The federal United States District Court for the Middle District of Georgia certified questions of Georgia law to the Georgia Supreme Court regarding the scope of the “acceptance doctrine” in negligent construction tort cases. At issue was whether and how the acceptance doctrine applied as a defense against a claim brought by a subsequent purchaser of allegedly negligently constructed buildings. Thomaston Crossing, LLC (the “original owner”) entered into a construction contract with appellee Piedmont Construction Group, Inc. to build an apartment complex in Macon. Piedmont then retained two subcontractors – appellees Alan Frank Roofing Company and Triad Mechanical Company, Inc. – to construct the roof and the HVAC system, respectively. In 2014, the complex was completed, turned over to, and accepted by the original owner. In 2016, the original owner sold the apartment complex to appellant Thomaston Acquisition, LLC (“Thomaston”) pursuant to an “as is” agreement. Shortly after the sale, Thomaston allegedly discovered evidence that the roof and HVAC system had been negligently constructed. Thomaston filed suit against Piedmont, asserting a claim for negligent construction of the roof and HVAC system and a claim for breach of contract/implied warranty. Piedmont then filed a third-party complaint against Alan Frank Roofing and Triad Mechanical because both companies had allegedly agreed to indemnify Piedmont for loses arising out of their work. Each of the appellees later moved for summary judgment based in part on the defense that Thomaston’s negligent construction claim is barred by the acceptance doctrine. The Georgia Supreme Court concluded the acceptance doctrine applied to Thomaston’s claim, and that “readily observable upon reasonable inspection” referred to the original owner’s inspection. “Without any real claim of privity, Thomaston nevertheless contends that it should be treated like the original owner because it is the current owner-occupier of the property. But doing so would undermine the acceptance doctrine’s foundational purpose of shielding contractors from liability for injuries occurring after the owner has accepted the completed work, thereby assuming responsibility for future injuries. There is no ‘current owner-occupier’ or ‘subsequent purchaser’ exception to the acceptance doctrine, and the facts of this case do not compel us to recognize one here.” View "Thomaston Acquisition, LLC v. Piedmont Construction Group, Inc." on Justia Law

by
Appellants, Sorokine and Koudriavtseva, are husband and wife. DBS and Kornach are California licensed contractors; DBS worked on their San Rafael house, while Kornach did not. Kornach, a longtime friend of Sorokine’s, had purchased materials for DIY projects at the property because of the discounts afforded to licensed general contractors. Sorokine does not speak English; Kornach often interpreted for Sorokine. After Koudriavtseva fired DBS, she hired unlicensed builders to complete the work and remedy alleged defects. DBS sued, alleging breach of contract and foreclosure of mechanic’s lien. Appellants’ response named as cross-defendants DBS, Komach, and ACIC, which had issued a surety bond to Kornach. The court of appeal reversed a directed verdict against appellants on a claim they violated an Internal Revenue Code provision and awarding $20,000 in sanctions and $122,995 in attorney fees against them. There was no evidence that appellants knew that 1099s issued to Komach were incorrect. The court also reversed directed verdicts against appellants on claims they had asserted against others; appellants were unable to prove damage because the trial court had granted a motion in limine preventing appellants from introducing evidence of payments made to an unlicensed contractor. The court also reversed an award of cost of proof damages to Kornach based on requests for admissions propounded by a different party. View "Design Built Systems v. Sorokine" on Justia Law

by
Land Holdings I, LLC, d/b/a Scarlet Pearl, LLC (“Casino”), sought to expunge a lien filed by GSI Services, LLC (“GSI”). The chancellor denied the Casino’s petition to expunge the lien because GSI performed work at the Casino within ninety days of filing its lien. Finding no error, the Mississippi Supreme Court affirmed the chancellor’s order. View "Land Holdings I, LLC d/b/a Scarlet Pearl, LLC v. GSI Services, LLC" on Justia Law

by
The Court of Appeal affirmed the trial court's judgment denying Acco's petition for writ of mandamus seeking review of an administrative decision adopted by the Registrar, finding Acco in violation of Business and Professions Code section 7110 for failing to obtain a building permit before replacing a boiler. The court held that the Legislature's use of the term "willful" in section 7110 only requires a showing of general intent. The court also held that there was substantial evidence to support the Administrative Judge's determination that Acco willfully violated the applicable building laws. The court noted that the fact that an individual employee may not have been aware of a specific local permit requirement does not excuse a corporate licensee from complying with the building laws. View "Acco Engineered Systems v. Contractors' State License Board" on Justia Law

by
Plaintiffs Travelers Property Casualty Company of America, the Travelers Indemnity Company of Connecticut, and St. Paul Fire and Marine Insurance Company (collectively, Travelers) filed this action against certain subcontractors to recover attorneys’ fees and costs Travelers incurred in defending developers Westlake Villas, LLC and Meer Capital Partners, LLC (collectively, Westlake) in a prior construction defect action. Travelers' claims were based on alleged subrogation to the rights of its additional insured, Westlake. The Westlake entities were suspended corporations under Revenue and Taxation Code section 23301, and could not assert these claims on their own behalf. Defendant Engel Insulation, Inc. moved for judgment on the pleadings on the basis that Travelers was also barred under this statute from prosecuting these claims. On appeal, Travelers contended the trial court erred in granting Engel’s motion without leave to amend. The Court of Appeal disagreed: an insurer could not file its own action to assert claims solely as a subrogee of a suspended corporation. View "Travelers Property Casualty Co. of Amer. v. Engel Insulation, Inc." on Justia Law

by
Several carpenters, including one single-member LLC, an installer of cement siding, and a painter contended they were employees of Bourbeau Custom Homes, Inc. for the purposes of Vermont’s unemployment compensation system. Bourbeau challenged that classification, contending that it was not liable for unemployment taxes on monies paid to a carpenter operating as a single-member LLC because an LLC was not an “individual” under the unemployment tax statute and therefore not subject to the ABC test established by 21 V.S.A. 1301(6)(B). Second, Bourbeau argued the Employment Security Board erred in applying the ABC test with respect to all of the workers whose remuneration is the subject of this appeal. The Vermont Supreme Court agreed with Bourbeau on the first point and held that an LLC was not an “individual” for the purposes of assessing unemployment taxes. However, the Court affirmed the Board’s determination that the remaining four individuals were employees for purposes of Vermont’s unemployment compensation system. View "In re Bourbeau Custom Homes, Inc." on Justia Law

by
Phoenix Pipeline filed a second amended complaint (SAC) alleging breach of contract claims related to SpaceX's failure to pay for its services from 2010 to October 2013. The trial court subsequently granted SpaceX's demurrer, which argued that the license issued to Phoenix Plumbing was not sufficient to satisfy the requirements of Business Code section 7031. The Court of Appeal held that Phoenix Pipeline's SAC failed to state a claim for construction related services because it did not allege that Phoenix Pipeline was a licensed contractor. The court explained that Phoenix Pipeline may not rely upon a license issued to another and that section 7031 was not limited to contracts with unsophisticated persons or homeowners. The court held, however, that Phoenix Pipeline adequately alleged that it provided some services for which no contractor license was necessary. Finally, the trial court acted within its discretion in declining to permit an amendment alleging that Phoenix Pipeline was an employee. Accordingly, the court reversed and remanded. View "Phoenix Mechanical Pipeline, Inc. v. Space Exploration Technologies Corp." on Justia Law

by
When this case came before the Mississippi Supreme Court on interlocutory appeal, the Court reversed in part. Because it was undisputed that neither sub-subcontractor Ground Control, LLC nor subcontractor Capsco Industries, Inc. (both Alabama companies) had a statutorily required certificate of responsibility to work in Mississippi, the Court agreed that the subcontract was void. But the Court found, despite the void contract, "Ground Control should not be precluded from having the opportunity to proceed in court under a claim for the value of what it expended in labor and supplies on the project." The case was remanded to the trial court so Ground Control could pursue the nonbarred "claims of unjust enrichment and quantum meruit." Despite this holding, Ground Control argued in this appeal that the trial court erred by limiting its claims on remand to unjust enrichment and quantum meruit. The Supreme Court found no error in the trial court so limiting Ground Control's claims. The Supreme Court did, however, find W.G. Yates and Sons Construction Company (Yates) and Capsco raised reversible errors in their cross-appeals. Based on the evidence presented at trial, the Supreme Court found Yates was entitled to a directed verdict because Ground Control failed to prove Yates’s liability for quantum meruit damages. The Court also found the quantum meruit damages award against Capsco was against the overwhelming weight of the evidence. Consequently, Capsco was entitled to a remittitur. The Court affirmed on Ground Control’s and Ground Control owner Frank Beaton’s direct appeals. On cross-appeal, the Court reversed a $36,644.69 judgment against Yates and rendered a judgment in Yates’s favor. The Court also reversed a $825,583.31 judgment against Capsco. The quantum meruit claim against Capsco was remanded, instructing the trial court to conduct a new trial on damages alone, unless a remittitur of $626,407.31, making the damage award $199,096, was accepted by Ground Control and Capsco. View "Ground Control, LLC v. Capsco Industries, Inc." on Justia Law

by
Rick Snider and Janan Snider, doing business as RJ Snider Construction ("Snider"), appealed the grant of summary judgment, forfeiting a construction lien against the property that formerly housed the Dickinson Elks Lodge later owned by private investors, the Dickinson Elks Building, LLC ("DEB"), and prohibiting Snider from recording additional liens against the property without performing additional work. The North Dakota Supreme Court was not convinced that perfecting a lien amounted to creating a lien, as argued by the Sniders. As such, the Court concluded that when a Court declares a lien is deemed forfeited or satisfied, the right to the lien for the construction services or materials provided is deemed forfeited, not just the document recording the lien and establishing its priority. The district court correctly interpreted N.D.C.C. 35-27-25 in concluding the statute barred Snider from recording another construction lien against DEB's property for the same work. The district court also correctly concluded Snider forfeited its construction lien created and attached as a matter of law under N.D.C.C. sections 35-27-02 and 35-27-03 when it failed to comply with DEB's demand to enforce the lien. View "Snider v. Dickinson Elks Building, LLC" on Justia Law

by
This litigation arose from the construction of a "Johnny Janosik" furniture store in Laurel. The Plaintiff-appellant LTL Acres Limited Partnership (LTL) was the owner of the Janosik Building. Defendant-appellee Butler Manufacturing Company (Butler) provided pre-engineered components which were used to build the roof and exterior walls. Defendant-appellee Dryvit Systems, Inc. (Dryvit) supplied a product used on the exterior finish of the walls, to protect and seal them. Dryvit warranted its product for ten years from the "date of substantial completion of the project." The building was completed in 2006. Unfortunately, the building had issues with water infiltration from the beginning. By February 2012, cladding began to crack and buckle. The water infiltration and delamination persisted through 2013 despite attempts to fix the issues. LTL brought this action in 2013, alleging breach of warranty, breach of contract, and negligence claims against Butler; and breach of warranty and breach of contract claims against Dryvit. The Superior Court granted summary judgment to both Butler and Dryvit on the grounds that the actions against both were barred by the applicable statute of limitations. It held that the action against Butler was barred by 10 Del. C. sec. 8127,which is a six year statute of limitations relating to alleged defective construction of an improvement to real property. After review, the Supreme Court concluded that summary judgment in favor of Butler was proper. The Superior Court ruled that LTL’s action against Dryvit was barred by a four year statute of limitations set forth in 6 Del. C. sec. 2-725. Dryvit gave LTL a ten year express warranty. The Superior Court described the warranty as a “repair and replacement warranty” and reasoned that such a warranty cannot be one that extended to future performance. It therefore concluded that the statute of limitations for an action on the warranty expired not later than four years after the Dryvit product was tendered and applied to the building; that is, not later than four years after 2006. The Supreme Court concluded that grant of summary judgment in favor of Dryvit was inappropriate, and had to be reversed. The case was remanded for further proceedings. View "LTL Acres Limited Partnership v. Butler Manufacturing Co." on Justia Law