Tampa Bay Water v. HDR Engineering, Inc.

by
TBW filed suit against several defendants, including HDR Engineering and Barnard Construction Company, alleging that HDR defectively designed TBW's reservoir and that Barnard defectively constructed it. The primary issue on appeal concerned the district court's decision to allow HDR to present evidence that Barnard caused the reservoir damage. The court held that, in the procedural posture of this case, the summary judgment granted to Barnard did not directly estop HDR from introducing evidence at trial that Barnard caused the damage; the district court's admission of certain expert testimony was not manifestly erroneous or an abuse of discretion; and the district court did not abuse its discretion in denying TBW's motion for leave to amend its complaint for a second time. Accordingly, the court affirmed the judgment of the district court and denied the motion to certify. View "Tampa Bay Water v. HDR Engineering, Inc." on Justia Law