Justia Construction Law Opinion Summaries
Edgerock Development, LLC v. C.H. Garmong & Son Inc
EdgeRock Development, LLC developed a planned unit development in Westfield, Indiana, comprising retail and residential projects. EdgeRock contracted with C.H. Garmong & Son, Inc. and Fox Contractors Corp. to develop the lots. When EdgeRock fell behind on payments, Garmong and Fox recorded construction liens on all five lots, including those sold to ZPS Westfield, LLC and a nonparty. The contractors sued EdgeRock for breach of contract and sought to foreclose the liens.The Hamilton Superior Court awarded the contractors most of the relief they sought, including foreclosure of the construction liens. The Indiana Court of Appeals reversed the foreclosure, concluding the liens were overstated as they were not limited to debts for improvements directly benefiting the properties to which the liens attached.The Indiana Supreme Court reviewed the case to address the validity and scope of the construction liens and the priority between the construction liens and First Bank Richmond’s mortgage lien. The court held that a construction lien secures only the debt for improvements directly benefiting the property to which the lien attaches. Therefore, the contractors can foreclose the liens on each property to recover only those amounts. The court also concluded that First Bank’s mortgage lien is senior to the construction liens for the amount loaned to satisfy Garmong’s prior construction lien but junior for the remaining amounts.The court affirmed the trial court’s judgment in part, reversed in part, and remanded for the trial court to amend the judgment consistent with its opinion. The court also noted that its holdings do not disturb the in personam judgments against EdgeRock on Garmong’s and Fox’s breach-of-contract claims. View "Edgerock Development, LLC v. C.H. Garmong & Son Inc" on Justia Law
Cashman Equipment Corporation, Inc. v. Cardi Corporation, Inc.
Cashman Equipment Corporation, Inc. (Cashman) was contracted by Cardi Corporation, Inc. (Cardi) to construct marine cofferdams for the Sakonnet River Bridge project. Cashman then subcontracted Specialty Diving Services, Inc. (SDS) to perform underwater aspects of the cofferdam installation. Cardi identified deficiencies in the cofferdams and sought to hold Cashman responsible. Cashman believed it had fulfilled its contractual obligations and sued Cardi for breach of contract, unjust enrichment, and quantum meruit. Cardi counterclaimed, alleging deficiencies in Cashman's construction. Cashman later added SDS as a defendant, claiming breach of contract and seeking indemnity and contribution.The Superior Court denied SDS's motion for summary judgment, finding genuine disputes of material fact. The case proceeded to a jury-waived trial, after which SDS moved for judgment as a matter of law. The trial justice granted SDS's motion, finding Cashman failed to establish that SDS breached any obligations. SDS then moved for attorneys' fees, which the trial justice granted, finding Cashman's claims were unsupported by evidence and lacked justiciable issues of fact or law. The trial justice ordered mediation over attorneys' fees, resulting in a stipulated amount of $224,671.14, excluding prejudgment interest.The Rhode Island Supreme Court reviewed the case and affirmed the Superior Court's amended judgment. The Supreme Court held that the trial justice did not err in granting judgment as a matter of law, as Cashman failed to provide specific evidence of justiciable issues of fact. The Court also upheld the award of attorneys' fees, finding no abuse of discretion. Additionally, the Court determined that the attorneys' fees were not barred by the Bankruptcy Code, as they arose post-confirmation and were not contingent claims. View "Cashman Equipment Corporation, Inc. v. Cardi Corporation, Inc." on Justia Law
Flintco, LLC v Total Installation Management Specialists, Inc.
A contractor, Flintco, LLC, entered into a subcontract with Total Installation Management Specialists, Inc. (Total) for flooring work on a construction project at Oklahoma State University. Total was required to secure a performance bond from Oklahoma Surety Company (OSC). Flintco later supplemented Total's workforce due to delays and performance issues but did not notify OSC until five weeks after taking over the work.The Tulsa County District Court ruled in favor of Flintco, awarding damages against Total and OSC. OSC appealed, arguing that Flintco failed to meet the performance bond's conditions requiring a declaration of default and reasonable notice before assuming control of the work. The Court of Civil Appeals reversed the district court's judgment, finding that the notice requirement was a mandatory condition precedent, and Flintco's failure to provide timely notice relieved OSC of liability.The Supreme Court of the State of Oklahoma reviewed the case and agreed with the Court of Civil Appeals. The court held that the performance bond's notice requirement constituted a mandatory condition precedent. Flintco's failure to provide timely notice to OSC so it could exercise its performance options under the bond relieved OSC from liability. The court vacated the Court of Civil Appeals' opinion, reversed the district court's judgment, and remanded the case with instructions to enter judgment consistent with this decision. The trial court's judgments against Total were not affected by this decision. View "Flintco, LLC v Total Installation Management Specialists, Inc." on Justia Law
New Star General Contractors, Inc. v. Dumar
New Star General Contractors, Inc. (New Star) filed a lawsuit to enforce its construction lien on twelve condo units in a large development in Grand County after the developer, Sage Creek at Moab, LLC (Sage Creek), failed to pay for New Star’s construction work. The units’ owners, Dumar, LLC, and Duane Shaw (collectively, Dumar), challenged the lien on multiple grounds. The district court ruled in favor of New Star, allowing it to enforce its lien. Dumar appealed the decision.The Seventh District Court, Grand County, initially heard the case and ruled that New Star could enforce its lien. The court found that New Star’s preliminary notices were sufficient and that the lien was valid despite New Star’s failure to allocate expenses between the units and the common areas. The court also concluded that Dumar was responsible for the full amount of the lien, which included the costs of constructing Building C and its common areas. Dumar’s excessive lien claim was dismissed, and the court awarded attorney fees to New Star.The Supreme Court of the State of Utah reviewed the case. The court held that New Star’s second preliminary notices, which were specific to Building C, substantially complied with the Construction Lien Statute despite not listing the correct parcel numbers. The court declined to analyze the first preliminary notices. The court also held that New Star’s failure to allocate expenses between the units and the common areas did not invalidate the lien. However, the court found that the district court erred in calculating the amount owed under the lien by treating Dumar as owning all the common areas of Building C, rather than only its ownership share in the development. The court remanded the case for the district court to determine the correct amount Dumar owes based on its ownership share.Additionally, the Supreme Court vacated the district court’s order dismissing Dumar’s excessive lien claim and the attorney fee award for New Star. The court directed the district court to reconsider both issues on remand. View "New Star General Contractors, Inc. v. Dumar" on Justia Law
Arellano v. Sunrise Homes, Inc.
Saul Arellano, a roofer, was injured while working on a construction project for Sunrise Homes, Inc. He fell from a roof without fall protection equipment and sustained multiple injuries. Arellano received worker’s compensation benefits through Sunrise Homes after it was discovered that his direct employer did not carry worker’s compensation insurance. Subsequently, Arellano filed negligence and negligence per se claims against Sunrise Homes, arguing that his injuries fell under the “unprovoked physical aggression” exception to Idaho’s worker’s compensation exclusive remedy rule.The District Court of the Seventh Judicial District, Madison County, granted summary judgment in favor of Sunrise Homes. The court concluded that Arellano failed to provide clear and convincing evidence that his claims fell within the statutory exception to the exclusive remedy rule. Specifically, the court found no genuine issues of material fact that Sunrise Homes knew injury or death was substantially likely to occur due to the lack of fall protection equipment.The Supreme Court of the State of Idaho reviewed the case and affirmed the district court’s decision. The Supreme Court held that the district court erred in applying the “clear and convincing” evidentiary standard at the summary judgment stage. However, upon de novo review, the Supreme Court found that Arellano did not raise a genuine issue of material fact regarding Sunrise Homes’ knowledge that injury was substantially likely to occur. The court also rejected Arellano’s arguments that the 2020 amendments to Idaho Code section 72-209(3) codified a more lenient standard or reduced the burden of proof for plaintiffs. Consequently, the Supreme Court affirmed the district court’s order granting summary judgment to Sunrise Homes and awarded costs on appeal to Sunrise Homes. View "Arellano v. Sunrise Homes, Inc." on Justia Law
Grosvold v. Neely
Neely, acting as his own general contractor, hired Grosvold to perform excavation work on his property under an oral contract. Grosvold worked from April to October 2021, but their relationship deteriorated, and Neely refused to pay for an invoice amounting to $55,858. Neely sent Grosvold a notice of alleged defects in the work, which Grosvold disputed. Grosvold then filed a complaint for breach of contract and prejudgment interest, while Neely counterclaimed for breach of contract, negligence, and construction defect.The District Court of the Third Judicial District in Anaconda-Deer Lodge County tried the case before a jury. The court refused to instruct the jury on Neely’s construction defect and negligence claims, reasoning that the evidence did not substantiate the work was done to a residence and that the case was strictly a breach of contract matter. The jury found Neely had breached the contract and awarded Grosvold $60,512.60 in damages. The court denied Grosvold’s request for prejudgment interest, finding the damages were not certain until the jury’s determination.The Supreme Court of the State of Montana reviewed the case. It affirmed the District Court’s decision not to instruct the jury on the construction defect claim, holding that the residential construction defect statute did not create an independent cause of action beyond breach of contract or tort. The court also affirmed the refusal to instruct the jury on negligence, finding that Neely’s substantial rights were not affected as the breach of contract instructions adequately covered the disputed subject matter. Finally, the court upheld the denial of prejudgment interest, concluding the amount of recovery was not capable of being made certain until the jury’s verdict. View "Grosvold v. Neely" on Justia Law
PNC Bank v. 2013 Travis Oak Creek
The case involves a dispute arising from alleged breaches of a partnership agreement between PNC Bank, N.A., Columbia Housing SLP Corporation (collectively, the "PNC Parties"), and Rene O. Campos, along with 2013 Travis Creek GP, LLC, as general partner. The partnership was formed to acquire, construct, develop, and operate an affordable housing apartment complex in Austin, Texas, with anticipated federal tax credits. A mechanic’s lien was placed on the property, leading to a default on the construction loan. The PNC Parties sought to remove the general partner and replace it with Columbia, resulting in a lawsuit.The PNC Parties filed the lawsuit in the United States District Court for the Western District of Texas, invoking diversity jurisdiction. The district court retained supplemental jurisdiction over the enforcement of the settlement agreement that resolved the 2017 lawsuit. In 2021, the Eureka Parties moved to re-open the case to enforce the settlement agreement, leading to competing motions to enforce. The district court severed the motions from the original lawsuit, creating a new case, and granted each motion in part, offsetting the balance owed. The Eureka Parties and the Partnership appealed.The United States Court of Appeals for the Fifth Circuit reviewed the case and found that the parties failed to establish an independent jurisdictional basis for the severed motions. The court noted that severed claims must have an independent jurisdictional basis and that the record lacked sufficient evidence to establish diversity of citizenship. Consequently, the court remanded the case to the district court for the limited purpose of determining whether such jurisdiction exists. The panel retained jurisdiction over the limited remand. View "PNC Bank v. 2013 Travis Oak Creek" on Justia Law
Palmetto Pointe v. Tri-County Roofing
In 2005, Island Pointe, LLC contracted Complete Building Corporation (CBC) to construct a condominium project, Palmetto Pointe at Peas Island. CBC subcontracted Tri-County Roofing (TCR) for roofing and related work. In 2014-2015, Palmetto discovered construction defects and sued CBC, TCR, and others for negligence and breach of warranty. Palmetto received $6,800,000 in settlements, including $1,000,000 from CBC's insurer for a covenant-not-to-execute and $1,975,000 from four other defendants.The trial began in May 2019, and the jury found CBC and TCR liable for $6,500,000 in actual damages and $500,000 each in punitive damages. The trial court apportioned 5% liability to two other defendants, making CBC and TCR jointly and severally liable for the remaining 90% of actual damages. TCR sought setoff for the $1,000,000 payment and the settlements from the four other defendants. The trial court denied TCR's motion for setoff, except for partial amounts conceded by Palmetto.The South Carolina Supreme Court reviewed the case. It reversed the court of appeals' decision, holding that TCR is entitled to set off the full $1,000,000 paid by CBC's insurer. The court affirmed the lower court's decision regarding the settlements from Novus, Atlantic, H and A, and Cohen's, agreeing that the trial court reasonably allocated the settlement amounts. The case was remanded to the trial court for the calculation of the judgment against TCR. View "Palmetto Pointe v. Tri-County Roofing" on Justia Law
Mid-Century Ins. Co. v. HIVE Construction
HIVE Construction, Inc. served as the general contractor for the construction of Masterpiece Kitchen, a restaurant. The contract required HIVE to follow specific architectural plans, including installing two layers of drywall on a wall separating the kitchen and dining area. Instead, HIVE installed one layer of drywall and one layer of combustible plywood without approval. A fire started within the wall, causing significant damage and forcing the restaurant to close. Mid-Century Insurance Company, as the property insurer and subrogee of Masterpiece Kitchen, paid for the damages and then sued HIVE for negligence, alleging willful and wanton conduct.The district court initially allowed Mid-Century to amend its complaint to include a breach of contract claim but later reversed this decision, requiring Mid-Century to proceed with the negligence claim. At trial, the jury found HIVE's conduct to be willful and wanton, awarding damages to Mid-Century. HIVE appealed, arguing that the economic loss rule barred the negligence claim. The Colorado Court of Appeals agreed, reversing the district court's decision and instructing a verdict in HIVE's favor.The Supreme Court of Colorado reviewed the case and concluded that the economic loss rule does not provide an exception for willful and wanton conduct. The court held that the rule barred Mid-Century's negligence claim because the duty HIVE allegedly breached was not independent of its contractual obligations. Consequently, the court affirmed the judgment of the Colorado Court of Appeals, upholding the application of the economic loss rule to bar the negligence claim. View "Mid-Century Ins. Co. v. HIVE Construction" on Justia Law
Phoenix Insurance Co. v. Wehr Constructors, Inc.
Wehr Constructors, Inc. (Wehr) entered into a contract with St. Claire Medical Center (St. Claire) to build an addition to the hospital. Wehr's performance was allegedly deficient, leading to significant construction defects. St. Claire terminated the contract and sought damages from Wehr's performance-bond carrier, Travelers Casualty and Surety Company (Travelers Surety). Travelers Surety then involved Wehr in the litigation. Wehr sought defense coverage from its insurers: Phoenix Insurance Company (Phoenix), St. Paul Surplus Lines Insurance Company (St. Paul), and Travelers Property Casualty Company of America (Travelers Property).The United States District Court for the Eastern District of Kentucky ruled that none of Wehr’s insurers had a duty to defend Wehr in the lawsuit initiated by St. Claire. The court held that Phoenix’s duty to defend was not triggered because St. Claire did not assert claims directly against Wehr. It also found that St. Paul had no duty to defend because Wehr did not specifically agree to perform as a construction manager, a requirement under the St. Paul policy. Although Wehr did not seek summary judgment against Travelers Property, the court noted that Travelers Property also had no duty to defend for the same reasons as Phoenix.The United States Court of Appeals for the Sixth Circuit reviewed the case. The court affirmed the district court’s decision regarding St. Paul, agreeing that Wehr did not specifically agree to serve as a construction manager. However, it reversed the decision regarding Phoenix, holding that Phoenix had a duty to defend Wehr because the damages alleged by St. Claire potentially fell within the policy coverage, and Wehr was a party to the suit. The court vacated the decision regarding Travelers Property and remanded for further proceedings to determine whether Travelers Property had a duty to defend, given the ambiguity in the district court’s ruling and the stipulation by the parties. View "Phoenix Insurance Co. v. Wehr Constructors, Inc." on Justia Law