Winger Contracting Co. v. Cargill, Inc.

by
The Supreme Court affirmed the ruling of the district court holding that mechanic's liens arising from the provision of materials and labor to a lessee did not attach to the property of the lessor under the circumstances of this case and that a construction mortgage lien ultimately obtained by the owner of the land on the leasehold and property of the lessee had prior over the later-filed mechanic's liens, holding that the district court's judgment was without error.Specifically, the Court held (1) the legislature has reworked Iowa Code 572.2 to limit mechanic's liens to property belonging to a narrowly defined owner, and therefore, Denniston & Patridge Co. v. Romp, 56 N.W.2d 601 (Iowa 1953), and Stroh Corp. v. K&S Development Corp., 247 N.W.2d 750 (Iowa 1976), are no longer good law; (2) the priority of the after-acquired construction mortgage lien was not defeated by the doctrine of merger; and (3) there was no fraud under the circumstances presented. View "Winger Contracting Co. v. Cargill, Inc." on Justia Law