined Appellant was owed money under the contract, plus interest, attorney's fees and costs. Respondents moved to vacate the award, seeking to have it set aside based on several unfavorable evidentiary rulings and general allegations that the arbitrator manifestly disregarded the law. The circuit court denied Respondents' motion. However, before an order was entered, Respondents learned that an engineer employed by GS2 was the brother of one of the arbitrator's law partners. Respondents filed a supplemental motion to vacate the arbitration award, reiterating their previous arguments and raising several new claims, citing the arbitrator's failure to disclose his law partner's relationship with an employee of GS2. The circuit court found that vacatur was warranted, and , the circuit court held the award should be set aside. Upon review, the Supreme Court concluded that the arbitrator was not evidently partial towards GS2 or either party. Accordingly, the Court reversed and remanded the case to the circuit court for confirmation of the arbitration award.View "Crouch Construction v. Causey" on Justia Law

by
At the heart of this case was a dispute between developer, Birchwood Land Company, Inc., and contractor, Ormond Bushey & Sons, Inc. over a construction contract.  The developer sued for breach of contract, claiming mainly that the contractor had removed excavated sand from the construction site without permission.  The contractor counterclaimed for amounts due under the contract. The court found that the contractor breached the contract and granted the developer damages for the lost sand. The unpaid balance owed on the contract was offset by the damages. On appeal, the contractor argued that the court erred in denying its request for interest penalties and attorney's fees as the substantially prevailing party. The developer argued that the court erred in limiting damages for the sand removal, denying its request for punitive damages, granting prejudgment interest on contractor's net recovery, and denying its claim for slander of title. Upon review, the Supreme Court concluded the evidence in the record supported the trial court's judgment in this case and affirmed the outcome.View "Birchwood Land Company, Inc. v. Ormond Bushey & Sons, Inc." on Justia Law

by
The issue before the Supreme Court centered on the grant of summary judgment in favor of Respondent Action Concrete Contractors, Inc. in a mechanic's lien foreclosure action. Owners Elvira Chappelear, Craig Chappelear, Premier Southern Homes, LLC, Henry G. Beal, Jr. and First Citizens Bank and Trust Co., Inc. argued on appeal there were material issues of fact and that the grant of summary judgment was inappropriate. The Supreme Court disagreed after its review of the trial court record and affirmed. View "Action Concrete v. Chappelear" on Justia Law

by
This litigation stemmed from a dispute over monies allegedly owed to a now-defunct corporation for work performed as part of a construction project that took place in 1990. Plaintiff corporation instituted suit about twenty-two years ago. Seventeen years later, the superior court dismissed the action, finding that Plaintiff could neither maintain the action in its own name nor substitute another entity as Plaintiff. The Supreme Court affirmed, holding that, as a defunct corporation, Plaintiff could no longer maintain this action in its own name, and because the receiver was discharged when Plaintiff was dissolved, the receiver could not maintain the action on its behalf. View "Piccoli & Sons, Inc. v. E & C Constr. Co., Inc." on Justia Law

by
This case arose out of several business transactions entered into by parties involved in the development of condominiums on Hauser Lake. Cherrad, Merritt & Marie, and Max & V (the Hale interests) were limited liability companies owned by Conrad and Cheryl Hale. Craig Kinnaman was sole proprietor of a business called CK Design. Merritt & Marie purchased the Hauser Lake property. Subsequently, the Hales and Kinnaman agreed to develop a portion of the property. Cherrad was the developer, and Mountain West Bank (MWB) made three loans to Cherrad to develop the project. CK Design suffered delays in the project and later left the project. In 2007, Kinnaman committed suicide, and the Estate recorded a $3.3 million construction lien on the condominiums. MWB brought this action 2008 against the Hale interests and the Estate seeking foreclosure on the three secured loans. The Hale interests and the Estate cross-claimed against each other. The district court (1) declared the Estate's construction lien invalid; and (2) determined Cherrad owed the Estate $76,278 for work that CK Design performed on the project. Finding no error, the Supreme Court affirmed. View "Mountain West Bank, N.A. v. Cherrad, LLC" on Justia Law

by
Kahrs imports engineered wood flooring panels for distribution to flooring wholesalers. Kahrs classified the products as “assembled parquet panels” under the Harmonized Tariff Schedule of the United States (HTSUS) subheading 4418.30.00, a duty-free provision for “Builders’ joinery and carpentry of wood, including cellular wood panels and assembled parquet panels; shingles and shakes: parquet panels.” Customs subsequently liquidated Kahrs’ merchandise under HTSUS 4412, which covers “plywood, veneered panels and similar laminated wood,” at a duty rate of eight percent ad valorem. Customs denied a protest and the Court of International Trade found that Customs correctly classified Kahrs’ merchandise as plywood under heading 4412. The Federal Circuit affirmed. View "Kahrs Int'l, Inc. v. United States" on Justia Law

by
The issue before the Supreme Court in this case concerned the grant of summary judgment dismissing an action to enforce an oral agreement to guaranty the debt of another on the ground that the agreement was barred by the statute of frauds. Sunshine Secretarial Services subleased office space from Accelerated Paving, Inc., and at times provided it with secretarial services. Accelerated Paving owed Plaintiff-Appellant Mickelsen Construction, Inc. money ($34,980.00) for providing asphalt to an Accelerated jobsite. Mickelsen threatened to file a materialmen’s lien against the real property on which the work was being done, and Accelerated's vice president asked that it not do so because that would delay the receipt of payment for the construction job. The vice president offered to pay the debt with an American Express credit card, but Mickelsen responded that it did not accept American Express credit cards. There was disagreement as to what happened next: Accelerate's vice president said there was not enough credit on the card to fund the payment, but when Accelerated received payment for the project it would pay down the balance so that there was enough credit to pay Mickelsen with the card. Mickelsen agreed not to file the lien if Accelerated could find someone to guaranty the payment by the credit card. Defendant-Respondent Lesa Horrocks of Sunshine agreed to do so and gave Mickelsen a check in the amount owed, drawn on Sunshine's account. Sunshine had a credit card machine that was capable of transacting with several credit cards including American Express credit cards. They told her that American Express had approved the transaction and asked her to use Sunshine credit card machine to run the transaction. It appeared to her that the transaction had been approved by American Express. issued the check. Several days later, Accelerated informed her that American Express had not approved the transaction. Accelerated then filed for bankruptcy. Mickelsen then sued Ms. Horrocks and Sunshine alleging that they had agreed to guaranty the credit card payment and so issued the check. The Defendants filed a motion for summary judgment, arguing that the alleged guaranty was barred by the statute of limitations in Idaho Code section 9-505. In response, Mickelsen argued that the check was a sufficient writing under the statute of frauds and, if not, that the transaction was governed by Idaho Code section 9-506 and therefore exempt from the statute of frauds. The district court held that the check was an insufficient writing and that section 9-506 did not apply because the Defendants did not receive any direct benefit. The court granted the motion for summary judgment and entered a judgment dismissing this action. Mickelsen then appealed. Finding no error with the district court's decision, the Supreme Court affirmed. View "Mickelsen Const v. Horrocks" on Justia Law

by
Defendants Stryker Biotech, LLC, Stryker Sales Corporation (collectively Stryker) and Turner Construction Company, appealed a superior court ruling which found them liable on a theory of unjust enrichment and awarded damages to the plaintiff, Axenics, Inc. f/k/a RenTec Corporation. Axenics cross-appealed, challenging the amount of damages awarded and the trial court's failure to find the defendants liable on its breach of contract and New Hampshire Consumer Protection Act (CPA) claims. This case arose from the construction of a biotech facility for Stryker for which Turner served as the general contractor. Axenics subcontracted with Turner to furnish labor, materials, equipment, and services for the installation of "process pipe" at the facility. A dispute arose when Axenics notified Turner of additional change orders related to delays and work that it believed to be outside the scope of the contract. Upon review, the Supreme Court found that the subcontract addressed the subject matter of Axenics' unjust enrichment claim. The Court reversed the trial court's decision finding Turner liable to Axenics on its theory of unjust enrichment. Furthermore, the Court found no evidence that Stryker accepted a benefit that would be unconscionable to retain. Therefore the Court held that the trial court erred in allowing Axenics to recover against Stryker under a theory of unjust enrichment. The Court found that an internal memorandum was admitted into evidence in error; the trial court erred in relying upon it in assessing damages. The Court affirmed the trial court's decision with respect to Axenics' CPA claims. The case was ultimately affirmed in part, vacated in part, and remanded for further proceedings. View "Axenics, Inc. v. Turner Construction Co." on Justia Law

by
Antelope Development LLC was formed to develop a residential subdivision in Bennett, Colorado. The LLC took out construction loans from the bank at the start of the project; before it was finished, the LLC had exhausted its financing. The LLC entered into oral agreements with Respondent AC Excavating for work on the subdivision. AC Excavating was paid for some but not all of its work. Petitioner Donald Yale, a member of the LLC, realized that the LLC had insufficient funds to meet its obligations, so he placed some of his own money in the LLC's bank account. Yale then applied these funds to the LLC's general business expenses and some outstanding subcontractor invoices. AC Excavating still was not paid in full. AC Excavating sued Yale alleging, among other things, that the LLC had violated Colorado's construction trust fund statute by failing to hold the funds in the LLC's bank account in trust for payment to AC Excavating. AC Excavating further alleged that Yale thereby committed theft, permitting it to claim treble damages and attorney fees under the state Rights in Stolen Property statute. The trial court ruled in favor of Yale, and AC Excavating appealed. The appellate court reversed. Upon review, the Supreme Court held that the LLC member's voluntary injection of capital into the company did not constitute "funds disbursed to a contractor . . . on a construction project" under the construction trust fund statute, as that money was not required to be held in trust. The Court also concluded the appellate court erred in remanding the case for a determination of whether Yale was civilly liable for theft under the Rights in Stolen Property statute. View "Yale v. AC Excavating, Inc." on Justia Law

by
H. Gordon Myrick, Inc. (Myrick) contracted with Harrison County Commercial Lot (HCCL) to build HCCL an executive office building. The parties' contract contained an arbitration provision, which excluded aesthetic-effect claims from arbitration. The issue before the Supreme Court in this case concerned which, if any, of the parties' claims were subject to arbitration. The trial court determined that the arbitration agreement was valid and ordered arbitration on designated, nonaesthetic claims. HCCL appealed and Myrick cross-appealed. Upon review, the Supreme Court found that the parties' claims were without merit, "but it is difficult to determine why the trial court ordered certain punch-list items to arbitration and others not. Thus, [the Court] remand[ed the case] to the trial court to provide further explanation on the punch-list items alone." View "Harrison County Commercial Lot, LLC v. H. Gordon Myrick, Inc." on Justia Law