Garrity v. Conservation Comm’n of Hingham

by
The Wetlands Protection Act, G.L. c. 131, 40, requires a conservation commission to issue a decision on a requested order of conditions within 21 days after holding a public hearing on the applicant's notice of intent to perform work covered by the act. Following the owner’s request for an extension, a hearing on his application for construction of a pile-supported pier and floating dock was held on April 6; the commission voted to deny the application on April 27 and mailed notice on April 28, 22 days after the hearing. The department reversed, based on the commission’s failure to timely act. In the meantime, the commission issued an enforcement order, based on work being done on the applicant’s property. The Supreme Judicial Court held that an applicant may waive the statutory time restriction, but any waiver must be voluntary in fact, its duration defined and reasonable in length, and notice of the waiver's duration must be a matter of public record, available to all interested persons. In this case, the applicant is entitled to proceed under the order issued by the department. View "Garrity v. Conservation Comm'n of Hingham" on Justia Law