NOVA Contracting, Inc. v. City of Olympia

by
The City of Olympia, Washington contracted with NOVA Contracting, Inc. to replace a deteriorating culvert. The contract contained a "notice of protest" provision, which was taken from the Washington Department of Transportation's "standard Specifications for Road, Bridge, and Municipal Construction (2012) manual. NOVA sued the City for breach of the implied covenant of good faith and fair dealing; the City moved to dismiss based in part on NOVA's filature to file a protest first before taking the City to court. The trial court dismissed NOVA's claim, but the Court of Appeals reversed. The Washington Supreme Court has addressed this written notice issue twice before; the Court of Appeals interpreted those holdings, however, as only applying to claims for cost of work performed and not claims for expectancy and consequential damages. The Supreme Court held the two prior cases applied even to claims of expectancy and consequential damages. Therefore, the Court reversed the appellate court and remanded this case for further proceedings. View "NOVA Contracting, Inc. v. City of Olympia" on Justia Law