C.G. Schmidt Inc. v. Permasteelisa N. Am.

by
Using a form provided by CGS, the general contractor for construction of an 18-story Milwaukee office building, PNA submitted a $12,675,421 bid to provide a glass curtainwall--a nonstructural outer covering for weatherproofing and aesthetics. The contract manual provided by CGS stated that “[t]he bidder must accept all terms of the [standard CGS] subcontract as a condition for submitting a bid.” After CGS chose PNA’s bid, PNA repeatedly expressed a need to review the finalized prime contract before it would execute a formal subcontract. CGS and PNA engaged in a “value engineering process” during which they refined the price and other terms of the subcontract. PNA regularly updated the proposed price and communicated the updates to CGS. Several times, PNA raised concerns about subcontract terms. CGS never indicated to PNA that, in CGS’s view, there was already an agreement in place. The parties never entered into a formal subcontract. CGS had to use a different subcontractor at a higher price. CGS filed suit. The district court granted PNA summary judgment, finding that the parties did not intend to be bound until the execution of a formal subcontract. The Seventh Circuit affirmed, agreeing that the parties never entered into a binding contract and that CGS’s promissory estoppel claim fails as a matter of law. View "C.G. Schmidt Inc. v. Permasteelisa N. Am." on Justia Law