Justia Construction Law Opinion Summaries

Articles Posted in Banking
by
Tender Care Veterinary Hospital, Inc. ("TCVH"), appealed the grant of summary judgment entered in favor of First Tuskegee Bank on breach-of-fiduciary-duty and fraud claims stemming from a construction loan TCVH received from First Tuskegee in September 2004. The gravamen of those claims was that TCVH was injured by First Tuskegee's alleged insistence that TCVH use PJ Construction as the general contractor on the project although PJ Construction was not licensed as a general contractor in Alabama, that PJ Construction's work product was below what one would expect from a properly licensed general contractor, and that using PJ Construction resulted in delays, cost overruns, and, TCVH argued, the ultimate failure of its business. However, because TCVH's claims accrued in approximately July 2005 and TCVH did not formally assert them until after it initiated this action in April 2009, those claims were barred by the two-year statute of limitations that governed them. Accordingly, the summary judgment entered by the trial court in favor of First Tuskegee was affirmed. View "Tender Care Veterinary Hospital, Inc. v. First Tuskegee Bank " on Justia Law

by
Construction Manager subcontracted with Subcontractor to do work on a construction project. After the project was substantially complete, Subcontractor recorded a mechanic’s lien for unpaid work on the project. Subcontractor then filed a complaint against Construction Manager as the general contractor of the project, the owner of the property (Landowner), and the bank that financed the project (Bank) to enforce its mechanic’s lien. Construction Manager did not enter an appearance in the case. The circuit court subsequently granted an application filed by Landowner and Bank and released the real estate that had been subject to Subcontractor’s mechanic’s lien. Bank filed a motion to dismiss the mechanic’s lien claim on the basis that Subcontractor failed to timely serve Construction Manager, who it alleged to be a necessary party to the mechanic’s lien enforcement action. The circuit court agreed and dismissed the mechanic’s lien claim with prejudice. The Supreme Court reversed, holding that Construction Manager, as the general contractor, was not a necessary party to Subcontractor’s mechanic’s lien enforcement action. Remanded. View "Synchronized Constr. Servs., Inc. v. Prav Lodging, LLC" on Justia Law

by
Debtors contracted with Builder to finish construction on a house. After Debtors defaulted on progress payments, Builder sued Debtors and Bank, claiming that Defendants falsely represented or concealed material information about whether Debtors could pay for the work. The district court sustained Defendants’ motions for summary judgment on Builder’s fraud and conspiracy claims. Debtors then confessed judgment on Builder’s breach of contract claim. After a bench trial, the district court ruled for Defendants on Builder’s equitable and promissory estoppel claims. The Supreme Court affirmed in part and reversed in part, holding (1) the court erred in granting summary judgment to Debtors on Builder’s fraud claim and to Debtors and Bank on Builder’s civil conspiracy claim; and (2) during trial, the court did not err in finding that Builder had failed to prove by clear and convincing evidence that Bank promised to fund Builder’s work that was definite enough to induce Builder’s foreseeable reliance on the statement, but these factual findings did not preclude Builder’s proof of the same facts for its fraud claims. Remanded. View "deNourie & Youst Homes, LLC v. Frost" on Justia Law

by
Developer obtained a loan from Bank to construct a commercial and condominium project. Bank secured its loan with two deeds of trust, the first of which attached before construction began on the project. Developer failed to pay the general contractor (Contractor) several million dollars for the project, and after Developer had sold many of the units, Contractor recorded a mechanics’ lien against the project. Contractor then sought to foreclose on its lien against Developer, the unit owners, and their lenders. The Owners and Lenders contested the foreclosure, arguing that they were equitably subrogated to Bank’s first deed of trust and thus had priority over Contractor’s mechanics’ lien. The trial court concluded that Contractor’s lien had priority. The Supreme Court reversed, holding (1) Ariz. Rev. Stat. 33-992(A), which gives mechanics’ liens priority over liens recorded after construction begins on real property, does not preclude assignment by equitable subrogation of lien that attached before construction began on the project; and (2) when a single mortgage burdens multiple parcels, a third party may be entitled to equitable subrogation when that party has paid a pro rata amount of the obligation and obtained a full release of the parcel at issue from the mortgage. Remanded. View "Weitz Co., LLC v. Heth" on Justia Law

by
Downing, Thorpe & James Design, Inc. (DTJ) was an architectural firm incorporated in Colorado. Thomas Thrope, one of DTJ’s three founding principals, was allowed to practice individually as a foreign architect in Nevada, but DTJ was not allowed to practice as a foreign corporation in Nevada. In 2004, DTJ contracted with a Nevada developer to provide architectural services for a Las Vegas subdivision owned by Prima Condominiums, LLC (Prima). Prima obtained a loan from First Republic Bank in exchange for a promissory note secured by a deed of trust on one of the subdivision’s units. After Prima defaulted on its payments, DTJ recorded a notice of mechanic’s lien against the property for unpaid services. First Republic then foreclosed and purchased the property. DTJ subsequently brought an action against First Republic for lien priority and unjust enrichment. The district court granted summary judgment for First Republic. The Supreme Court affirmed, holding (1) because DTJ had failed to comply with Nevada’s statutory registration and filing provisions, it was barred from maintaining an action in Nevada for compensation for its architectural services; and (2) Thorpe’s individual status had no bearing on whether DTJ could bring or maintain an action for compensation for its services.View "DTJ Design, Inc. v. First Republic Bank" on Justia Law

by
Mark Hilde hired Big Lake Lumber (Big Lake), Wruck Excavating (Wruck), and J. DesMarais Construction (DesMarais) to help him build a "spec home." 21st Century Bank (Bank) recorded a mortgage against the property to finance the purchase of the property and the home construction. After the Bank foreclosed on its mortgage, Big Lake commenced this mechanic's lien foreclosure action. The district court found that the mechanic's liens of Big Lake and DesMarais related back to the date Wruck commenced work on the improvement project, and thus, the mechanic's liens of Big Lake and DesMarais had priority over the mortgage of the Bank. The court of appeals reversed. The Supreme Court reversed, holding (1) the court of appeals erred by adopting and then applying a new "integrated analysis" to find the Bank's mortgage superior to the liens; and (2) the district court did not clearly err when it found that Wruck, Big Lake, and DesMarais contributed to the same project of improvement, and accordingly, under the relation-back doctrine, the mechanic's liens of Big Lake and DesMarais had priority over the Bank's mortgage.View "Big Lake Lumber, Inc. v. Sec. Prop. Invs., Inc." on Justia Law

by
At the heart of this appeal was a mechanic's lien filed against the Black Rock North Development in Coeur d?Alene, Idaho, and an uncompleted golf course community development. American Bank (the Bank) was the lender to BRN Development, Inc. (BRN). BRN hired Wadsworth Golf Construction Company of the Southwest (Wadsworth) to construct a golf course. BRN failed to pay Wadsworth for a portion of the work it performed, and Wadsworth filed a mechanic's lien against the property. BRN defaulted on the loan, and the Bank initiated foreclosure proceedings. Wadsworth's claim of lien was subordinate to the Bank's mortgage interest in the property. In order to proceed with a foreclosure sale, the Bank posted a lien release bond in order to secure the district court's order releasing Wadsworth's lien. The Bank was the successful bidder at the foreclosure sale. The district court ruled that priority of the parties? claims against the property was irrelevant once the property was replaced by the lien release bond as security for Wadsworth's claim and the Bank (by way of the bond) was responsible for payment of Wadsworth's lien claim. The Bank appeals that decision, arguing that Wadsworth should have been prevented from recovering against the lien release bond because its interest would have been extinguished if it had attempted to foreclose its mechanic's lien and the bond merely served as substitute security in place of the property. Wadsworth cross-appealed, arguing the district court erred in holding that Wadsworth waived its right to file a lien for the unpaid retainage on the contract. Upon review, the Supreme Court reversed the district court allowing Wadsworth to recover against the lien release bond and vacated the district court's judgment in favor of Wadsworth. View "Americn Bank v. Wadsworth Golf" on Justia Law

by
ROK Builders LLC (ROK) constructed a hotel for Moultonborough and had a mechanic's lien on the property. 2010-1 SFG Venture LLC (SFG) was the assignee of the construction lender and had a mortgage on the hotel. After Moultonborough filed for bankruptcy, SFG initiated an adversary proceeding against ROK in bankruptcy court, seeking a declaration that its mortgage was senior to ROK's lien to the extent the construction lender had disbursed loan funds to ROK. ROK, in turn, asserted that its lien was senior to SFG's mortgage. The New Hampshire bankruptcy court and district court entered judgment in favor of SFG. The First Circuit Court of Appeals affirmed, holding that the bankruptcy court did not err in concluding that N.H. Rev. Stat. Ann. 447:12-a established the seniority of SFG's mortgage over ROK's mechanic's lien to the extent of the amount of money the construction lender disbursed to ROK. View "ROK Builders, LLC v. 2010-1 SFG Venture, LLC" on Justia Law

by
RICS executed a note secured by a mortgage on real estate. Meanwhile, TLA entered into a contract with RICS to provide architectural and engineering services for the project and recorded two documents related to its work on the project. Subsequently, TLA filed a petition to enforce its mechanics' lien. No claimant timely entered an appearance in TLA's mechanics' lien litigation to preserve the priority of their claims. Months later, Petra purchased the note and mortgage, which had not been recorded by the previous owner. Meanwhile, the superior court entered a consent order signed by RICS and TLS in the mechanics' lien litigation. RICS subsequently conveyed the property, and the court placed the property into receivership. Petra later filed a motion to file an answer and statement of claim out of time in the mechanics' lien proceedings. The court granted the motion, thereby restoring the mortgage's priority over TLA's mechanics' lien. The property was sold to Petra through a receivership action. The Supreme Court reversed the superior court's grant of Petra's motion, thereby restoring the priority of TLA's mechanics' lien, holding that the motion justice erred in determining that Petra's failure to file a timely statement of claim was the result of "excusable neglect." View "R.I. Constr. Servs., Inc. v. Harris Mill, LLC" on Justia Law

by
This case arose out of several business transactions entered into by parties involved in the development of condominiums on Hauser Lake. Cherrad, Merritt & Marie, and Max & V (the Hale interests) were limited liability companies owned by Conrad and Cheryl Hale. Craig Kinnaman was sole proprietor of a business called CK Design. Merritt & Marie purchased the Hauser Lake property. Subsequently, the Hales and Kinnaman agreed to develop a portion of the property. Cherrad was the developer, and Mountain West Bank (MWB) made three loans to Cherrad to develop the project. CK Design suffered delays in the project and later left the project. In 2007, Kinnaman committed suicide, and the Estate recorded a $3.3 million construction lien on the condominiums. MWB brought this action 2008 against the Hale interests and the Estate seeking foreclosure on the three secured loans. The Hale interests and the Estate cross-claimed against each other. The district court (1) declared the Estate's construction lien invalid; and (2) determined Cherrad owed the Estate $76,278 for work that CK Design performed on the project. Finding no error, the Supreme Court affirmed. View "Mountain West Bank, N.A. v. Cherrad, LLC" on Justia Law