Ground Zero Constr. v. Walnut Creek, LLC

by
At issue in this appeal was whether a seventy-five-day lien notice sent by Appellant, Ground Zero Construction, to Appellees, Walnut Creek, LLC and Rees Development, complied with the requirements of Ark. Code Ann. 18-44-115(e)(2)(C)(i), which requires that the notice contain a "general description of the labor, service, or materials furnished." The lien notice was provided in connection with sums owed and unpaid for labor and materials provided to Appellees for the construction and improvements of water and sewer for a subdivision. The circuit court concluded that the notice did not comply with the materialman's statute. The Supreme Court affirmed, holding that Ground Zero's description of the labor, service, or materials furnished did not comply with the statute because Ground Zero essentially provided no description at all. View "Ground Zero Constr. v. Walnut Creek, LLC" on Justia Law